22411 W CLARENDON ST 91367

Certificate Information: 22411 W CLARENDON ST 91367

Application / Permit
20010-20000-01725
Plan Check / Job No.
B20VN06926
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 32'-4" X 20'-8" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 12/8/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2020 APPLICANT
Assigned to Plan Check Engineer 6/19/2020 SELLA BENYAMIN
Corrections Issued 6/23/2020 SELLA BENYAMIN
Quality Review Completed 6/24/2020 STEVEN KIM
Building Plans Picked Up 6/24/2020 APPLICANT
Plan Check Approved 10/19/2020 SELLA BENYAMIN
Issued 12/8/2020 APPLICANT
CofO in Progress 5/29/2021 TROY SANDERS
CofO Issued 6/23/2021 JOHN JANSON
Permit Finaled 6/23/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/10/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 8/10/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 8/11/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 9/1/2020 MATTHEW CRAIG
Low Impact Development Cleared 9/7/2020 SELLA BENYAMIN
Roof/Waste drainage to street Cleared 9/9/2020 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 9/18/2020 PATRICK MISCHLICH
GPI Written Notices Cleared 10/19/2020 SELLA BENYAMIN
Hold Cleared 12/15/2020 JASON SHEETS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 12/10/2020 Approved TROY SANDERS
Underground Mechanical 12/10/2020 Approved TROY SANDERS
Footing/Foundation/Slab 12/17/2020 Approved TROY SANDERS
BUILDING-Rough-Frame 1/21/2021 Not Ready for Inspection TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/21/2021 Approved TROY SANDERS
Green Building Rough 1/21/2021 Not Ready for Inspection TROY SANDERS
MERV13>=Rough 1/21/2021 Approved TROY SANDERS
Underground Mechanical 1/21/2021 Approved TROY SANDERS
Verify Sprinkler Sign Off 1/21/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 2/5/2021 Not Ready for Inspection TROY SANDERS
ELECTRICAL-Rough 2/5/2021 Approved TROY SANDERS
Green Building Rough 2/5/2021 Not Ready for Inspection TROY SANDERS
Insulation 2/5/2021 Approved TROY SANDERS
PLUMBING-Rough 2/5/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 2/10/2021 Approved TROY SANDERS
Drywall Nailing 2/10/2021 Approved TROY SANDERS
Green Building Rough 2/10/2021 Approved TROY SANDERS
Interior/Exterior Lathing 2/10/2021 Approved TROY SANDERS
Interior/Exterior Lathing 2/26/2021 Partial Approval TROY SANDERS
Final 5/27/2021 Corrections Issued TROY SANDERS
Green Building Final 5/27/2021 Corrections Issued TROY SANDERS
MERV13>=Final 5/27/2021 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 5/27/2021 SGSOV Approved TROY SANDERS
Service/Power Release 5/27/2021 Approved TROY SANDERS
Smoke Detectors 5/27/2021 Approved TROY SANDERS
Final 5/28/2021 OK to Issue CofO TROY SANDERS
Green Building Final 5/28/2021 Approved TROY SANDERS