Underground Mechanical
|
3/11/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
METHANE-Subgrade
|
3/15/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Excavation/Setback/Form/Re-Bar
|
3/18/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
METHANE-Subgrade
|
3/18/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
METHANE-Barrier
|
3/19/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Deputy Methane Barrier
|
3/22/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Footing/Foundation/Slab
|
3/22/2021
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Excavation/Setback/Form/Re-Bar
|
3/23/2021
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Footing/Foundation/Slab
|
3/24/2021
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
METHANE-Barrier
|
3/24/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
METHANE-Subgrade
|
3/24/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Footing/Foundation/Slab
|
3/26/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Deputy Methane Barrier
|
3/30/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Deputy Methane Barrier
|
3/31/2021
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
METHANE-Barrier
|
4/6/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
METHANE-Subgrade
|
4/6/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Footing/Foundation/Slab
|
4/8/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/22/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
4/27/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/30/2021
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/19/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/26/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/1/2021
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/3/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/17/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
6/18/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/2/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/6/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/26/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/28/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/19/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/27/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/9/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
9/23/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/23/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Underground Mechanical
|
10/15/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/30/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/5/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/7/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/12/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Rough
|
1/18/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Rough
|
2/28/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Rough
|
3/14/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Rough
|
3/14/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Rough
|
3/24/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Rough
|
3/24/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Rough
|
3/30/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/31/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
METHANE-Rough
|
4/1/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Rough
|
4/1/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Rough
|
4/5/2022
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Rough
|
4/5/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
METHANE-Rough
|
4/5/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/13/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/18/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Rough
|
4/18/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
METHANE-Rough
|
4/20/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Rough
|
4/20/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Insulation
|
4/21/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/23/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
5/26/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
5/26/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
6/7/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Rough
|
6/7/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
6/7/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
7/8/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
7/8/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Verify Sprinkler Sign Off
|
7/8/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Insulation
|
7/12/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
7/20/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Interior/Exterior Lathing
|
7/29/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Interior/Exterior Lathing
|
8/2/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Shower Pan
|
9/13/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Interior/Exterior Lathing
|
9/19/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Final
|
2/2/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Underground Mechanical
|
2/16/2023
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Final
|
10/16/2023
|
Not Ready for Inspection
|
BRENDAN MORELLI
|
|
Green Building Final
|
10/16/2023
|
Not Ready for Inspection
|
BRENDAN MORELLI
|
|
SGSOV-Seismic Gas S/O Valve
|
10/16/2023
|
SGSOV Not Ready
|
BRENDAN MORELLI
|
|
Service/Power Release
|
10/16/2023
|
Not Ready for Inspection
|
BRENDAN MORELLI
|
|
Smoke Detectors
|
10/16/2023
|
Not Ready for Inspection
|
BRENDAN MORELLI
|
|
Grounding or Bonding
|
10/17/2023
|
Not Ready for Inspection
|
BRENDAN MORELLI
|
|
ELECTRICAL-Final
|
10/18/2023
|
Partial Approval
|
BRENDAN MORELLI
|
|
PLUMBING-Final
|
10/18/2023
|
Approved
|
BRENDAN MORELLI
|
|
ELECTRICAL-Final
|
10/31/2023
|
Not Ready for Inspection
|
BRENDAN MORELLI
|
|
ELECTRICAL-Final
|
11/1/2023
|
Approved
|
BRENDAN MORELLI
|
|
HVAC-Final
|
11/15/2023
|
Approved
|
BRENDAN MORELLI
|
|
Final
|
12/7/2023
|
Conditional Approval
|
BRENDAN MORELLI
|
|
Green Building Final
|
12/7/2023
|
Approved
|
BRENDAN MORELLI
|
|
SGSOV-Seismic Gas S/O Valve
|
12/7/2023
|
SGSOV Approved
|
BRENDAN MORELLI
|
|
Service/Power Release
|
12/7/2023
|
Approved
|
BRENDAN MORELLI
|
|
Smoke Detectors
|
12/7/2023
|
Approved
|
BRENDAN MORELLI
|
|
Final
|
1/25/2024
|
OK to Issue CofO
|
BRENDAN MORELLI
|