17609 W VANOWEN ST 91406

Certificate Information: 17609 W VANOWEN ST 91406

Application / Permit
20010-20000-01700
Plan Check / Job No.
B20VN06851
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 33'-6" X 28'-3" IRREGULAR SHAPED TWO STORY ACCESSORY DWELLING UNIT WITH RECROOM AND ROOF DECK. SPRINKLER REQUIRED THROUGHOUT. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 6/14/2022
Issuing Office
Current Status
CofO Issued on 10/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2020 APPLICANT
Assigned to Plan Check Engineer 6/11/2020 ARTIN ZARUKIAN
Corrections Issued 6/13/2020 ARTIN ZARUKIAN
Quality Review Completed 6/18/2020 STEVEN KIM
Green Plans Picked Up 6/23/2020 APPLICANT
Applicant returned to address corrections 5/17/2022 ARTIN ZARUKIAN
Applicant returned to address corrections 5/31/2022 ARTIN ZARUKIAN
Plan Check Approved 6/13/2022 ARTIN ZARUKIAN
Issued 6/14/2022 APPLICANT
Building Plans Picked Up 6/16/2022 APPLICANT
CofO in Progress 9/21/2023 JON MCHUGH
Permit Finaled 10/10/2023 JOHN JANSON
CofO Issued 10/10/2023 JOHN JANSON
Permit Finaled 10/10/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/29/2020 JOHN TRIANTAFYLLOS
Permit Cleared 9/29/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 9/30/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 9/30/2020 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 5/17/2022 OSCAR CASTRO
Roof/Waste drainage to street Cleared 5/18/2022 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 7/25/2022 Approved SEAN HAUPT
Special/Order Compliance 7/25/2022 Partial Approval SEAN HAUPT
Excavation/Setback/Form/Re-Bar 7/29/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 7/29/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 8/22/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 10/7/2022 Approved SEAN HAUPT
Deputy Wood Construction 10/21/2022 Conditional Approval MORRIS JACKSON
Interior/Exterior Lathing 11/4/2022 Approved SEAN HAUPT
Rough-Elec/Plmb/HVAC 11/23/2022 No Access for Inspection DAVID SANDOVAL
Underground Mechanical 11/23/2022 No Access for Inspection DAVID SANDOVAL
ELECTRICAL-Rough 12/2/2022 Corrections Issued PETER FOLLING
HVAC-Rough 12/2/2022 Corrections Issued PETER FOLLING
PLUMBING-Rough 12/2/2022 Corrections Issued PETER FOLLING
Verify Sprinkler Sign Off 12/2/2022 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 12/9/2022 Approved SEAN HAUPT
Green Building Rough 12/9/2022 Approved SEAN HAUPT
Rough-Elec/Plmb/HVAC 12/9/2022 Approved SEAN HAUPT
Underground Mechanical 12/9/2022 Not Ready for Inspection SEAN HAUPT
Verify Sprinkler Sign Off 12/9/2022 Approved SEAN HAUPT
Insulation 12/22/2022 Approved JON MCHUGH
Underground Mechanical 12/22/2022 Approved JON MCHUGH
Drywall Nailing 1/3/2023 Approved JON MCHUGH
Interior/Exterior Lathing 1/5/2023 Approved MORRIS JACKSON
Shower Pan 1/5/2023 Approved MORRIS JACKSON
ELECTRICAL-Final 6/27/2023 Corrections Issued JON MCHUGH
Final 6/27/2023 Corrections Issued JON MCHUGH
Green Building Final 6/27/2023 Not Ready for Inspection JON MCHUGH
HVAC-Final 6/27/2023 Not Ready for Inspection JON MCHUGH
PLUMBING-Final 6/27/2023 Partial Approval JON MCHUGH
SGSOV-Seismic Gas S/O Valve 6/27/2023 SGSOV Not Ready JON MCHUGH
Service/Power Release 6/27/2023 Not Ready for Inspection JON MCHUGH
Smoke Detectors 6/27/2023 Corrections Issued JON MCHUGH
ELECTRICAL-Final 7/10/2023 Corrections Issued JON MCHUGH
Final 7/10/2023 Corrections Issued JON MCHUGH
Green Building Final 7/10/2023 Not Ready for Inspection JON MCHUGH
HVAC-Final 7/10/2023 Not Ready for Inspection JON MCHUGH
PLUMBING-Final 7/10/2023 Corrections Issued JON MCHUGH
SGSOV-Seismic Gas S/O Valve 7/10/2023 SGSOV Not Ready JON MCHUGH
Service/Power Release 7/10/2023 Not Ready for Inspection JON MCHUGH
Smoke Detectors 7/10/2023 Approved JON MCHUGH
Final 8/14/2023 Corrections Issued JON MCHUGH
Green Building Final 8/14/2023 Not Ready for Inspection JON MCHUGH
SGSOV-Seismic Gas S/O Valve 8/14/2023 SGSOV Not Ready JON MCHUGH
Service/Power Release 8/14/2023 Not Ready for Inspection JON MCHUGH
Final 8/22/2023 Corrections Issued JON MCHUGH
Green Building Final 8/22/2023 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 8/22/2023 SGSOV Not Ready JON MCHUGH
Service/Power Release 8/22/2023 Not Ready for Inspection JON MCHUGH
Final 9/14/2023 Corrections Issued JON MCHUGH
SGSOV-Seismic Gas S/O Valve 9/14/2023 SGSOV Approved JON MCHUGH
Service/Power Release 9/14/2023 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Final 9/20/2023 Approved JON MCHUGH
Final 9/20/2023 OK to Issue CofO JON MCHUGH
HVAC-Final 9/20/2023 Approved JON MCHUGH
PLUMBING-Final 9/20/2023 Approved JON MCHUGH
Service/Power Release 9/20/2023 Approved JON MCHUGH