17609 W VANOWEN ST 91406
Certificate Information: 17609 W VANOWEN ST 91406
- Application / Permit
- 20010-20000-01700
- Plan Check / Job No.
- B20VN06851
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 33'-6" X 28'-3" IRREGULAR SHAPED TWO STORY ACCESSORY DWELLING UNIT WITH RECROOM AND ROOF DECK. SPRINKLER REQUIRED THROUGHOUT. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
- Permit Issued
- Issued on 6/14/2022
- Issuing Office
- Current Status
- CofO Issued on 10/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2020 | ARTIN ZARUKIAN |
| Corrections Issued | 6/13/2020 | ARTIN ZARUKIAN |
| Quality Review Completed | 6/18/2020 | STEVEN KIM |
| Green Plans Picked Up | 6/23/2020 | APPLICANT |
| Applicant returned to address corrections | 5/17/2022 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 5/31/2022 | ARTIN ZARUKIAN |
| Plan Check Approved | 6/13/2022 | ARTIN ZARUKIAN |
| Issued | 6/14/2022 | APPLICANT |
| Building Plans Picked Up | 6/16/2022 | APPLICANT |
| CofO in Progress | 9/21/2023 | JON MCHUGH |
| Permit Finaled | 10/10/2023 | JOHN JANSON |
| CofO Issued | 10/10/2023 | JOHN JANSON |
| Permit Finaled | 10/10/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/29/2020 | JOHN TRIANTAFYLLOS |
| Permit | Cleared | 9/29/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 9/30/2020 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 5/17/2022 | OSCAR CASTRO |
| Roof/Waste drainage to street | Cleared | 5/18/2022 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 7/25/2022 | Approved | SEAN HAUPT |
| Special/Order Compliance | 7/25/2022 | Partial Approval | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 7/29/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 7/29/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2022 | Approved | SEAN HAUPT |
| Deputy Wood Construction | 10/21/2022 | Conditional Approval | MORRIS JACKSON |
| Interior/Exterior Lathing | 11/4/2022 | Approved | SEAN HAUPT |
| Rough-Elec/Plmb/HVAC | 11/23/2022 | No Access for Inspection | DAVID SANDOVAL |
| Underground Mechanical | 11/23/2022 | No Access for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Rough | 12/2/2022 | Corrections Issued | PETER FOLLING |
| HVAC-Rough | 12/2/2022 | Corrections Issued | PETER FOLLING |
| PLUMBING-Rough | 12/2/2022 | Corrections Issued | PETER FOLLING |
| Verify Sprinkler Sign Off | 12/2/2022 | Not Ready for Inspection | PETER FOLLING |
| BUILDING-Rough-Frame | 12/9/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 12/9/2022 | Approved | SEAN HAUPT |
| Rough-Elec/Plmb/HVAC | 12/9/2022 | Approved | SEAN HAUPT |
| Underground Mechanical | 12/9/2022 | Not Ready for Inspection | SEAN HAUPT |
| Verify Sprinkler Sign Off | 12/9/2022 | Approved | SEAN HAUPT |
| Insulation | 12/22/2022 | Approved | JON MCHUGH |
| Underground Mechanical | 12/22/2022 | Approved | JON MCHUGH |
| Drywall Nailing | 1/3/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 1/5/2023 | Approved | MORRIS JACKSON |
| Shower Pan | 1/5/2023 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 6/27/2023 | Corrections Issued | JON MCHUGH |
| Final | 6/27/2023 | Corrections Issued | JON MCHUGH |
| Green Building Final | 6/27/2023 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Final | 6/27/2023 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Final | 6/27/2023 | Partial Approval | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 6/27/2023 | SGSOV Not Ready | JON MCHUGH |
| Service/Power Release | 6/27/2023 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 6/27/2023 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Final | 7/10/2023 | Corrections Issued | JON MCHUGH |
| Final | 7/10/2023 | Corrections Issued | JON MCHUGH |
| Green Building Final | 7/10/2023 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Final | 7/10/2023 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Final | 7/10/2023 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 7/10/2023 | SGSOV Not Ready | JON MCHUGH |
| Service/Power Release | 7/10/2023 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 7/10/2023 | Approved | JON MCHUGH |
| Final | 8/14/2023 | Corrections Issued | JON MCHUGH |
| Green Building Final | 8/14/2023 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 8/14/2023 | SGSOV Not Ready | JON MCHUGH |
| Service/Power Release | 8/14/2023 | Not Ready for Inspection | JON MCHUGH |
| Final | 8/22/2023 | Corrections Issued | JON MCHUGH |
| Green Building Final | 8/22/2023 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 8/22/2023 | SGSOV Not Ready | JON MCHUGH |
| Service/Power Release | 8/22/2023 | Not Ready for Inspection | JON MCHUGH |
| Final | 9/14/2023 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 9/14/2023 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 9/14/2023 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 9/20/2023 | Approved | JON MCHUGH |
| Final | 9/20/2023 | OK to Issue CofO | JON MCHUGH |
| HVAC-Final | 9/20/2023 | Approved | JON MCHUGH |
| PLUMBING-Final | 9/20/2023 | Approved | JON MCHUGH |
| Service/Power Release | 9/20/2023 | Approved | JON MCHUGH |