5000-5000 1/2 N CLEON AVE 91601

Certificate Information: 5000-5000 1/2 N CLEON AVE 91601

Application / Permit
20010-20000-01696
Plan Check / Job No.
B20VN06846
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
TWO FAMILY 2 STORY DWELLING ( 40'-0"X44'-1") ( BUILDING 1)_ WITH ROOF DECK FULLEY SPRINKLERED
Permit Issued
Issued on 2/24/2021
Issuing Office
Current Status
CofO Issued on 12/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/28/2020 APPLICANT
Assigned to Plan Check Engineer 6/26/2020 MOHAMMAD ESMAILI
Corrections Issued 6/30/2020 MOHAMMAD ESMAILI
Quality Review Completed 7/2/2020 OMID HEDAYAT
Building Plans Picked Up 7/7/2020 APPLICANT
Applicant returned to address corrections 10/26/2020 MOHAMMAD ESMAILI
Plan Check Approved 2/1/2021 MOHAMMAD ESMAILI
Issued 2/24/2021 APPLICANT
CofO in Progress 8/23/2024 ROBERTO PALACIOS-LOPEZ
CofO in Progress 8/30/2024 JUAN VALENZUELA
No Progress 8/30/2024 JUAN VALENZUELA
CofO in Progress 12/4/2024 ROBERTO PALACIOS-LOPEZ
Permit Finaled 12/24/2024 RUBEN SALAS
CofO Issued 12/24/2024 RUBEN SALAS
Permit Finaled 12/24/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/27/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 7/28/2020 ADRIAN CASTRO
Sewer availability Cleared 7/28/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 8/5/2020 KURT CORRAL
Trees in Parkway Cleared 8/20/2020 JOHN KIM
Highway dedication Cleared 10/1/2020 ADRIAN CASTRO
Low Impact Development Cleared 12/9/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 12/15/2020 ADRIAN CASTRO
Permit Cleared 12/29/2020 ADRIAN CASTRO
Frnt yard landscape/Water mgmt Cleared 1/21/2021 MIGUEL GAMBOA
Construction near power lines Cleared 1/26/2021 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/12/2021 Approved DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 7/14/2021 Partial Approval ARAM AVEDISIAN
Insulation 12/8/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Wood Frame 12/8/2021 Corrections Issued CHRISTOPHE COCHRAN
Drywall Nailing 12/17/2021 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Rough 12/22/2021 Approved MATT KELLERMAN
HVAC-Rough 12/22/2021 Approved MATT KELLERMAN
Insulation 12/22/2021 Approved MATT KELLERMAN
PLUMBING-Rough 12/22/2021 Approved MATT KELLERMAN
Special/Order Compliance 3/18/2024 Approved JOHN HAYES
BUILDING-Rough-Frame 7/8/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 7/8/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 7/8/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 7/8/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 7/8/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Rough 7/8/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Final 7/8/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 7/8/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 7/8/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 7/8/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 7/8/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 7/8/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 7/15/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 7/15/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 7/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 7/15/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Gas Test 7/15/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 7/15/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Rough 7/15/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Final 7/15/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 7/15/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 7/15/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 7/15/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 7/15/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 7/15/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 7/22/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 7/22/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 7/22/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 7/22/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 7/22/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 7/22/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Rough 7/22/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Final 7/22/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 7/22/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 7/22/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 7/22/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 7/22/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 7/22/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 7/30/2024 Partial Inspection JOSE AVILA
BUILDING-Rough-Frame 8/8/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 8/8/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 8/8/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 8/8/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Green Building Final 8/8/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 8/8/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 8/8/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 8/8/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 8/8/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 8/8/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 8/8/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 8/8/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 8/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 8/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 8/15/2024 Approved ROBERTO PALACIOS-LOPEZ
Gas Test 8/15/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 8/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 8/15/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 8/15/2024 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 8/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 8/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/23/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 8/23/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 8/23/2024 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
HVAC-Final 8/23/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 8/23/2024 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 8/23/2024 Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 8/23/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 8/30/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 12/4/2024 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Service/Power Release 12/4/2024 Approved ROBERTO PALACIOS-LOPEZ