5000-5000 1/2 N CLEON AVE 91601
Certificate Information: 5000-5000 1/2 N CLEON AVE 91601
- Application / Permit
- 20010-20000-01696
- Plan Check / Job No.
- B20VN06846
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- TWO FAMILY 2 STORY DWELLING ( 40'-0"X44'-1") ( BUILDING 1)_ WITH ROOF DECK FULLEY SPRINKLERED
- Permit Issued
- Issued on 2/24/2021
- Issuing Office
- Current Status
- CofO Issued on 12/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 6/30/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 7/2/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 7/7/2020 | APPLICANT |
| Applicant returned to address corrections | 10/26/2020 | MOHAMMAD ESMAILI |
| Plan Check Approved | 2/1/2021 | MOHAMMAD ESMAILI |
| Issued | 2/24/2021 | APPLICANT |
| CofO in Progress | 8/23/2024 | ROBERTO PALACIOS-LOPEZ |
| CofO in Progress | 8/30/2024 | JUAN VALENZUELA |
| No Progress | 8/30/2024 | JUAN VALENZUELA |
| CofO in Progress | 12/4/2024 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 12/24/2024 | RUBEN SALAS |
| CofO Issued | 12/24/2024 | RUBEN SALAS |
| Permit Finaled | 12/24/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/27/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 7/28/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 8/5/2020 | KURT CORRAL |
| Trees in Parkway | Cleared | 8/20/2020 | JOHN KIM |
| Highway dedication | Cleared | 10/1/2020 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 12/9/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 12/15/2020 | ADRIAN CASTRO |
| Permit | Cleared | 12/29/2020 | ADRIAN CASTRO |
| Frnt yard landscape/Water mgmt | Cleared | 1/21/2021 | MIGUEL GAMBOA |
| Construction near power lines | Cleared | 1/26/2021 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | , ; Lic. No.: C61464 | 6701 CORIE LN WEST HILLS, CA 91307 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/12/2021 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2021 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 12/8/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Wood Frame | 12/8/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| Drywall Nailing | 12/17/2021 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 12/22/2021 | Approved | MATT KELLERMAN |
| HVAC-Rough | 12/22/2021 | Approved | MATT KELLERMAN |
| Insulation | 12/22/2021 | Approved | MATT KELLERMAN |
| PLUMBING-Rough | 12/22/2021 | Approved | MATT KELLERMAN |
| Special/Order Compliance | 3/18/2024 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 7/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 7/8/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 7/8/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 7/8/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 7/8/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 7/8/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 7/8/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 7/8/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 7/8/2024 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 7/8/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 7/8/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 7/8/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 7/15/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 7/15/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 7/15/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 7/15/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 7/15/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 7/15/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 7/15/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 7/15/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 7/15/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 7/15/2024 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 7/15/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 7/15/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 7/15/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 7/22/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 7/22/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 7/22/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 7/22/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 7/22/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 7/22/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 7/22/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 7/22/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 7/22/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 7/22/2024 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 7/22/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 7/22/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 7/22/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 7/30/2024 | Partial Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 8/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 8/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 8/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 8/8/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 8/8/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 8/8/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 8/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 8/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 8/8/2024 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 8/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 8/8/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 8/8/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/15/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 8/15/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 8/15/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 8/15/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 8/15/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 8/15/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 8/15/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 8/15/2024 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 8/15/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 8/15/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/23/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 8/23/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 8/23/2024 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 8/23/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 8/23/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 8/23/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 8/23/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 8/30/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 12/4/2024 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 12/4/2024 | Approved | ROBERTO PALACIOS-LOPEZ |