7507 N YARMOUTH AVE 91335

Certificate Information: 7507 N YARMOUTH AVE 91335

Application / Permit
20010-20000-01673
Plan Check / Job No.
B20VN06736
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 37' X 23'-3" 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d). FIRE SPRINKLER REQUIRED NFPA-13D. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISION.
Permit Issued
Issued on 8/12/2021
Issuing Office
Current Status
CofO Issued on 6/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2020 APPLICANT
Assigned to Plan Check Engineer 6/11/2020 SERGIO MUNIZ
Corrections Issued 6/15/2020 SERGIO MUNIZ
Quality Review Completed 6/26/2020 OMID HEDAYAT
Applicant returned to address corrections 10/9/2020 SERGIO MUNIZ
Applicant returned to address corrections 6/10/2021 SERGIO MUNIZ
Plan Check Approved 7/28/2021 SERGIO MUNIZ
Building Plans Picked Up 8/6/2021 APPLICANT
Issued 8/12/2021 APPLICANT
CofO in Progress 6/21/2022 VINCENT HANLEY
CofO Issued 6/30/2022 MICHAEL SMITH
Permit Finaled 6/30/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/18/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/21/2020 ADRIAN CASTRO
Sewer availability Cleared 3/25/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 4/27/2021 MATTHEW CRAIG
Low Impact Development Cleared 4/27/2021 ANDRES COVARRUBIAS
Construction near power lines Cleared 6/10/2021 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 7/15/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: C89103 1010 RALEIGH ST   APT 107    , CA

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/15/2021 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 9/15/2021 Not Ready for Inspection VINCENT HANLEY
Footing/Foundation/Slab 9/21/2021 Not Ready for Inspection RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 10/26/2021 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 12/21/2021 Approved VINCENT HANLEY
HVAC-Rough 12/21/2021 Approved VINCENT HANLEY
PLUMBING-Rough 12/21/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 12/27/2021 Approved VINCENT HANLEY
Green Building Rough 12/27/2021 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 12/27/2021 Approved VINCENT HANLEY
Insulation 1/5/2022 Conditional Approval JUSTIN HAWLEY
Interior/Exterior Lathing 1/5/2022 Not Ready for Inspection JUSTIN HAWLEY
Insulation 1/6/2022 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 1/6/2022 Not Ready for Inspection JUSTIN HAWLEY
Drywall Nailing 1/13/2022 Approved JUSTIN HAWLEY
Insulation 1/13/2022 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 1/13/2022 Approved JUSTIN HAWLEY
ELECTRICAL-Rough 5/9/2022 Approved VINCENT HANLEY
Final 5/9/2022 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 5/9/2022 Approved VINCENT HANLEY
Green Building Final 5/9/2022 Approved VINCENT HANLEY
HVAC-Final 5/9/2022 Approved VINCENT HANLEY
PLUMBING-Final 5/9/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/9/2022 SGSOV Approved VINCENT HANLEY
Service/Power Release 5/9/2022 Approved VINCENT HANLEY
Smoke Detectors 5/9/2022 Approved VINCENT HANLEY
Final 5/23/2022 Corrections Issued VINCENT HANLEY
ELECTRICAL-Final 6/21/2022 Approved VINCENT HANLEY
Final 6/21/2022 OK to Issue CofO VINCENT HANLEY
Service/Power Release 6/21/2022 Approved VINCENT HANLEY