14926 W SEPTO ST 91345

Certificate Information: 14926 W SEPTO ST 91345

Application / Permit
20010-20000-01653
Plan Check / Job No.
B20VN06686
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
TWO STORY ACCESSORY DWELLING UNT PER LAMC 12.22 A.33(c) and (d) (20'-0"X27'-6") fire sprinklers NFPA-13D
Permit Issued
Issued on 1/11/2022
Issuing Office
Current Status
CofO Issued on 10/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2020 APPLICANT
Assigned to Plan Check Engineer 6/11/2020 MOHAMMAD ESMAILI
Corrections Issued 6/13/2020 MOHAMMAD ESMAILI
Quality Review Completed 6/26/2020 OMID HEDAYAT
Building Plans Picked Up 7/2/2020 APPLICANT
Green Plans Picked Up 7/2/2020 APPLICANT
Applicant returned to address corrections 8/28/2020 MOHAMMAD ESMAILI
Applicant returned to address corrections 9/13/2021 MOHAMMAD ESMAILI
Applicant returned to address corrections 9/15/2021 MOHAMMAD ESMAILI
Plan Check Approved 12/6/2021 MOHAMMAD ESMAILI
Issued 1/11/2022 APPLICANT
CofO in Progress 10/17/2025 JENNIFER RABUCHIN
Permit Finaled 10/24/2025 RUBEN SALAS
CofO Issued 10/24/2025 RUBEN SALAS
Permit Finaled 10/24/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/27/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 8/4/2020 ABDULLAH SADOZAI
Sewer availability Cleared 8/4/2020 ABDULLAH SADOZAI
Hydrant and Access approval Cleared 9/25/2020 GILBERT URREA
Construction near power lines Cleared 10/4/2020 RIDWAN HARDY
Low Impact Development Cleared 6/17/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 6/18/2021 ADRIAN CASTRO

Contact Information

Architect Woodcraft,, Lawrence Albert; Lic. No.: C23651 20812 VENTURA BLVD, STE 205      WOODLAND HILLS, CA 91364
Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/6/2022 Partial Approval JENNIFER RABUCHIN
Deputy Drilled-In Anchors 4/7/2022 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 4/11/2022 Partial Approval DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 4/12/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/4/2022 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 6/10/2022 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 6/29/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 7/5/2022 Corrections Issued MATT KELLERMAN
PLUMBING-Rough 7/19/2022 Conditional Approval DEANDRE HOFFMAN
BUILDING-Rough-Frame 9/21/2022 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 9/21/2022 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 12/20/2022 Not Ready for Inspection JENNIFER RABUCHIN
Interior/Exterior Lathing 12/20/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 1/3/2023 Approved JENNIFER RABUCHIN
HVAC-Rough 1/10/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 1/18/2023 Not Ready for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 1/20/2023 Corrections Issued JOHN COLEMAN
HVAC-Rough 1/20/2023 Corrections Issued JOHN COLEMAN
BUILDING-Rough-Frame 3/7/2023 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 3/7/2023 Approved JENNIFER RABUCHIN
Insulation 3/7/2023 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 3/7/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 3/22/2023 Approved JENNIFER RABUCHIN
Shower Pan 4/28/2023 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 5/8/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/18/2023 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/14/2024 Approved JENNIFER RABUCHIN
Final 11/14/2024 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 11/14/2024 Approved JENNIFER RABUCHIN
Green Building Final 11/14/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/14/2024 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 11/14/2024 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 11/14/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 9/3/2025 Approved NICHOLAS TROWBRIDGE
Final 9/3/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 9/3/2025 Approved NICHOLAS TROWBRIDGE
HVAC-Final 9/3/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Final 9/3/2025 Approved NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 9/3/2025 SGSOV Approved NICHOLAS TROWBRIDGE
Service/Power Release 9/3/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Final 10/10/2025 OK to Issue CofO JENNIFER RABUCHIN
Service/Power Release 10/10/2025 Approved JENNIFER RABUCHIN