9943 N LOUISE AVE 91325
Certificate Information: 9943 N LOUISE AVE 91325
- Application / Permit
- 20010-20000-01619
- Plan Check / Job No.
- B20VN06623
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-STORY ACCESSORY DWELLING UNIT PER ENG'R DESIGN
- Permit Issued
- Issued on 4/7/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 6/11/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 6/11/2020 | STEVEN KIM |
| Building Plans Picked Up | 6/16/2020 | APPLICANT |
| Green Plans Picked Up | 6/16/2020 | APPLICANT |
| Plan Check Approved | 2/23/2021 | NILOOFAR MEHRAIN |
| Issued | 4/7/2021 | APPLICANT |
| CofO in Progress | 4/21/2023 | JAVIER RAMOS JR |
| CofO Issued | 4/25/2023 | MICHAEL SMITH |
| Permit Finaled | 4/25/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/25/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/26/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 7/29/2020 | KURT CORRAL |
| Construction near power lines | Cleared | 11/10/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/10/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 1/13/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 1/19/2021 | GUILLERMO PETRA |
| Green Code | Cleared | 2/23/2021 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/6/2021 | Partial Approval | MARK JOHNSON |
| Footing/Foundation/Slab | 9/10/2021 | Approved | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2021 | Partial Approval | RAUL OLAGI |
| Deputy Wood Construction | 10/19/2021 | Conditional Approval | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2021 | Partial Approval | MARK JOHNSON |
| Wood Frame | 11/2/2021 | Partial Approval | MARK JOHNSON |
| ELECTRICAL-Final | 12/21/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 12/21/2021 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 12/21/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 12/21/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2021 | Partial Approval | MICHEL ABAJAN |
| Gas Test | 12/29/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/29/2021 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/5/2022 | Corrections Issued | MARK JOHNSON |
| Interior/Exterior Lathing | 1/5/2022 | Approved | MARK JOHNSON |
| ELECTRICAL-Rough | 2/18/2022 | Corrections Issued | VINCENT HANLEY |
| HVAC-Rough | 2/18/2022 | Corrections Issued | VINCENT HANLEY |
| Wood Frame | 2/18/2022 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/2/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 3/2/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Rough | 3/2/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 3/2/2022 | Corrections Issued | RAUL OLAGI |
| Verify Sprinkler Sign Off | 3/2/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 4/11/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 4/11/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 4/11/2022 | Approved | RAUL OLAGI |
| Insulation | 4/21/2022 | Corrections Issued | JAVIER RAMOS JR |
| Insulation | 4/26/2022 | Approved | MICHAEL TEMPLE |
| Drywall Nailing | 6/29/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/29/2022 | Approved | JAVIER RAMOS JR |
| Shower Pan | 6/29/2022 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 6/29/2022 | Partial Approval | JAVIER RAMOS JR |
| Underground Mechanical | 9/12/2022 | Approved | JAVIER RAMOS JR |
| Final | 3/10/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 3/10/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 3/10/2023 | SGSOV Not Ready | JAVIER RAMOS JR |
| Service/Power Release | 3/10/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 3/10/2023 | Approved | JAVIER RAMOS JR |
| Final | 4/20/2023 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 4/20/2023 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/20/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 4/20/2023 | Approved | JAVIER RAMOS JR |