4775 N YARMOUTH AVE 91316

Certificate Information: 4775 N YARMOUTH AVE 91316

Application / Permit
20010-20000-01566
Plan Check / Job No.
B20VN06576
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY SFD AND ATTACHED GARAGE ( 66'-3"X75'-2") FULLY SPRINKLERS NFPA-13D
Permit Issued
Issued on 2/5/2021
Issuing Office
Current Status
CofO Issued on 3/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2020 APPLICANT
Assigned to Plan Check Engineer 6/4/2020 MOHAMMAD ESMAILI
Corrections Issued 6/8/2020 MOHAMMAD ESMAILI
Quality Review Completed 6/23/2020 OMID HEDAYAT
Building Plans Picked Up 6/24/2020 APPLICANT
Green Plans Picked Up 6/24/2020 APPLICANT
Applicant returned to address corrections 7/6/2020 MOHAMMAD ESMAILI
Applicant returned to address corrections 11/16/2020 MOHAMMAD ESMAILI
Plan Check Approved 1/20/2021 MOHAMMAD ESMAILI
Issued 2/5/2021 APPLICANT
CofO in Progress 2/28/2023 DAVID SANDOVAL
CofO Issued 3/29/2023 MICHAEL SMITH
Permit Finaled 3/29/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/16/2020 GUILLERMO PETRA
Permit Cleared 10/16/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 10/20/2020 GUILLERMO PETRA
Sewer availability Cleared 10/20/2020 GUILLERMO PETRA
Trees in Parkway Cleared 10/27/2020 JOHN KIM
Hydrant and Access approval Cleared 11/19/2020 MATTHEW CRAIG
Low Impact Development Cleared 1/4/2021 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 1/5/2021 GUILLERMO PETRA
GPI Written Notices Cleared 1/20/2021 MOHAMMAD ESMAILI
Grading Pre-Inspection Cleared 1/20/2021 MOHAMMAD ESMAILI

Contact Information

Contractor Owner-Builder       ,
Engineer Pirbadian,, Amir; Lic. No.: C72413 5435 BALBOA BLVD 214      ENCINO, CA 91342

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/22/2021 Conditional Approval DAVID SANDOVAL
Excavation/Setback/Form/Re-Bar 5/5/2021 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 5/5/2021 Not Ready for Inspection DAVID SANDOVAL
Footing/Foundation/Slab 5/10/2021 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 5/20/2021 Partial Approval DAVID SANDOVAL
PLUMBING-Rough 6/8/2021 Approved DAVID SANDOVAL
Deputy Wood Construction 6/15/2021 Conditional Approval DAVID SANDOVAL
ELECTRICAL-Rough 6/17/2021 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Rough 6/22/2021 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 6/22/2021 Approved DAVID SANDOVAL
HVAC-Rough 6/30/2021 Corrections Issued DAVID SANDOVAL
Shower Pan 6/30/2021 Approved DAVID SANDOVAL
Interior/Exterior Lathing 7/16/2021 Approved RYAN SALAZAR
BUILDING-Rough-Frame 8/5/2021 Approved DAVID SANDOVAL
Green Building Rough 8/5/2021 Approved DAVID SANDOVAL
HVAC-Rough 8/5/2021 Approved DAVID SANDOVAL
Insulation 8/5/2021 Approved DAVID SANDOVAL
Verify Sprinkler Sign Off 8/5/2021 Approved DAVID SANDOVAL
Drywall Nailing 8/13/2021 Approved DAVID SANDOVAL
Pre-Inspection 1/20/2022 Approved DAVID SANDOVAL
ELECTRICAL-Final 2/23/2022 Approved DAVID SANDOVAL
HVAC-Final 2/23/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Final 2/23/2022 Approved DAVID SANDOVAL
Gas Test 3/8/2022 Approved DAVID SANDOVAL
HVAC-Final 3/8/2022 Approved DAVID SANDOVAL
Final 2/27/2023 OK to Issue CofO DAVID SANDOVAL
Green Building Final 2/27/2023 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 2/27/2023 SGSOV Approved DAVID SANDOVAL
Service/Power Release 2/27/2023 Approved DAVID SANDOVAL
Smoke Detectors 2/27/2023 Approved DAVID SANDOVAL