6251 N ALLOTT AVE 91401
Certificate Information: 6251 N ALLOTT AVE 91401
- Application / Permit
- 20010-20000-01560
- Plan Check / Job No.
- B20VN06520
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 31'-6" X 21' 1-STORY ACCESSORY DWELLING UNIT. (N) 8' X 21' PATIO COVER ATTACHED TO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 4/20/2021
- Issuing Office
- Current Status
- CofO Issued on 11/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2020 | SERGIO MUNIZ |
| Corrections Issued | 6/16/2020 | SERGIO MUNIZ |
| Quality Review Completed | 6/19/2020 | OMID HEDAYAT |
| Green Plans Picked Up | 6/24/2020 | APPLICANT |
| Applicant returned to address corrections | 3/7/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 3/31/2021 | SERGIO MUNIZ |
| Plan Check Approved | 4/20/2021 | SERGIO MUNIZ |
| Issued | 4/20/2021 | APPLICANT |
| Building Plans Picked Up | 4/21/2021 | APPLICANT |
| CofO in Progress | 8/20/2024 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 11/18/2024 | DANIEL ORRANTE |
| CofO Issued | 11/18/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/18/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/24/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 7/7/2020 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 12/3/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 12/15/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 1/21/2021 | JEREMY CARTER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | , ; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/10/2021 | Approved | RICHARD DOCKUS |
| Sewer | 6/10/2021 | Approved | RICHARD DOCKUS |
| Underground Mechanical | 6/10/2021 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 6/21/2021 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 7/22/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 8/23/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Rough | 8/23/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 8/23/2021 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 10/13/2021 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 10/13/2021 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/19/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 10/19/2021 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 10/19/2021 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 10/19/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Rough | 1/19/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 1/19/2022 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Rough | 1/21/2022 | Approved | JACK KARGODORIAN |
| Wood Frame | 1/21/2022 | Corrections Issued | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 1/27/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Insulation | 1/27/2022 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 1/27/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 1/27/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Insulation | 2/25/2022 | Partial Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 2/25/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Wood Frame | 2/25/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 3/17/2022 | Approved | MATT KELLERMAN |
| Wood Frame | 3/17/2022 | Approved | MATT KELLERMAN |
| Drywall Nailing | 4/6/2022 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 4/6/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 4/21/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 4/25/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 4/27/2022 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 6/16/2022 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Final | 6/16/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Interior/Exterior Lathing | 6/16/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 6/16/2022 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/13/2022 | Approved | RAFAEL CORTES |
| ELECTRICAL-Final | 7/13/2022 | Corrections Issued | RAFAEL CORTES |
| Final | 7/13/2022 | Corrections Issued | RAFAEL CORTES |
| Green Building Final | 7/13/2022 | Not Ready for Inspection | RAFAEL CORTES |
| HVAC-Final | 7/13/2022 | Not Ready for Inspection | RAFAEL CORTES |
| PLUMBING-Final | 7/13/2022 | Corrections Issued | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 7/13/2022 | SGSOV Not Ready | RAFAEL CORTES |
| Service/Power Release | 7/13/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Smoke Detectors | 7/13/2022 | Approved | RAFAEL CORTES |
| Final | 8/4/2022 | Corrections Issued | RAFAEL CORTES |
| Green Building Final | 8/4/2022 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 8/4/2022 | SGSOV Not Ready | RAFAEL CORTES |
| Service/Power Release | 8/4/2022 | Not Ready for Inspection | RAFAEL CORTES |
| ELECTRICAL-Final | 8/22/2022 | Approved | RAFAEL CORTES |
| Final | 8/22/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 8/22/2022 | Corrections Issued | RAFAEL CORTES |
| HVAC-Final | 8/22/2022 | Approved | RAFAEL CORTES |
| PLUMBING-Final | 8/22/2022 | Approved | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 8/22/2022 | SGSOV Not Ready | RAFAEL CORTES |
| Service/Power Release | 8/22/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 8/29/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 8/29/2022 | Approved | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 8/29/2022 | SGSOV Approved | RAFAEL CORTES |
| Final | 6/21/2024 | Corrections Issued | JOSE AVILA |
| Service/Power Release | 6/21/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 6/25/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 6/25/2024 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 6/25/2024 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 8/13/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 8/19/2024 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 8/19/2024 | Approved | ROBERTO PALACIOS-LOPEZ |