23055 1/2 W STRATHERN ST 91304
Certificate Information: 23055 1/2 W STRATHERN ST 91304
- Application / Permit
- 20010-20000-01552
- Plan Check / Job No.
- B20VN06500
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 25' X 19'-11" DETACHED ACCESSORY DWELLING UNIT. ALL WORK PER WFPP.
- Permit Issued
- Issued on 1/19/2021
- Issuing Office
- Current Status
- CofO Issued on 6/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2020 | RAPHAEL ROSAS |
| Corrections Issued | 6/17/2020 | RAPHAEL ROSAS |
| Building Plans Picked Up | 6/24/2020 | APPLICANT |
| Applicant returned to address corrections | 9/29/2020 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 10/14/2020 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 10/30/2020 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 12/22/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 1/4/2021 | RAPHAEL ROSAS |
| Issued | 1/19/2021 | APPLICANT |
| CofO in Progress | 6/27/2022 | STEVEN BACK |
| Permit Finaled | 6/28/2022 | JOHN JANSON |
| CofO Issued | 6/28/2022 | JOHN JANSON |
| Permit Finaled | 6/28/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/6/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 8/6/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 8/27/2020 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 9/11/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/16/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Sewer | 2/16/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Special/Order Compliance | 2/16/2021 | Corrections Issued | DAVID STEPANYAN |
| Footing/Foundation/Slab | 1/10/2022 | Corrections Issued | PETER FOLLING |
| Sewer | 1/10/2022 | Not Ready for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 1/24/2022 | Approved | PETER FOLLING |
| PLUMBING-Rough | 1/24/2022 | Partial Approval | PETER FOLLING |
| Sewer | 1/24/2022 | Approved | PETER FOLLING |
| ELECTRICAL-Rough | 3/3/2022 | Approved | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2022 | Partial Approval | PETER FOLLING |
| HVAC-Rough | 3/3/2022 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 3/3/2022 | Approved | PETER FOLLING |
| Rough-Elec/Plmb/HVAC | 3/3/2022 | Not Ready for Inspection | PETER FOLLING |
| Wood Frame | 3/3/2022 | Not Ready for Inspection | PETER FOLLING |
| BUILDING-Rough-Frame | 3/17/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 3/17/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Rough | 3/17/2022 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 3/17/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 3/17/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Wood Frame | 3/17/2022 | Approved | CHRIS CHRISTENSEN |
| Insulation | 5/10/2022 | Approved | JESUS PINEDA |
| Green Building Rough | 5/13/2022 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 5/13/2022 | Approved | JESUS PINEDA |
| Shower Pan | 5/13/2022 | Approved | JESUS PINEDA |
| Deputy Drilled-In Anchors | 5/18/2022 | Conditional Approval | JUSTIN HAWLEY |
| Drywall Nailing | 5/18/2022 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 6/17/2022 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 6/17/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 6/17/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 6/17/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 6/17/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 6/17/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 6/17/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 6/17/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 6/17/2022 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 6/17/2022 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 6/27/2022 | Approved | STEVEN BACK |
| Final | 6/27/2022 | OK to Issue CofO | STEVEN BACK |
| Green Building Final | 6/27/2022 | Approved | STEVEN BACK |
| HVAC-Final | 6/27/2022 | Approved | STEVEN BACK |
| PLUMBING-Final | 6/27/2022 | Approved | STEVEN BACK |
| Service/Power Release | 6/27/2022 | Approved | STEVEN BACK |