19515 W SHIRLEY CT 91356

Certificate Information: 19515 W SHIRLEY CT 91356

Application / Permit
20010-20000-01524
Plan Check / Job No.
B20VN06393
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE IRREG. 68'-4"X80'-7" TWO STORY SFD WITH ATTACHED TWO CAR GARAGE, OPEN TRELLIS AT FRONT AND REAR_ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D [SEE COMMENTS].
Permit Issued
Issued on 10/22/2020
Issuing Office
Current Status
CofO Issued on 6/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2020 APPLICANT
Assigned to Plan Check Engineer 5/28/2020 DAWN MC NULTY
Corrections Issued 6/5/2020 DAWN MC NULTY
Quality Review Completed 6/8/2020 CHON CHIO KUO
Building Plans Picked Up 6/12/2020 APPLICANT
Green Plans Picked Up 6/12/2020 APPLICANT
Applicant returned to address corrections 9/22/2020 DAWN MC NULTY
Plan Check Approved 10/5/2020 DAWN MC NULTY
Issued 10/22/2020 APPLICANT
CofO in Progress 6/18/2021 DAVID SANDOVAL
CofO Issued 6/19/2021 MICHAEL SMITH
Permit Finaled 6/19/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/7/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 7/8/2020 LEE GUILBEAUX
Sewer availability Cleared 7/8/2020 LEE GUILBEAUX
Construction near power lines Cleared 7/20/2020 WALTER RAMIREZ
Hydrant and Access approval Cleared 8/3/2020 MATTHEW CRAIG
Low Impact Development Cleared 8/5/2020 ROBIN YAMADA
Roof/Waste drainage to street Cleared 8/19/2020 GABRIEL ROBLES
GPI Written Notices Cleared 9/22/2020 DAWN MC NULTY
Grading Pre-Inspection Cleared 9/22/2020 DAWN MC NULTY
Miscellaneous Cleared 9/22/2020 DAWN MC NULTY
Green Code Cleared 9/23/2020 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/23/2020 Approved DAVID SANDOVAL
Footing/Foundation/Slab 11/23/2020 Partial Approval DAVID SANDOVAL
Sewer 11/23/2020 Approved DAVID SANDOVAL
Underground Mechanical 11/23/2020 Approved DAVID SANDOVAL
Deputy Reinf. Concrete 11/30/2020 Approved DAVID SANDOVAL
Footing/Foundation/Slab 12/4/2020 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 12/22/2020 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 1/19/2021 Approved DAVID SANDOVAL
HVAC-Rough 2/2/2021 Approved DAVID SANDOVAL
PLUMBING-Rough 2/2/2021 Approved DAVID SANDOVAL
Deputy Wood Construction 2/4/2021 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 2/5/2021 Approved DAVID SANDOVAL
ELECTRICAL-Rough 2/5/2021 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 2/5/2021 Approved DAVID SANDOVAL
Gas Test 2/5/2021 Approved DAVID SANDOVAL
Green Building Rough 2/5/2021 Not Ready for Inspection DAVID SANDOVAL
Shower Pan 2/5/2021 Approved DAVID SANDOVAL
Verify Sprinkler Sign Off 2/5/2021 Approved DAVID SANDOVAL
Green Building Rough 2/10/2021 Approved DAVID SANDOVAL
Insulation 2/10/2021 Approved DAVID SANDOVAL
Interior/Exterior Lathing 2/10/2021 Partial Approval DAVID SANDOVAL
Interior/Exterior Lathing 2/12/2021 Partial Approval CHRISTOPHER DELLEFIELD
Drywall Nailing 2/18/2021 Approved DAVID SANDOVAL
ELECTRICAL-Final 5/26/2021 Approved DAVID SANDOVAL
HVAC-Final 5/26/2021 Approved DAVID SANDOVAL
PLUMBING-Final 5/26/2021 Approved DAVID SANDOVAL
Final 6/17/2021 OK to Issue CofO DAVID SANDOVAL
Green Building Final 6/17/2021 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 6/17/2021 SGSOV Approved DAVID SANDOVAL
Service/Power Release 6/17/2021 Approved DAVID SANDOVAL
Smoke Detectors 6/17/2021 Approved DAVID SANDOVAL
Verify Sprinkler Sign Off 6/17/2021 Approved DAVID SANDOVAL