8616 N LUBAO AVE 91306
Certificate Information: 8616 N LUBAO AVE 91306
- Application / Permit
- 20010-20000-01503
- Plan Check / Job No.
- B20VN06286
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33
- Permit Issued
- Issued on 1/31/2021
- Issuing Office
- Current Status
- CofO Issued on 6/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2020 | DANIEL YIP |
| Corrections Issued | 6/12/2020 | DANIEL YIP |
| Quality Review Completed | 7/6/2020 | QUAN NGHIEM |
| Building Plans Picked Up | 7/10/2020 | APPLICANT |
| Plan Check Approved | 1/29/2021 | DANIEL YIP |
| Issued | 1/31/2021 | APPLICANT |
| CofO in Progress | 6/3/2021 | JOHN JANSON |
| Permit Finaled | 6/4/2021 | JOHN JANSON |
| CofO Issued | 6/4/2021 | JOHN JANSON |
| Permit Finaled | 6/4/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/17/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 7/17/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2020 | ADRIAN CASTRO |
| Green Code | Cleared | 7/30/2020 | MICHAEL AYERS |
| Construction near power lines | Cleared | 12/6/2020 | RIDWAN HARDY |
| Sewer availability | Cleared | 12/23/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | S&P Remodeling And Construction Inc; Lic. No.: 1070724-B | 8614 LUBAO AVE CANOGA PARK, CA 91306 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/16/2021 | Corrections Issued | JEFFREY PARD |
| Sewer | 2/16/2021 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 3/1/2021 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 3/1/2021 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 3/12/2021 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 3/12/2021 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 3/12/2021 | Approved | JEFFREY PARD |
| Wood Frame | 3/12/2021 | Not Ready for Inspection | JEFFREY PARD |
| BUILDING-Rough-Frame | 3/15/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 3/15/2021 | Approved | JEFFREY PARD |
| Green Building Rough | 3/15/2021 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 3/15/2021 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 3/15/2021 | Approved | JEFFREY PARD |
| Verify Sprinkler Sign Off | 3/15/2021 | Approved | JEFFREY PARD |
| Wood Frame | 3/15/2021 | Approved | JEFFREY PARD |
| Insulation | 3/18/2021 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 3/18/2021 | Not Ready for Inspection | JEFFREY PARD |
| Shower Pan | 3/18/2021 | Approved | JEFFREY PARD |
| Drywall Nailing | 3/22/2021 | Approved | JEFFREY PARD |
| Green Building Rough | 3/22/2021 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 3/22/2021 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 4/29/2021 | Approved | JEFFREY PARD |
| Final | 4/29/2021 | Corrections Issued | JEFFREY PARD |
| Footing/Foundation/Slab | 4/29/2021 | Approved | JEFFREY PARD |
| Green Building Final | 4/29/2021 | Corrections Issued | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 4/29/2021 | SGSOV Approved | JEFFREY PARD |
| Smoke Detectors | 4/29/2021 | Approved | JEFFREY PARD |
| Final | 5/7/2021 | Partial Approval | JEFFREY PARD |
| Green Building Final | 5/7/2021 | Approved | JEFFREY PARD |
| Service/Power Release | 5/7/2021 | Approved | JEFFREY PARD |
| Final | 6/1/2021 | OK to Issue CofO | JEFFREY PARD |