8333 N SHIRLEY AVE 91324
Certificate Information: 8333 N SHIRLEY AVE 91324
- Application / Permit
- 20010-20000-01459
- Plan Check / Job No.
- B20VN06140
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (57'-6"x 26'-0") IRR SHAPE DETACHED ACCESSORY DWELLING UNIT WITH NFPA-13D FIRE SPRINKLER THOUGHOUT PER LAMC 12.22 A.33 (c) and (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 4/22/2021
- Issuing Office
- Current Status
- CofO Issued on 8/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2020 | TROY DEGUZMAN |
| Corrections Issued | 5/26/2020 | TROY DEGUZMAN |
| Quality Review Completed | 5/28/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 5/28/2020 | APPLICANT |
| Green Plans Picked Up | 7/7/2020 | APPLICANT |
| Applicant returned to address corrections | 9/10/2020 | TROY DEGUZMAN |
| Plan Check Approved | 4/21/2021 | TROY DEGUZMAN |
| Issued | 4/22/2021 | APPLICANT |
| CofO in Progress | 8/15/2024 | KRISTEN BEVERIDGE |
| Permit Finaled | 8/30/2024 | JOHN JANSON |
| CofO Issued | 8/30/2024 | JOHN JANSON |
| Permit Finaled | 8/30/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/2/2020 | HOWARD COOPER |
| Miscellaneous | Cleared | 6/29/2020 | MARC WOERSCHING |
| Permit | Cleared | 7/7/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 7/8/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 7/17/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 7/23/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/24/2020 | JOHN TRIANTAFYLLOS |
| Green Code | Cleared | 8/11/2020 | MICHAEL AYERS |
| Trees in Parkway | Cleared | 4/14/2021 | JOHN KIM |
Contact Information
| Contractor | Gmx Construction Inc; Lic. No.: 498247-B | 15335 MORRISON STREET STE #305 SHERMAN OAKS, CA 91403 |
| Engineer | Missirian,, Garo; Lic. No.: C42608 | 4980 PALO DRIVE TARZANA, CA 913564441 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/10/2021 | Partial Inspection | MICHAEL PELHAM |
| Footing/Foundation/Slab | 9/30/2021 | Corrections Issued | JEFFREY PARD |
| Footing/Foundation/Slab | 10/7/2021 | Partial Approval | JEFFREY PARD |
| PLUMBING-Rough | 10/7/2021 | Partial Approval | JEFFREY PARD |
| Footing/Foundation/Slab | 10/29/2021 | Approved | JEFFREY PARD |
| Deputy Wood Construction | 10/23/2023 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 10/24/2023 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 10/24/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 10/24/2023 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 12/5/2023 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 12/5/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 12/5/2023 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 12/6/2023 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 12/12/2023 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 12/13/2023 | Partial Approval | DAVID SCANTLIN |
| PLUMBING-Rough | 12/15/2023 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 12/19/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 12/20/2023 | Approved | JOHN KIDWELL |
| Green Building Rough | 12/20/2023 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 12/20/2023 | Approved | JOHN KIDWELL |
| Insulation | 12/29/2023 | Approved | JOHN KIDWELL |
| Drywall Nailing | 1/8/2024 | Approved | DAVID SCANTLIN |
| Shower Pan | 1/11/2024 | Approved | DAVID SCANTLIN |
| Underground Mechanical | 3/19/2024 | Partial Approval | DAVID SCANTLIN |
| Sewer | 3/20/2024 | Approved | DAVID SCANTLIN |
| Underground Mechanical | 3/21/2024 | Partial Approval | DAVID SCANTLIN |
| ELECTRICAL-Rough | 3/26/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| Grounding or Bonding | 3/27/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 3/28/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Underground Mechanical | 3/28/2024 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 4/19/2024 | Approved | DAVID SCANTLIN |
| Service/Power Release | 4/19/2024 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 4/22/2024 | Partial Inspection | KRISTEN CAUSEY |
| SGSOV-Seismic Gas S/O Valve | 5/23/2024 | SGSOV Not Ready | KRISTEN CAUSEY |
| Service/Power Release | 5/23/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| Green Building Final | 7/31/2024 | Approved | KRISTEN CAUSEY |
| SGSOV-Seismic Gas S/O Valve | 7/31/2024 | SGSOV Approved | KRISTEN CAUSEY |
| Smoke Detectors | 7/31/2024 | Approved | KRISTEN CAUSEY |
| Final | 8/15/2024 | OK to Issue CofO | KRISTEN CAUSEY |