8333 N SHIRLEY AVE 91324

Certificate Information: 8333 N SHIRLEY AVE 91324

Application / Permit
20010-20000-01459
Plan Check / Job No.
B20VN06140
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (57'-6"x 26'-0") IRR SHAPE DETACHED ACCESSORY DWELLING UNIT WITH NFPA-13D FIRE SPRINKLER THOUGHOUT PER LAMC 12.22 A.33 (c) and (d). WORK PER ENGINEER.
Permit Issued
Issued on 4/22/2021
Issuing Office
Current Status
CofO Issued on 8/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/1/2020 APPLICANT
Assigned to Plan Check Engineer 5/22/2020 TROY DEGUZMAN
Corrections Issued 5/26/2020 TROY DEGUZMAN
Quality Review Completed 5/28/2020 CHON CHIO KUO
Building Plans Picked Up 5/28/2020 APPLICANT
Green Plans Picked Up 7/7/2020 APPLICANT
Applicant returned to address corrections 9/10/2020 TROY DEGUZMAN
Plan Check Approved 4/21/2021 TROY DEGUZMAN
Issued 4/22/2021 APPLICANT
CofO in Progress 8/15/2024 KRISTEN BEVERIDGE
Permit Finaled 8/30/2024 JOHN JANSON
CofO Issued 8/30/2024 JOHN JANSON
Permit Finaled 8/30/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/2/2020 HOWARD COOPER
Miscellaneous Cleared 6/29/2020 MARC WOERSCHING
Permit Cleared 7/7/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 7/8/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 7/8/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 7/17/2020 KURT CORRAL
Low Impact Development Cleared 7/23/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 7/24/2020 JOHN TRIANTAFYLLOS
Green Code Cleared 8/11/2020 MICHAEL AYERS
Trees in Parkway Cleared 4/14/2021 JOHN KIM

Contact Information

Contractor Gmx Construction Inc; Lic. No.: 498247-B 15335 MORRISON STREET STE #305      SHERMAN OAKS, CA 91403
Engineer Missirian,, Garo; Lic. No.: C42608 4980 PALO DRIVE      TARZANA, CA 913564441

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/10/2021 Partial Inspection MICHAEL PELHAM
Footing/Foundation/Slab 9/30/2021 Corrections Issued JEFFREY PARD
Footing/Foundation/Slab 10/7/2021 Partial Approval JEFFREY PARD
PLUMBING-Rough 10/7/2021 Partial Approval JEFFREY PARD
Footing/Foundation/Slab 10/29/2021 Approved JEFFREY PARD
Deputy Wood Construction 10/23/2023 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 10/24/2023 Partial Approval JOHN KIDWELL
Green Building Rough 10/24/2023 Not Ready for Inspection JOHN KIDWELL
Verify Sprinkler Sign Off 10/24/2023 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 12/5/2023 Partial Approval JOHN KIDWELL
Green Building Rough 12/5/2023 Not Ready for Inspection JOHN KIDWELL
Verify Sprinkler Sign Off 12/5/2023 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 12/6/2023 Approved DAVID SCANTLIN
HVAC-Rough 12/12/2023 Approved DAVID SCANTLIN
Interior/Exterior Lathing 12/13/2023 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 12/15/2023 Approved DAVID SCANTLIN
PLUMBING-Rough 12/19/2023 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 12/20/2023 Approved JOHN KIDWELL
Green Building Rough 12/20/2023 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 12/20/2023 Approved JOHN KIDWELL
Insulation 12/29/2023 Approved JOHN KIDWELL
Drywall Nailing 1/8/2024 Approved DAVID SCANTLIN
Shower Pan 1/11/2024 Approved DAVID SCANTLIN
Underground Mechanical 3/19/2024 Partial Approval DAVID SCANTLIN
Sewer 3/20/2024 Approved DAVID SCANTLIN
Underground Mechanical 3/21/2024 Partial Approval DAVID SCANTLIN
ELECTRICAL-Rough 3/26/2024 Not Ready for Inspection KRISTEN CAUSEY
Grounding or Bonding 3/27/2024 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 3/28/2024 Not Ready for Inspection DAVID SCANTLIN
Underground Mechanical 3/28/2024 Approved DAVID SCANTLIN
ELECTRICAL-Final 4/19/2024 Approved DAVID SCANTLIN
Service/Power Release 4/19/2024 Approved DAVID SCANTLIN
ELECTRICAL-Final 4/22/2024 Partial Inspection KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 5/23/2024 SGSOV Not Ready KRISTEN CAUSEY
Service/Power Release 5/23/2024 Not Ready for Inspection KRISTEN CAUSEY
Green Building Final 7/31/2024 Approved KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 7/31/2024 SGSOV Approved KRISTEN CAUSEY
Smoke Detectors 7/31/2024 Approved KRISTEN CAUSEY
Final 8/15/2024 OK to Issue CofO KRISTEN CAUSEY