4926 N PETIT AVE 91436

Certificate Information: 4926 N PETIT AVE 91436

Application / Permit
20010-20000-01455
Plan Check / Job No.
B20VN06130
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW (13'-0" x 19'-6") IRR SHAPE ONE STORY DETACHED REC. ROOM. WORK PER ENGINEER. SEE COMMENTS.
Permit Issued
Issued on 7/20/2020
Issuing Office
Current Status
CofO Issued on 12/11/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2020 APPLICANT
Assigned to Plan Check Engineer 5/6/2020 SERGIO MUNIZ
Corrections Issued 5/13/2020 SERGIO MUNIZ
Building Plans Picked Up 5/14/2020 APPLICANT
Plan Check Approved 7/20/2020 TROY DEGUZMAN
Issued 7/20/2020 APPLICANT
CofO in Progress 12/9/2020 RONALD COWAN
Permit Finaled 12/11/2020 DONALD SUNSERI
CofO Issued 12/11/2020 DONALD SUNSERI
Permit Finaled 12/11/2020 DONALD SUNSERI

Permit Application Clearance Information

Low Impact Development Cleared 6/24/2020 ROBIN YAMADA
Eng Process Fee Ord 176,300 Cleared 6/25/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 6/25/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/28/2020 Partial Approval RONALD COWAN
Excavation/Setback/Form/Re-Bar 7/30/2020 Corrections Issued RONALD COWAN
Excavation/Setback/Form/Re-Bar 8/4/2020 Partial Approval RONALD COWAN
BUILDING-Rough-Frame 8/18/2020 Approved RONALD COWAN
ELECTRICAL-Rough 8/18/2020 Approved RONALD COWAN
Green Building Rough 8/18/2020 Approved RONALD COWAN
PLUMBING-Rough 8/18/2020 Approved RONALD COWAN
Shower Pan 8/18/2020 Approved RONALD COWAN
Verify Sprinkler Sign Off 8/18/2020 Approved RONALD COWAN
Insulation 8/21/2020 Approved RONALD COWAN
Interior/Exterior Lathing 8/21/2020 Approved RONALD COWAN
Drywall Nailing 12/4/2020 Approved RONALD COWAN
Final 12/4/2020 OK to Issue CofO RONALD COWAN
Footing/Foundation/Slab 12/4/2020 Approved RONALD COWAN
Green Building Final 12/4/2020 Approved RONALD COWAN
SGSOV-Seismic Gas S/O Valve 12/4/2020 SGSOV Approved RONALD COWAN
Service/Power Release 12/4/2020 Approved RONALD COWAN
Smoke Detectors 12/4/2020 Approved RONALD COWAN