815 N LA JOLLA AVE 90046

Certificate Information: 815 N LA JOLLA AVE 90046

Application / Permit
20010-20000-01453
Plan Check / Job No.
B20VN06117
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE NEW 3 STORY SFD WITH ATTACHED GARAGE AND OPEN ROOF DECK_BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D (SEE COMMENTS).
Permit Issued
Issued on 11/2/2020
Issuing Office
Current Status
CofO Issued on 3/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2020 APPLICANT
Assigned to Plan Check Engineer 5/21/2020 DAWN MC NULTY
Green Plans Picked Up 6/1/2020 APPLICANT
Corrections Issued 6/9/2020 DAWN MC NULTY
Quality Review Completed 6/10/2020 CHON CHIO KUO
Building Plans Picked Up 6/11/2020 APPLICANT
Applicant returned to address corrections 10/5/2020 DAWN MC NULTY
Plan Check Approved 10/28/2020 DAWN MC NULTY
Issued 11/2/2020 APPLICANT
CofO in Progress 3/2/2022 CHRIS CHRISTENSEN
Permit Finaled 3/11/2022 DEROLD HAUFF
CofO Issued 3/11/2022 DEROLD HAUFF
Permit Finaled 3/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/18/2020 WALLIE JONG
Permit Cleared 6/19/2020 WALLIE JONG
Sewer availability Cleared 6/19/2020 WALLIE JONG
Trees in Parkway Cleared 6/24/2020 JOHN KIM
Low Impact Development Cleared 7/27/2020 MARTIN FRAGOSO
Frnt yard landscape/Water mgmt Cleared 8/3/2020 JOE LUCKEY
Roof/Waste drainage to street Cleared 8/10/2020 ROSA SILVA
Hydrant and Access approval Cleared 8/18/2020 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 8/27/2020 WALLIE JONG
Green Code Cleared 9/23/2020 MICHAEL AYERS

Contact Information

Contractor Sunset Built Inc; Lic. No.: 1005054-B 5455 WILSHIRE BLVD #1811      LOS ANGELES, CA 90036
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/9/2020 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 12/10/2020 Approved CHRIS CHRISTENSEN
Deputy Steel/Welding 1/7/2021 Conditional Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 1/11/2021 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 1/26/2021 Conditional Approval CHRIS CHRISTENSEN
HVAC-Rough 4/6/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 4/6/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/13/2021 Approved CHRIS CHRISTENSEN
Shower Pan 5/13/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/14/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/14/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 5/14/2021 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 5/14/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 5/26/2021 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 6/22/2021 Approved ALFREDO BALANDRA
Interior/Exterior Lathing 6/22/2021 Not Ready for Inspection ALFREDO BALANDRA
Interior/Exterior Lathing 6/25/2021 Partial Approval CHRIS CHRISTENSEN
HVAC-Final 11/24/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 2/14/2022 Approved CHRIS CHRISTENSEN
Service/Power Release 2/14/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Final 2/15/2022 Approved CHRIS CHRISTENSEN
Service/Power Release 2/15/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Smoke Detectors 2/15/2022 Approved CHRIS CHRISTENSEN
Final 2/24/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 2/24/2022 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 2/24/2022 SGSOV Approved CHRIS CHRISTENSEN
Final 3/1/2022 OK to Issue CofO CHRIS CHRISTENSEN