3749 N SCADLOCK LANE 91403

Certificate Information: 3749 N SCADLOCK LANE 91403

Application / Permit
20010-20000-01450
Plan Check / Job No.
B20VN06111
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 42'6"X28'3'" 1-STORY ADU PER LAMC 12.22 A.33(c) and (d) NFPA 13 D REQ'D THROUGHOUT
Permit Issued
Issued on 3/7/2023
Issuing Office
Valley
Current Status
CofO Issued on 12/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2020 APPLICANT
Assigned to Plan Check Engineer 5/21/2020 MARVEL DELACRUZ
Corrections Issued 5/27/2020 MARVEL DELACRUZ
Quality Review Completed 5/28/2020 STEVEN KIM
Green Plans Picked Up 6/1/2020 APPLICANT
Building Plans Picked Up 7/15/2020 APPLICANT
Applicant returned to address corrections 7/14/2021 MARVEL DELACRUZ
Plan Check Approved 11/9/2021 MARVEL DELACRUZ
Issued 3/7/2023 APPLICANT
CofO in Progress 10/10/2023 THOMAS FINNILA
Permit Finaled 12/19/2023 RUBEN SALAS
CofO Issued 12/19/2023 RUBEN SALAS
Permit Finaled 12/19/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/28/2020 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 7/28/2020 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 7/28/2020 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 7/28/2020 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 7/28/2020 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 7/28/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 7/28/2020 LEE GUILBEAUX
Sewer availability Cleared 7/28/2020 LEE GUILBEAUX
Distance to fire station Cleared 12/1/2020 MATTHEW CRAIG
Hydrant and Access approval Cleared 12/1/2020 MATTHEW CRAIG
Low Impact Development Cleared 3/11/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 3/15/2021 ABDULLAH SADOZAI
Green Code Cleared 7/14/2021 MARVEL DELACRUZ

Contact Information

Contractor Owner-Builder       ,
Engineer Babapirzadeh,, Ghazal; Lic. No.: C90480 1530 N DETROIT ST APT 109      LOS ANGELES, CA 90046
Engineer Minas,, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204
Geologist Minas,, Shant; Lic. No.: EG2607 566 RIVERDALE DRIVE      GLENDALE, CA 91204

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 4/19/2023 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 5/3/2023 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 5/9/2023 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 5/9/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 5/12/2023 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 5/22/2023 Approved THOMAS FINNILA
Wood Frame 6/6/2023 Corrections Issued THOMAS FINNILA
Wood Frame 6/8/2023 Partial Approval THOMAS FINNILA
Wood Frame 6/12/2023 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 7/5/2023 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 7/5/2023 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Rough 7/5/2023 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 7/5/2023 Corrections Issued MISAEL ESPARZA
Wood Frame 7/5/2023 Corrections Issued MISAEL ESPARZA
Wood Frame 7/7/2023 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 7/17/2023 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 7/17/2023 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 7/17/2023 Not Ready for Inspection THOMAS FINNILA
Wood Frame 7/17/2023 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 7/20/2023 Approved THOMAS FINNILA
HVAC-Rough 7/20/2023 Approved THOMAS FINNILA
PLUMBING-Rough 7/20/2023 Approved THOMAS FINNILA
Verify Sprinkler Sign Off 7/20/2023 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 7/25/2023 Not Ready for Inspection THOMAS FINNILA
Wood Frame 7/25/2023 Corrections Issued THOMAS FINNILA
Interior/Exterior Lathing 7/28/2023 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 7/28/2023 Conditional Approval MISAEL ESPARZA
Insulation 8/2/2023 Conditional Approval THOMAS FINNILA
Interior/Exterior Lathing 8/2/2023 Partial Approval THOMAS FINNILA
Interior/Exterior Lathing 8/8/2023 Partial Approval THOMAS FINNILA
Drywall Nailing 8/14/2023 Approved THOMAS FINNILA
Green Building Rough 8/14/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 8/17/2023 Partial Approval THOMAS FINNILA
Shower Pan 8/17/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 8/21/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 8/28/2023 Approved THOMAS FINNILA
BUILDING-Rough-Frame 9/12/2023 Conditional Approval THOMAS FINNILA
Final 9/12/2023 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 9/12/2023 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 9/12/2023 Approved THOMAS FINNILA
Verify Sprinkler Sign Off 9/12/2023 Approved THOMAS FINNILA
BUILDING-Rough-Frame 9/18/2023 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 9/18/2023 Not Ready for Inspection MISAEL ESPARZA
Final 9/18/2023 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 9/18/2023 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Final 9/18/2023 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Rough 9/18/2023 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/18/2023 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 9/18/2023 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 9/29/2023 Approved THOMAS FINNILA
Final 9/29/2023 Corrections Issued THOMAS FINNILA
Green Building Final 9/29/2023 Approved THOMAS FINNILA
MERV13>=Final 9/29/2023 Approved THOMAS FINNILA
MERV13>=Rough 9/29/2023 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 9/29/2023 SGSOV Not Ready THOMAS FINNILA
Service/Power Release 9/29/2023 Corrections Issued THOMAS FINNILA
Pre-Inspection 10/4/2023 Approved THOMAS FINNILA
ELECTRICAL-Final 10/6/2023 Approved THOMAS FINNILA
Final 10/6/2023 OK to Issue CofO THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 10/6/2023 SGSOV Approved THOMAS FINNILA
Service/Power Release 10/6/2023 Approved THOMAS FINNILA