3516 1/2 E SABINA ST 90023

Certificate Information: 3516 1/2 E SABINA ST 90023

Application / Permit
20010-20000-01442
Plan Check / Job No.
B20VN06058
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 27'-6" X 23'-6" TWO STORY ACCESSORY DWELLING ALL WORK PER ENGINEERING NFPA 13D SPRINKLER SYSTEM REQUIRED THROUGHOUT
Permit Issued
Issued on 3/5/2021
Issuing Office
Metro
Current Status
CofO Issued on 5/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2020 APPLICANT
Assigned to Plan Check Engineer 5/14/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 5/22/2020 SEWADA ZADOORIAN MILAGARDI
Green Plans Picked Up 5/28/2020 APPLICANT
Quality Review Completed 6/5/2020 OMID HEDAYAT
Plan Check Approved 2/8/2021 SEWADA ZADOORAN MILAGARDI
Issued 3/5/2021 APPLICANT
Building Plans Picked Up 1/7/2022 APPLICANT
CofO in Progress 5/8/2023 FREDDIE RIVERA
Permit Finaled 5/21/2023 DEROLD HAUFF
CofO Issued 5/21/2023 DEROLD HAUFF
Permit Finaled 5/21/2023 DEROLD HAUFF

Permit Application Clearance Information

Clean Up Green Up Cleared 6/19/2020 STEVEN WECHSLER
Address approval Cleared 6/30/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 7/9/2020 EMIL KYUPELYAN
Sewer availability Cleared 7/9/2020 EMIL KYUPELYAN
Low Impact Development Cleared 9/13/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/29/2020 ELENA LOPEZ
Green Code Cleared 10/1/2020 DAVID MATSON
Hydrant and Access approval Cleared 11/17/2020 MATTHEW CRAIG

Contact Information

Contractor Specialty Remodeling Inc; Lic. No.: 1050840-B 3940 LAUREL CAYON BLVD   #120    STUDIO CITY, CA 91604
Engineer Standley,, Craig Erick; Lic. No.: C87675 6631 MURIETTA AVE      LOS ANGELES, CA 91405

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/14/2021 Partial Inspection ROBERT VORHIS
Excavation/Setback/Form/Re-Bar 9/13/2021 Approved ROBERT VORHIS
Footing/Foundation/Slab 9/13/2021 Approved ROBERT VORHIS
PLUMBING-Rough 9/13/2021 Partial Approval ROBERT VORHIS
Sewer 9/13/2021 Partial Inspection ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 11/4/2021 Partial Approval OSVALDO PARAMO
Underground Mechanical 11/4/2021 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 12/1/2021 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 12/1/2021 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Rough 12/1/2021 Not Ready for Inspection ALIZAH MAYAGOITIA
Sewer 12/1/2021 Corrections Issued ALIZAH MAYAGOITIA
Underground Mechanical 12/1/2021 Not Ready for Inspection ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 12/1/2021 Not Ready for Inspection ALIZAH MAYAGOITIA
Wood Frame 12/1/2021 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 12/10/2021 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 12/10/2021 Approved ALIZAH MAYAGOITIA
HVAC-Rough 12/10/2021 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 12/10/2021 Corrections Issued ALIZAH MAYAGOITIA
Sewer 12/10/2021 Approved ALIZAH MAYAGOITIA
Underground Mechanical 12/10/2021 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 12/17/2021 Not Ready for Inspection ALIZAH MAYAGOITIA
Gas Test 12/17/2021 Partial Approval ALIZAH MAYAGOITIA
HVAC-Rough 12/17/2021 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 12/17/2021 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 12/17/2021 Approved ALIZAH MAYAGOITIA
Insulation 12/23/2021 Conditional Approval LILIANA PORTILLO
Interior/Exterior Lathing 12/23/2021 Approved LILIANA PORTILLO
Shower Pan 12/23/2021 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 6/27/2022 Approved RYAN SALAZAR
Green Building Rough 6/27/2022 Approved RYAN SALAZAR
Insulation 6/27/2022 Approved RYAN SALAZAR
MERV13>=Rough 6/27/2022 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 6/27/2022 Approved RYAN SALAZAR
Drywall Nailing 7/7/2022 Approved RYAN SALAZAR
Gas Test 8/2/2022 Approved MICHAEL LEWIS
ELECTRICAL-Final 12/12/2022 Approved FREDDIE RIVERA
Final 12/12/2022 Partial Inspection FREDDIE RIVERA
Green Building Final 12/12/2022 Approved FREDDIE RIVERA
HVAC-Final 12/12/2022 Approved FREDDIE RIVERA
MERV13>=Final 12/12/2022 Approved FREDDIE RIVERA
PLUMBING-Final 12/12/2022 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 12/12/2022 SGSOV Approved FREDDIE RIVERA
Service/Power Release 12/12/2022 Partial Inspection FREDDIE RIVERA
Smoke Detectors 12/12/2022 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Final 1/11/2023 Approved FREDDIE RIVERA
Final 1/11/2023 Corrections Issued FREDDIE RIVERA
HVAC-Final 1/11/2023 Approved FREDDIE RIVERA
PLUMBING-Final 1/11/2023 Approved FREDDIE RIVERA
Service/Power Release 1/11/2023 Approved FREDDIE RIVERA
Smoke Detectors 1/11/2023 Approved FREDDIE RIVERA
Final 5/5/2023 OK to Issue CofO FREDDIE RIVERA