6366 W 79TH ST 90045
Certificate Information: 6366 W 79TH ST 90045
- Application / Permit
- 20010-20000-01432
- Plan Check / Job No.
- B20VN06023
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 59'10"X45'0" IRREGULAR SHAPED 2-STORY SFD WITH 2-CAR ATTACHED GARAGE. NFPA 13D FIRE SPRINKLERS REQ'D THROUGHOUT
- Permit Issued
- Issued on 8/28/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2020 | MARVEL DELACRUZ |
| Corrections Issued | 6/16/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 6/18/2020 | STEVEN KIM |
| Building Plans Picked Up | 6/23/2020 | APPLICANT |
| Green Plans Picked Up | 6/23/2020 | APPLICANT |
| Plan Check Approved | 8/17/2020 | MARVEL DELACRUZ |
| Issued | 8/28/2020 | APPLICANT |
| CofO in Progress | 4/16/2021 | BRENDAN LOONEY |
| Permit Finaled | 5/12/2021 | VINCENT COTTON |
| CofO Issued | 5/12/2021 | VINCENT COTTON |
| Permit Finaled | 5/12/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 6/30/2020 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2020 | CATHERINE ADROVER |
| Sewer availability | Cleared | 6/30/2020 | CATHERINE ADROVER |
| Low Impact Development | Cleared | 7/6/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 7/7/2020 | CATHERINE ADROVER |
| Green Code | Cleared | 7/14/2020 | MICHAEL AYERS |
| Specific Plan | Cleared | 7/27/2020 | FREDDY GARCIA |
| Hydrant and Access approval | Cleared | 7/28/2020 | KURT CORRAL |
Contact Information
| Contractor | Local Construction Remodeling; Lic. No.: 966738-B | 14901 TUBA STREET MISSION HILLS, CA 91345 |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Engineer | Vidal,, Juan Alonso; Lic. No.: GE861 | 7438 SHIRLEY AVE RESEDA, CA 91335 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/14/2020 | Partial Approval | JOHNNY MIRANDA |
| METHANE-Barrier | 9/14/2020 | Approved | JOHNNY MIRANDA |
| METHANE-Subgrade | 9/14/2020 | Approved | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 9/21/2020 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 9/21/2020 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/29/2020 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 9/29/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| METHANE-Rough | 9/29/2020 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 9/29/2020 | Corrections Issued | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 9/29/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2020 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 10/1/2020 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2020 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2020 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2020 | Partial Approval | JOHNNY MIRANDA |
| Rough-Elec/Plmb/HVAC | 11/13/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Rough-Elec/Plmb/HVAC | 11/17/2020 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 11/18/2020 | Not Ready for Inspection | RICHARD ROBLES |
| Green Building Rough | 11/18/2020 | Not Ready for Inspection | RICHARD ROBLES |
| Interior/Exterior Lathing | 11/18/2020 | Not Ready for Inspection | RICHARD ROBLES |
| Shower Pan | 11/18/2020 | Not Ready for Inspection | RICHARD ROBLES |
| Verify Sprinkler Sign Off | 11/18/2020 | Approved | RICHARD ROBLES |
| Interior/Exterior Lathing | 11/19/2020 | Partial Approval | JOHNNY MIRANDA |
| Shower Pan | 11/19/2020 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 11/23/2020 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 11/23/2020 | Approved | JOHNNY MIRANDA |
| Insulation | 11/23/2020 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 11/23/2020 | Partial Approval | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 11/25/2020 | Approved | JOHNNY MIRANDA |
| Sewer | 11/25/2020 | Approved | JOHNNY MIRANDA |
| Underground Mechanical | 11/25/2020 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 12/2/2020 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2020 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 3/5/2021 | Approved | DAVID HEINE |
| Gas Test | 3/5/2021 | Approved | DAVID HEINE |
| HVAC-Final | 3/5/2021 | Approved | DAVID HEINE |
| PLUMBING-Final | 3/5/2021 | Approved | DAVID HEINE |
| Service/Power Release | 3/5/2021 | Not Ready for Inspection | DAVID HEINE |
| Smoke Detectors | 3/5/2021 | Approved | DAVID HEINE |
| Final | 4/9/2021 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 4/9/2021 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 4/9/2021 | SGSOV Approved | JOHNNY MIRANDA |
| Service/Power Release | 4/9/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Final | 4/13/2021 | Corrections Issued | JUAN VALENZUELA |
| Service/Power Release | 4/13/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Final | 4/15/2021 | OK to Issue CofO | BRENDAN LOONEY |
| Service/Power Release | 4/15/2021 | Approved | BRENDAN LOONEY |