14011 W CHANDLER BLVD 91401

Certificate Information: 14011 W CHANDLER BLVD 91401

Application / Permit
20010-20000-01426
Plan Check / Job No.
B20VN06002
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20'x37'8" Accessory Dwelling Unit over three (3) car garage PER STATE ORDINANCE 186.481,
Permit Issued
Issued on 10/30/2020
Issuing Office
Current Status
CofO Issued on 3/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2020 APPLICANT
Assigned to Plan Check Engineer 5/22/2020 LUIS RINCON
Corrections Issued 5/23/2020 LUIS RINCON
Green Plans Picked Up 6/1/2020 APPLICANT
Quality Review Completed 6/8/2020 CHON CHIO KUO
Building Plans Picked Up 6/11/2020 APPLICANT
Applicant returned to address corrections 7/31/2020 SERGIO MUNIZ
Plan Check Approved 10/14/2020 SERGIO MUNIZ
Issued 10/30/2020 APPLICANT
CofO in Progress 12/23/2021 RICHARD DOCKUS
Permit Finaled 3/26/2022 DEROLD HAUFF
CofO Issued 3/26/2022 DEROLD HAUFF
Permit Finaled 3/26/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/25/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 6/25/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 6/26/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 6/26/2020 JOHN TRIANTAFYLLOS
Green Code Cleared 7/14/2020 MICHAEL AYERS
Miscellaneous Cleared 8/17/2020 MARITZA PRZEKOP
Low Impact Development Cleared 9/22/2020 SARAH YOUSSEF
Hydrant and Access approval Cleared 9/23/2020 MATTHEW CRAIG

Contact Information

Architect Scrafano,, Elissa F; Lic. No.: C26071 163 N SYCAMORE      LOS ANGELES, CA 90036
Contractor Rustom Group Corp; Lic. No.: 748738-B 26893 BOUQUET CYN RD #C-453      SANTA CLARITA, CA 91350
Engineer Manalo,, Philip Casis; Lic. No.: S3823 9547 WYSTONE AVE      NORTHRIDGE, CA 91324
Geologist Schick,, John Wayne; Lic. No.: EG1300 7650 HASKELL AVENUE STE D      VAN NUYS, CA 91406

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/3/2020 Partial Inspection MICHEL ABAJAN
Footing/Foundation/Slab 12/30/2020 Partial Approval JOHN HAYES
Footing/Foundation/Slab 1/5/2021 Conditional Approval MICHEL ABAJAN
Footing/Foundation/Slab 1/19/2021 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 1/26/2021 Partial Approval MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 2/9/2021 Partial Approval MICHEL ABAJAN
Green Building Rough 2/9/2021 Not Ready for Inspection MICHEL ABAJAN
Verify Sprinkler Sign Off 2/9/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 2/16/2021 Approved VINCENT HANLEY
PLUMBING-Rough 2/26/2021 Partial Approval MATTHEW NELSON
HVAC-Rough 3/15/2021 Corrections Issued MICHAEL TEMPLE
ELECTRICAL-Rough 3/19/2021 Approved BRENDAN LOONEY
HVAC-Rough 4/8/2021 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 4/15/2021 Approved MICHAEL TEMPLE
HVAC-Rough 4/26/2021 Approved JENNIFER RABUCHIN
Underground Mechanical 4/26/2021 Approved JENNIFER RABUCHIN
Wood Frame 4/26/2021 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/4/2021 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 5/4/2021 Not Ready for Inspection JENNIFER RABUCHIN
Insulation 5/20/2021 Approved JOHN HAYES
Interior/Exterior Lathing 5/20/2021 Partial Approval JOHN HAYES
Drywall Nailing 6/4/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 6/30/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 8/6/2021 Approved RONALD COWAN
HVAC-Final 8/26/2021 Corrections Issued RICHARD DOCKUS
Gas Test 8/27/2021 Approved RICHARD DOCKUS
HVAC-Final 8/27/2021 Corrections Issued RICHARD DOCKUS
PLUMBING-Final 8/27/2021 Approved RICHARD DOCKUS
HVAC-Final 9/17/2021 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 9/22/2021 Approved RICHARD DOCKUS
Final 9/22/2021 Corrections Issued RICHARD DOCKUS
Green Building Final 9/22/2021 Approved RICHARD DOCKUS
Green Building Rough 9/22/2021 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 9/22/2021 SGSOV Not Ready RICHARD DOCKUS
Service/Power Release 9/22/2021 Not Ready for Inspection RICHARD DOCKUS
Smoke Detectors 9/22/2021 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 10/12/2021 SGSOV Approved RICHARD DOCKUS
Final 11/2/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Final 11/2/2021 Approved JENNIFER RABUCHIN
Service/Power Release 11/2/2021 Not Ready for Inspection JENNIFER RABUCHIN
Final 12/22/2021 OK to Issue CofO RICHARD DOCKUS
Service/Power Release 12/22/2021 Approved RICHARD DOCKUS