5340 N AURA AVE 91356
Certificate Information: 5340 N AURA AVE 91356
- Application / Permit
- 20010-20000-01373
- Plan Check / Job No.
- B20VN05872
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- (N) 19'-6" x 13' Irregular shape Recroom and Full Bath with exterior access & attached 19'-6" x 14" Open Trellis.
- Permit Issued
- Issued on 8/18/2020
- Issuing Office
- Current Status
- CofO Issued on 3/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2020 | OMID HEDAYAT |
| Corrections Issued | 5/15/2020 | OMID HEDAYAT |
| Quality Review Completed | 5/19/2020 | STEVEN KIM |
| Building Plans Picked Up | 5/20/2020 | APPLICANT |
| Green Plans Picked Up | 5/20/2020 | APPLICANT |
| Applicant returned to address corrections | 8/17/2020 | OMID HEDAYAT |
| Plan Check Approved | 8/17/2020 | OMID HEDAYAT |
| Issued | 8/18/2020 | APPLICANT |
| CofO in Progress | 3/14/2022 | DAVID SANDOVAL |
| Permit Finaled | 3/22/2022 | JOHN JANSON |
| CofO Issued | 3/22/2022 | JOHN JANSON |
| Permit Finaled | 3/22/2022 | JOHN JANSON |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 5/13/2020 | OMID HEDAYAT |
| Grading Pre-Inspection | Cleared | 5/13/2020 | OMID HEDAYAT |
| Low Impact Development | Cleared | 8/2/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/5/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2020 | GABRIEL ROBLES |
| Green Code | Cleared | 8/13/2020 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/28/2020 | Partial Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 10/2/2020 | Corrections Issued | DAVID SANDOVAL |
| Excavation/Setback/Form/Re-Bar | 10/6/2020 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 10/6/2020 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2020 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 11/9/2020 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 12/1/2020 | Approved | RONALD COWAN |
| HVAC-Rough | 12/1/2020 | Approved | RONALD COWAN |
| Shower Pan | 12/8/2020 | Approved | JOSEPH SAGEN |
| Interior/Exterior Lathing | 12/17/2020 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 1/5/2021 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 1/5/2021 | Approved | DAVID SANDOVAL |
| Green Building Rough | 1/5/2021 | Approved | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 1/5/2021 | Approved | DAVID SANDOVAL |
| Special/Order Compliance | 9/2/2021 | Corrections Issued | DAVID SANDOVAL |
| ELECTRICAL-Final | 2/9/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Final | 2/9/2022 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Final | 2/15/2022 | Approved | DAVID SANDOVAL |
| Final | 2/15/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Final | 2/15/2022 | Approved | DAVID SANDOVAL |
| HVAC-Final | 2/15/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Final | 2/15/2022 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 2/15/2022 | SGSOV Approved | DAVID SANDOVAL |
| Service/Power Release | 2/15/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Smoke Detectors | 2/15/2022 | Approved | DAVID SANDOVAL |
| Final | 3/11/2022 | OK to Issue CofO | DAVID SANDOVAL |
| Service/Power Release | 3/11/2022 | Approved | DAVID SANDOVAL |