9612 N RUDNICK AVE 91311

Certificate Information: 9612 N RUDNICK AVE 91311

Application / Permit
20010-20000-01365
Plan Check / Job No.
B20VN05845
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 21'-4" X 43' DETACHED ACCESSORY DWELLING UNIT WITH COVERED PORCH AND 20'-4" X 8' TRELLIS PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 2/11/2022
Issuing Office
Current Status
CofO Issued on 7/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2020 APPLICANT
Assigned to Plan Check Engineer 5/22/2020 JEROME MAGAT PALMA
Corrections Issued 5/26/2020 JEROME MAGAT PALMA
Quality Review Completed 5/27/2020 STEVEN KIM
Green Plans Picked Up 6/1/2020 APPLICANT
Applicant returned to address corrections 1/21/2022 JEROME MAGAT PALMA
Plan Check Approved 2/11/2022 JEROME MAGAT PALMA
Issued 2/11/2022 APPLICANT
Building Plans Picked Up 2/14/2022 APPLICANT
CofO in Progress 5/26/2023 CHRIS CHRISTENSEN
Permit Finaled 7/24/2023 JOHN JANSON
CofO Issued 7/24/2023 JOHN JANSON
Permit Finaled 7/24/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/18/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 2/18/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/18/2021 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 2/22/2021 BRIAN MILLER
ZI Cleared 4/19/2021 DANG NGUYEN
Low Impact Development Cleared 6/24/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 8/14/2021 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 10/13/2021 MATTHEW CRAIG
Specific Plan Cleared 10/15/2021 STEVEN WECHSLER
GPI Written Notices Cleared 12/7/2021 JEROME MAGAT PALMA
Green Code Cleared 2/11/2022 JEROME MAGAT PALMA

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/16/2022 Partial Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 3/30/2022 Conditional Approval CHRIS CHRISTENSEN
Underground Mechanical 3/30/2022 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/26/2022 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 5/26/2022 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 5/26/2022 Approved CHRIS CHRISTENSEN
Underground Mechanical 5/26/2022 Partial Approval CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 5/26/2022 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/13/2022 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 6/13/2022 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 6/13/2022 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/17/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 6/17/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/17/2022 Partial Approval CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 6/17/2022 Approved CHRIS CHRISTENSEN
Insulation 6/27/2022 Approved MORRIS JACKSON
Drywall Nailing 7/27/2022 Approved JESUS PINEDA
Gas Test 8/18/2022 Approved CHRIS CHRISTENSEN
Shower Pan 8/18/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 8/24/2022 Approved JESUS PINEDA
ELECTRICAL-Final 10/27/2022 Corrections Issued CHRIS CHRISTENSEN
Final 4/21/2023 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 4/21/2023 Approved CHRIS CHRISTENSEN
Green Building Final 4/21/2023 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 4/21/2023 SGSOV Approved CHRIS CHRISTENSEN
Service/Power Release 4/21/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Smoke Detectors 4/21/2023 Approved CHRIS CHRISTENSEN
Final 5/23/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 5/23/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Service/Power Release 5/23/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Final 5/25/2023 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 5/25/2023 Approved CHRIS CHRISTENSEN
Service/Power Release 5/25/2023 Approved CHRIS CHRISTENSEN