4425 N HASKELL AVE 91436
Certificate Information: 4425 N HASKELL AVE 91436
- Application / Permit
- 20010-20000-01357
- Plan Check / Job No.
- B20VN05820
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW 15'-3" x 9'-9" DETACHED OPEN ROOF TRELLIS (OPEN ON 3 SIDES), PER ENGR DESIGN.
- Permit Issued
- Issued on 8/20/2020
- Issuing Office
- Current Status
- CofO Issued on 3/5/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2020 | MARJAN SHENASI |
| Corrections Issued | 4/28/2020 | MARJAN SHENASI |
| Building Plans Picked Up | 5/19/2020 | APPLICANT |
| Applicant returned to address corrections | 6/4/2020 | LUIS RINCON |
| Applicant returned to address corrections | 6/29/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 7/28/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 7/29/2020 | JEROME MAGAT PALMA |
| Issued | 8/20/2020 | APPLICANT |
| CofO in Progress | 3/1/2021 | RONALD COWAN |
| Permit Finaled | 3/5/2021 | RONALD MYRICK |
| CofO Issued | 3/5/2021 | RONALD MYRICK |
| Permit Finaled | 3/5/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/18/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 5/22/2020 | GEORGE SUCHAND |
| Grading Pre-Inspection | Cleared | 6/4/2020 | TIMOTHY POWELL |
| Miscellaneous | Cleared | 7/2/2020 | LAUREN PADICK |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Socal Design And Building Inc; Lic. No.: 1036852-B | 4100 SUMAC DRIVE SHERMAN OAKS, CA 91403 |
| Engineer | Javadi-Koma,, Shahram; Lic. No.: C69497 | 6701 ETON AVE APT 115 CANOGA PARK, CA 91303 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/17/2020 | Corrections Issued | RONALD COWAN |
| Wood Frame | 1/8/2021 | Not Ready for Inspection | RONALD COWAN |
| Interior/Exterior Lathing | 1/19/2021 | Not Ready for Inspection | RONALD COWAN |
| Interior/Exterior Lathing | 1/25/2021 | Approved | HENRY KIM |
| Drywall Nailing | 2/8/2021 | No Access for Inspection | PAUL CHOPP |
| Final | 2/8/2021 | No Access for Inspection | PAUL CHOPP |
| Footing/Foundation/Slab | 2/8/2021 | No Access for Inspection | PAUL CHOPP |
| SGSOV-Seismic Gas S/O Valve | 2/8/2021 | SGSOV Not Ready | PAUL CHOPP |
| Smoke Detectors | 2/8/2021 | No Access for Inspection | PAUL CHOPP |
| Verify Sprinkler Sign Off | 2/8/2021 | No Access for Inspection | PAUL CHOPP |
| Wood Frame | 2/8/2021 | No Access for Inspection | PAUL CHOPP |
| Final | 2/26/2021 | OK to Issue CofO | RONALD COWAN |
| Footing/Foundation/Slab | 2/26/2021 | Approved | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 2/26/2021 | SGSOV Approved | RONALD COWAN |
| Smoke Detectors | 2/26/2021 | Approved | RONALD COWAN |
| Wood Frame | 2/26/2021 | Approved | RONALD COWAN |