8767 N HERRICK AVE 91352
Certificate Information: 8767 N HERRICK AVE 91352
- Application / Permit
- 20010-20000-01355
- Plan Check / Job No.
- B20VN05817
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 27'3" X 27'2" TWO STORY IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER LAMC12.22.A33(C) AND (E) , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 2/22/2021
- Issuing Office
- Current Status
- CofO Issued on 8/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2020 | RARES BODEA |
| Corrections Issued | 5/21/2020 | RARES BODEA |
| Quality Review Completed | 5/27/2020 | STEVEN KIM |
| Building Plans Picked Up | 5/28/2020 | APPLICANT |
| Green Plans Picked Up | 5/28/2020 | APPLICANT |
| Plan Check Approved | 2/22/2021 | RARES BODEA |
| Issued | 2/22/2021 | APPLICANT |
| CofO in Progress | 5/6/2022 | CHRISTOPHER DELLEFIELD |
| No Progress | 5/11/2022 | CHRISTOPHER DELLEFIELD |
| CofO in Progress | 5/11/2022 | CHRISTOPHER DELLEFIELD |
| CofO Issued | 8/17/2022 | MICHAEL SMITH |
| Permit Finaled | 8/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/29/2020 | GUILLERMO PETRA |
| ZI | Cleared | 5/29/2020 | SHEILA GERSHON |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 6/3/2020 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 12/29/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/30/2020 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 2/4/2021 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/8/2021 | Approved | BEAU COLLINS |
| BUILDING-Rough-Frame | 4/16/2021 | Partial Approval | BEAU COLLINS |
| PLUMBING-Rough | 4/16/2021 | Partial Approval | BEAU COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2021 | Partial Approval | BEAU COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2021 | Partial Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 6/30/2021 | Corrections Issued | JOHN HAYES |
| Green Building Rough | 6/30/2021 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 6/30/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 7/23/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 7/23/2021 | Approved | MATTHEW NELSON |
| HVAC-Rough | 7/23/2021 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 7/23/2021 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/6/2021 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 8/6/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 8/6/2021 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 8/6/2021 | Not Ready for Inspection | JOHN HAYES |
| Deputy Wood Construction | 8/18/2021 | Conditional Approval | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 8/20/2021 | Conditional Approval | WILLIAM KUEHN |
| ELECTRICAL-Rough | 8/20/2021 | Approved | WILLIAM KUEHN |
| PLUMBING-Rough | 8/20/2021 | Approved | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 8/20/2021 | Approved | WILLIAM KUEHN |
| Wood Frame | 8/20/2021 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 9/10/2021 | Partial Inspection | WILLIAM KUEHN |
| Insulation | 9/16/2021 | Conditional Approval | JUSTIN HAWLEY |
| Drywall Nailing | 9/23/2021 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 10/13/2021 | Partial Inspection | WILLIAM KUEHN |
| PLUMBING-Final | 11/30/2021 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 12/3/2021 | No Access for Inspection | WILLIAM KUEHN |
| Gas Test | 12/3/2021 | Partial Inspection | WILLIAM KUEHN |
| Rough-Elec/Plmb/HVAC | 12/3/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 2/15/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 2/15/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 2/15/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Final | 2/15/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/15/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 2/15/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 2/15/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Service/Power Release | 3/1/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 3/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 3/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 3/11/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 3/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Final | 3/11/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 3/11/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 3/11/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 3/11/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 3/11/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 3/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 3/18/2022 | Approved | MICHAEL TEMPLE |
| HVAC-Final | 3/18/2022 | Approved | MICHAEL TEMPLE |
| PLUMBING-Final | 3/18/2022 | Approved | MICHAEL TEMPLE |
| Final | 5/6/2022 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |
| Green Building Final | 5/6/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 5/6/2022 | Approved | CHRISTOPHER DELLEFIELD |