19908 W SATICOY ST 91306

Certificate Information: 19908 W SATICOY ST 91306

Application / Permit
20010-20000-01350
Plan Check / Job No.
B20VN05796
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD NEW 22'-10" x 32'-5" TWO-STORY ACCESSORY DWELLING UNIT TO (E) DET. GARAGE PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 8/9/2021
Issuing Office
Valley
Current Status
CofO Issued on 9/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2020 APPLICANT
Assigned to Plan Check Engineer 5/6/2020 SEAN SHAHMIRI
Corrections Issued 5/8/2020 SEAN SHAHMIRI
Green Plans Picked Up 5/20/2020 APPLICANT
Quality Review Completed 5/22/2020 OMID HEDAYAT
Building Plans Picked Up 5/29/2020 APPLICANT
Applicant returned to address corrections 11/23/2020 SEAN SHAHMIRI
Applicant returned to address corrections 4/19/2021 SEAN SHAHMIRI
Applicant returned to address corrections 6/21/2021 SEAN SHAHMIRI
Plan Check Approved 6/21/2021 SEAN SHAHMIRI
Issued 8/9/2021 APPLICANT
CofO in Progress 8/15/2025 ALEXANDER HANDY
Permit Finaled 9/18/2025 JOHN JANSON
CofO Issued 9/18/2025 JOHN JANSON
Permit Finaled 9/18/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/7/2020 WALLIE JONG
Sewer availability Cleared 7/8/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/24/2020 WALLIE JONG
Hydrant and Access approval Cleared 9/24/2020 KURT CORRAL
Green Code Cleared 10/1/2020 AARON COSTA
Low Impact Development Cleared 10/29/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 11/10/2020 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/10/2022 Partial Inspection STEVEN BACK
PLUMBING-Rough 7/20/2022 Partial Approval STEVEN BACK
Footing/Foundation/Slab 9/1/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 11/30/2022 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 11/30/2022 Partial Approval STEVEN BACK
Deputy Wood Construction 2/3/2023 Conditional Approval MORRIS JACKSON
Pre-Inspection 2/6/2023 Not Ready for Inspection JON MCHUGH
PLUMBING-Rough 3/7/2023 Partial Approval ALEXANDER HANDY
BUILDING-Rough-Frame 6/9/2023 Corrections Issued ALEXANDER HANDY
ELECTRICAL-Rough 6/9/2023 Approved ALEXANDER HANDY
Green Building Rough 6/9/2023 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 7/11/2023 Partial Approval DAVID SCANTLIN
BUILDING-Rough-Frame 8/8/2023 Approved ALEXANDER HANDY
Interior/Exterior Lathing 8/8/2023 Partial Approval ALEXANDER HANDY
Insulation 9/1/2023 Approved MORRIS JACKSON
Drywall Nailing 9/8/2023 Approved ALEXANDER HANDY
Interior/Exterior Lathing 9/8/2023 Approved ALEXANDER HANDY
Sewer 3/15/2024 Approved ALEXANDER HANDY
Underground Mechanical 3/15/2024 Approved ALEXANDER HANDY
ELECTRICAL-Final 2/27/2025 Not Ready for Inspection ALEXANDER HANDY
Final 2/27/2025 Corrections Issued ALEXANDER HANDY
Green Building Final 2/27/2025 Not Ready for Inspection ALEXANDER HANDY
HVAC-Final 2/27/2025 Not Ready for Inspection ALEXANDER HANDY
PLUMBING-Final 2/27/2025 Not Ready for Inspection ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 2/27/2025 SGSOV Not Ready ALEXANDER HANDY
Smoke Detectors 2/27/2025 Approved ALEXANDER HANDY
ELECTRICAL-Final 8/13/2025 Approved ALEXANDER HANDY
Final 8/13/2025 OK to Issue CofO ALEXANDER HANDY
Green Building Final 8/13/2025 Approved ALEXANDER HANDY
HVAC-Final 8/13/2025 Approved ALEXANDER HANDY
PLUMBING-Final 8/13/2025 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 8/13/2025 SGSOV Approved ALEXANDER HANDY