9925 N COLLETT AVE 91343

Certificate Information: 9925 N COLLETT AVE 91343

Application / Permit
20010-20000-01325
Plan Check / Job No.
B20VN05682
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW FULLY SPRINKLERED 28'-8" X 59'-4" IRREG SHAPED DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A. 33(c) and (e)
Permit Issued
Issued on 1/19/2021
Issuing Office
Current Status
CofO Issued on 11/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2020 APPLICANT
Assigned to Plan Check Engineer 5/22/2020 JEROME MAGAT PALMA
Corrections Issued 5/26/2020 JEROME MAGAT PALMA
Quality Review Completed 5/27/2020 STEVEN KIM
Building Plans Picked Up 6/12/2020 APPLICANT
Green Plans Picked Up 12/16/2020 APPLICANT
Applicant returned to address corrections 1/7/2021 JEROME MAGAT PALMA
Plan Check Approved 1/19/2021 JEROME MAGAT PALMA
Issued 1/19/2021 APPLICANT
CofO in Progress 11/16/2021 MARK JOHNSON
CofO Issued 11/18/2021 MICHAEL SMITH
Permit Finaled 11/18/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/6/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 11/20/2020 GUILLERMO PETRA
Sewer availability Cleared 11/20/2020 GUILLERMO PETRA
Grading Pre-Inspection Cleared 12/15/2020 BRIAN MILLER
Low Impact Development Cleared 12/16/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 1/4/2021 GUILLERMO PETRA
GPI Written Notices Cleared 1/7/2021 JEROME MAGAT PALMA
Green Code Cleared 1/7/2021 JEROME MAGAT PALMA
Hydrant and Access approval Cleared 1/14/2021 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Martirossyan,, Armen; Lic. No.: C64223 802 PORTOLA AVE      GLENDALE, CA 91206

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/5/2021 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 2/5/2021 Partial Approval MARK JOHNSON
Underground Mechanical 2/5/2021 Partial Approval MARK JOHNSON
Footing/Foundation/Slab 2/12/2021 Corrections Issued MICHAEL TEMPLE
Footing/Foundation/Slab 2/18/2021 Approved MARK JOHNSON
ELECTRICAL-Rough 3/30/2021 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 3/30/2021 Corrections Issued MARK JOHNSON
PLUMBING-Rough 3/30/2021 Approved MARK JOHNSON
Sewer 3/30/2021 Approved MARK JOHNSON
Underground Mechanical 3/30/2021 Approved MARK JOHNSON
HVAC-Rough 4/8/2021 Corrections Issued MARK JOHNSON
BUILDING-Rough-Frame 4/19/2021 Partial Approval MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 4/19/2021 Partial Approval MARK JOHNSON
HVAC-Rough 4/19/2021 Approved MARK JOHNSON
Insulation 5/5/2021 Not Ready for Inspection MARK JOHNSON
Green Building Rough 5/11/2021 Approved MARK JOHNSON
Insulation 5/11/2021 Approved MARK JOHNSON
Verify Sprinkler Sign Off 5/11/2021 Approved MARK JOHNSON
Drywall Nailing 5/17/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 6/8/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 6/8/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 7/2/2021 Not Ready for Inspection MARK JOHNSON
Shower Pan 8/19/2021 Approved ADAM ESCOTO
Interior/Exterior Lathing 9/2/2021 Approved MARK JOHNSON
Shower Pan 9/2/2021 Approved MARK JOHNSON
ELECTRICAL-Final 10/25/2021 Approved MARK JOHNSON
Final 10/25/2021 Corrections Issued MARK JOHNSON
Green Building Final 10/25/2021 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 10/25/2021 SGSOV Approved MARK JOHNSON
Service/Power Release 10/25/2021 Approved MARK JOHNSON
Smoke Detectors 10/25/2021 Approved MARK JOHNSON
Final 10/28/2021 Corrections Issued MARK JOHNSON
Final 11/17/2021 OK to Issue CofO MARK JOHNSON