9188 N CAYUGA AVE 91352
Certificate Information: 9188 N CAYUGA AVE 91352
- Application / Permit
- 20010-20000-01314
- Plan Check / Job No.
- B20VN05657
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW 23'-0" X 18'-0" DETACHED PATIO COVER
- Permit Issued
- Issued on 5/21/2020
- Issuing Office
- Current Status
- CofO Issued on 3/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 4/29/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 5/21/2020 | COLIN LOREDO |
| Issued | 5/21/2020 | APPLICANT |
| CofO in Progress | 7/16/2020 | MICHAEL SMITH |
| Permit Finaled | 3/2/2021 | RONALD MYRICK |
| CofO Issued | 3/2/2021 | RONALD MYRICK |
| Permit Finaled | 3/2/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/1/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2020 | ADRIAN CASTRO |
| Miscellaneous | Cleared | 5/12/2020 | MIGUEL GAMBOA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/3/2020 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 6/3/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 6/3/2020 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 6/4/2020 | Approved | JOHN HAYES |
| PLUMBING-Rough | 6/4/2020 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 6/15/2020 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 6/15/2020 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 6/22/2020 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 6/22/2020 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 6/30/2020 | Not Ready for Inspection | PIERRE VEGA |
| Final | 6/30/2020 | Not Ready for Inspection | PIERRE VEGA |
| SGSOV-Seismic Gas S/O Valve | 6/30/2020 | SGSOV Not Ready | PIERRE VEGA |
| Service/Power Release | 6/30/2020 | Not Ready for Inspection | PIERRE VEGA |
| Smoke Detectors | 6/30/2020 | Corrections Issued | PIERRE VEGA |
| Verify Sprinkler Sign Off | 6/30/2020 | Not Ready for Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 7/8/2020 | Not Ready for Inspection | JOHN HAYES |
| Final | 7/8/2020 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 7/8/2020 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 7/8/2020 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 7/8/2020 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 7/8/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 7/13/2020 | Not Ready for Inspection | JOHN HAYES |
| Final | 7/13/2020 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 7/13/2020 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 7/13/2020 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 7/13/2020 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 7/13/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 7/15/2020 | Approved | JOHN HAYES |
| Final | 7/15/2020 | OK to Issue CofO | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 7/15/2020 | SGSOV Approved | JOHN HAYES |
| Service/Power Release | 7/15/2020 | Approved | JOHN HAYES |
| Smoke Detectors | 7/15/2020 | Approved | JOHN HAYES |
| Verify Sprinkler Sign Off | 7/15/2020 | Approved | JOHN HAYES |