7441 1/2 N BECKFORD AVE 91335

Certificate Information: 7441 1/2 N BECKFORD AVE 91335

Application / Permit
20010-20000-01295
Plan Check / Job No.
B20VN05550
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 50'-10" X 24'-1" DETACHED ONE STORY ACCESSORY DWELLING UNIT ALL WORK PER ENGINEERING
Permit Issued
Issued on 9/8/2020
Issuing Office
Current Status
CofO Issued on 10/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/12/2020 APPLICANT
Assigned to Plan Check Engineer 6/4/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 6/10/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 6/22/2020 OMID HEDAYAT
Building Plans Picked Up 6/25/2020 APPLICANT
Green Plans Picked Up 6/25/2020 APPLICANT
Plan Check Approved 9/1/2020 SEWADA ZADOORAN MILAGARDI
Issued 9/8/2020 APPLICANT
CofO in Progress 10/20/2021 VINCENT HANLEY
CofO Issued 10/23/2021 MICHAEL SMITH
Permit Finaled 10/23/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/1/2020 GABRIEL ROBLES
Construction near power lines Cleared 7/1/2020 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 7/1/2020 GABRIEL ROBLES
Sewer availability Cleared 7/1/2020 GABRIEL ROBLES
Hydrant and Access approval Cleared 8/7/2020 MATTHEW CRAIG
Low Impact Development Cleared 8/27/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 9/1/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/9/2020 Approved VINCENT HANLEY
PLUMBING-Rough 12/9/2020 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/30/2020 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 1/19/2021 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 1/19/2021 Approved VINCENT HANLEY
Green Building Rough 1/19/2021 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 1/19/2021 Approved VINCENT HANLEY
PLUMBING-Rough 1/19/2021 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 1/19/2021 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 1/27/2021 Partial Approval VINCENT HANLEY
Green Building Rough 1/27/2021 Approved VINCENT HANLEY
Insulation 1/27/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 1/27/2021 Approved VINCENT HANLEY
Drywall Nailing 2/1/2021 Approved VINCENT HANLEY
Underground Mechanical 3/17/2021 Partial Approval VINCENT HANLEY
Sewer 3/22/2021 Approved VINCENT HANLEY
Underground Mechanical 3/22/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 10/12/2021 Partial Approval VINCENT HANLEY
ELECTRICAL-Final 10/12/2021 Approved VINCENT HANLEY
Final 10/12/2021 Corrections Issued VINCENT HANLEY
Gas Test 10/12/2021 Approved VINCENT HANLEY
Green Building Final 10/12/2021 Approved VINCENT HANLEY
HVAC-Final 10/12/2021 Approved VINCENT HANLEY
PLUMBING-Final 10/12/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 10/12/2021 SGSOV Approved VINCENT HANLEY
Service/Power Release 10/12/2021 Not Ready for Inspection VINCENT HANLEY
Smoke Detectors 10/12/2021 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 10/12/2021 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 10/20/2021 Approved VINCENT HANLEY
Final 10/20/2021 OK to Issue CofO VINCENT HANLEY
Service/Power Release 10/20/2021 Approved VINCENT HANLEY