- (N) IRREGULAR SHAPED 111' X 78' SINGLE FAMILY DWELLING WITH ATTCHED THREE-CAR GARAGE AND 30' X 9' COVERED PORCH AND AND ATTACHED 22' X 18' -11" TRELLIS ALL WORK PER ENGINEERING NFPA 13D FIRE SPRINKLERS REQUIRED
- Permit Issued
- Issued on 5/5/2021
- Issuing Office
- Current Status
- CofO Issued on 4/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 6/10/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 6/17/2020 | STEVEN KIM |
| Building Plans Picked Up | 6/18/2020 | APPLICANT |
| Green Plans Picked Up | 6/18/2020 | APPLICANT |
| Applicant returned to address corrections | 2/8/2021 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 3/17/2021 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 3/18/2021 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 3/23/2021 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 3/31/2021 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 5/5/2021 | SEWADA ZADOORAN MILAGARDI |
| Issued | 5/5/2021 | APPLICANT |
| CofO in Progress | 3/7/2025 | RYAN SALAZAR |
| Permit Finaled | 4/11/2025 | RUBEN SALAS |
| CofO Issued | 4/11/2025 | RUBEN SALAS |
| Permit Finaled | 4/11/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Highway dedication | Cleared | 7/24/2020 | JOHN TRIANTAFYLLOS |
| Permit | Cleared | 7/27/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 8/3/2020 | JOHN TRIANTAFYLLOS |
| Trees in Parkway | Cleared | 8/13/2020 | JOHN KIM |
| Hydrant and Access approval | Cleared | 8/27/2020 | MATTHEW CRAIG |
| Disturb/Remove Protected Trees | Cleared | 1/12/2021 | SEWADA ZADOORAN MILAGARDI |
| Low Impact Development | Cleared | 2/8/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 4/20/2021 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 5/11/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| PLUMBING-Rough | 5/11/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Pre-Inspection | 5/11/2021 | Corrections Issued | MICHAEL TEMPLE |
| Sewer | 5/11/2021 | Corrections Issued | MICHAEL TEMPLE |
| Underground Mechanical | 5/11/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| PLUMBING-Rough | 5/20/2021 | Corrections Issued | MICHAEL TEMPLE |
| Sewer | 5/20/2021 | Partial Approval | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 6/15/2021 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 6/15/2021 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 6/21/2021 | Approved | ARTHUR SARGSYAN |
| Sewer | 6/21/2021 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 7/2/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 7/3/2021 | Corrections Issued | DANIEL ORRANTE |
| Excavation/Setback/Form/Re-Bar | 7/9/2021 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 8/16/2021 | Corrections Issued | RICHARD DOCKUS |
| Wood Frame | 10/6/2021 | Partial Approval | RICHARD DOCKUS |
| ELECTRICAL-Rough | 2/18/2022 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 2/18/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 2/18/2022 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 3/25/2022 | Corrections Issued | RICHARD DOCKUS |
| Green Building Rough | 3/31/2022 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 3/31/2022 | Approved | RICHARD DOCKUS |
| Verify Sprinkler Sign Off | 3/31/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Wood Frame | 3/31/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 4/4/2022 | Corrections Issued | RICHARD DOCKUS |
| Verify Sprinkler Sign Off | 4/4/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 4/11/2022 | Approved | RICHARD DOCKUS |
| Verify Sprinkler Sign Off | 4/11/2022 | Approved | RICHARD DOCKUS |
| Insulation | 4/14/2022 | Corrections Issued | ALAN MORELOS |
| Interior/Exterior Lathing | 4/14/2022 | Partial Approval | ALAN MORELOS |
| Shower Pan | 4/29/2022 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 5/16/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Drywall Nailing | 5/24/2022 | Approved | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 5/24/2022 | Approved | MICHAEL TEMPLE |
| ELECTRICAL-Final | 8/25/2023 | Approved | RYAN SALAZAR |
| Final | 7/30/2024 | Not Ready for Inspection | JOSE AVILA |
| Footing/Foundation/Slab | 7/30/2024 | Not Ready for Inspection | JOSE AVILA |
| Green Building Final | 7/30/2024 | Not Ready for Inspection | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 7/30/2024 | SGSOV Not Ready | JOSE AVILA |
| Service/Power Release | 7/30/2024 | Not Ready for Inspection | JOSE AVILA |
| Smoke Detectors | 7/30/2024 | Not Ready for Inspection | JOSE AVILA |
| Gas Test | 8/19/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 8/19/2024 | Approved | RYAN SALAZAR |
| Service/Power Release | 8/27/2024 | Approved | RYAN SALAZAR |
| Final | 10/10/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Footing/Foundation/Slab | 10/10/2024 | Approved | RYAN SALAZAR |
| Green Building Final | 10/10/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 10/10/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 10/10/2024 | Approved | RYAN SALAZAR |
| Final | 2/3/2025 | Partial Approval | RYAN SALAZAR |
| Final | 3/10/2025 | OK to Issue CofO | RYAN SALAZAR |