12405 W PIERCE ST 91331

Certificate Information: 12405 W PIERCE ST 91331

Application / Permit
20010-20000-01282
Plan Check / Job No.
B20VN05538
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 23' x 42' ONE-STORY ACCESSORY DWELLING UNIT. ALL WORK PER WFPP.
Permit Issued
Issued on 9/14/2020
Issuing Office
Current Status
CofO Issued on 10/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/13/2020 APPLICANT
Assigned to Plan Check Engineer 4/30/2020 SEAN SHAHMIRI
Corrections Issued 5/6/2020 SEAN SHAHMIRI
Quality Review Completed 5/11/2020 OMID HEDAYAT
Building Plans Picked Up 5/19/2020 APPLICANT
Applicant returned to address corrections 8/12/2020 SEAN SHAHMIRI
Green Plans Picked Up 8/12/2020 APPLICANT
Applicant returned to address corrections 8/25/2020 SEAN SHAHMIRI
Plan Check Approved 9/14/2020 SEAN SHAHMIRI
Issued 9/14/2020 APPLICANT
CofO in Progress 10/25/2022 MICHEL ABAJAN
Permit Finaled 10/26/2022 RONALD MYRICK
CofO Issued 10/26/2022 RONALD MYRICK
Permit Finaled 10/26/2022 RONALD MYRICK

Permit Application Clearance Information

Hydrant and Access approval Cleared 6/25/2020 KURT CORRAL
Low Impact Development Cleared 7/16/2020 ORVAL HERNANDEZ-MARCI
Address approval Cleared 7/29/2020 GABRIEL ROBLES
ZA Case Cleared 7/29/2020 PABLO ESTRADA
Eng Process Fee Ord 176,300 Cleared 7/30/2020 GABRIEL ROBLES
Sewer availability Cleared 7/30/2020 GABRIEL ROBLES
Green Code Cleared 8/14/2020 MICHAEL AYERS
Roof/Waste drainage to street Cleared 9/4/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/16/2021 Corrections Issued MICHEL ABAJAN
Underground Mechanical 6/16/2021 Partial Approval MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 8/24/2021 Partial Inspection MICHEL ABAJAN
Footing/Foundation/Slab 8/24/2021 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 8/24/2021 Partial Approval MICHEL ABAJAN
Deputy Drilled-In Anchors 8/25/2021 No Access for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 8/27/2021 Approved MICHEL ABAJAN
Deputy Drilled-In Anchors 10/21/2021 No Access for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 10/25/2021 Partial Approval MICHEL ABAJAN
Green Building Rough 10/25/2021 Partial Inspection MICHEL ABAJAN
Verify Sprinkler Sign Off 10/25/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 11/19/2021 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 11/19/2021 Approved MICHEL ABAJAN
Green Building Rough 11/19/2021 Not Ready for Inspection MICHEL ABAJAN
HVAC-Rough 11/19/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 11/19/2021 Partial Approval MICHEL ABAJAN
Interior/Exterior Lathing 12/3/2021 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 12/3/2021 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 12/28/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 12/29/2021 Approved MICHEL ABAJAN
Green Building Rough 12/29/2021 Approved MICHEL ABAJAN
HVAC-Rough 3/17/2022 Approved MICHEL ABAJAN
Insulation 3/17/2022 Approved MICHEL ABAJAN
Drywall Nailing 3/29/2022 Approved DEANDRE HOFFMAN
Shower Pan 3/29/2022 Approved DEANDRE HOFFMAN
Pre-Inspection 8/1/2022 Partial Inspection MICHEL ABAJAN
ELECTRICAL-Final 10/5/2022 Approved MICHEL ABAJAN
Final 10/5/2022 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 10/5/2022 Approved MICHEL ABAJAN
HVAC-Final 10/5/2022 Approved MICHEL ABAJAN
PLUMBING-Final 10/5/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 10/5/2022 SGSOV Approved MICHEL ABAJAN
Service/Power Release 10/5/2022 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 10/5/2022 Approved MICHEL ABAJAN
Final 10/12/2022 Not Ready for Inspection MICHEL ABAJAN
Service/Power Release 10/12/2022 Not Ready for Inspection MICHEL ABAJAN
Final 10/25/2022 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 10/25/2022 Approved MICHEL ABAJAN