16105 W PARTHENIA ST 91343

Certificate Information: 16105 W PARTHENIA ST 91343

Application / Permit
20010-20000-01280
Plan Check / Job No.
B20VN05533
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) & ATTACHED 2-CAR GARAGE
Permit Issued
Issued on 4/30/2021
Issuing Office
Current Status
CofO Issued on 12/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2020 APPLICANT
Assigned to Plan Check Engineer 5/21/2020 NILOOFAR MEHRAIN
Corrections Issued 5/28/2020 NILOOFAR MEHRAIN
Quality Review Completed 5/28/2020 STEVEN KIM
Building Plans Picked Up 6/1/2020 APPLICANT
Green Plans Picked Up 6/1/2020 APPLICANT
Plan Check Approved 4/23/2021 NILOOFAR MEHRAIN
Issued 4/30/2021 APPLICANT
CofO in Progress 12/2/2022 RAUL OLAGI
Permit Finaled 12/17/2022 MICHAEL SMITH
CofO Issued 12/17/2022 MICHAEL SMITH
Permit Finaled 12/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Hydrant and Access approval Cleared 7/1/2020 KURT CORRAL
Address approval Cleared 1/11/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/11/2021 ADRIAN CASTRO
Permit Cleared 1/11/2021 ADRIAN CASTRO
Sewer availability Cleared 1/11/2021 ADRIAN CASTRO
Low Impact Development Cleared 1/14/2021 SARAH YOUSSEF
Construction near power lines Cleared 1/15/2021 WALTER RAMIREZ
Construction within easement Cleared 1/15/2021 WALTER RAMIREZ
Trees in Parkway Cleared 1/28/2021 JOHN KIM
Roof/Waste drainage to street Cleared 2/19/2021 GUILLERMO PETRA
Green Code Cleared 3/25/2021 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/1/2021 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 12/13/2021 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 12/20/2021 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 1/13/2022 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 4/4/2022 Approved RAUL OLAGI
HVAC-Rough 4/4/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 4/4/2022 Corrections Issued RAUL OLAGI
Underground Mechanical 4/4/2022 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 4/18/2022 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/18/2022 Partial Approval RAUL OLAGI
HVAC-Rough 4/18/2022 Approved RAUL OLAGI
Verify Sprinkler Sign Off 4/18/2022 Approved RAUL OLAGI
Deputy Wood Construction 4/21/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/21/2022 Approved RAUL OLAGI
PLUMBING-Rough 4/21/2022 Approved RAUL OLAGI
Underground Mechanical 4/21/2022 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 5/9/2022 Approved RAUL OLAGI
Green Building Rough 5/9/2022 Not Ready for Inspection RAUL OLAGI
Shower Pan 5/9/2022 Approved RAUL OLAGI
Green Building Rough 5/16/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 5/16/2022 Partial Approval RAUL OLAGI
Insulation 5/23/2022 Corrections Issued ALAN MORELOS
Insulation 5/25/2022 Approved RAUL OLAGI
Drywall Nailing 6/2/2022 Approved DEANDRE HOFFMAN
Underground Mechanical 7/21/2022 Approved DEANDRE HOFFMAN
ELECTRICAL-Final 9/14/2022 Corrections Issued RAUL OLAGI
Final 9/14/2022 Corrections Issued RAUL OLAGI
Gas Test 9/14/2022 Approved RAUL OLAGI
HVAC-Final 9/14/2022 Corrections Issued RAUL OLAGI
PLUMBING-Final 9/14/2022 Approved RAUL OLAGI
Service/Power Release 9/14/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Final 12/2/2022 Approved RAUL OLAGI
Final 12/2/2022 OK to Issue CofO RAUL OLAGI
Green Building Final 12/2/2022 Approved RAUL OLAGI
HVAC-Final 12/2/2022 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 12/2/2022 SGSOV Approved RAUL OLAGI
Service/Power Release 12/2/2022 Approved RAUL OLAGI
Smoke Detectors 12/2/2022 Approved RAUL OLAGI