16105 W PARTHENIA ST 91343
Certificate Information: 16105 W PARTHENIA ST 91343
- Application / Permit
- 20010-20000-01280
- Plan Check / Job No.
- B20VN05533
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) & ATTACHED 2-CAR GARAGE
- Permit Issued
- Issued on 4/30/2021
- Issuing Office
- Current Status
- CofO Issued on 12/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 5/28/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 5/28/2020 | STEVEN KIM |
| Building Plans Picked Up | 6/1/2020 | APPLICANT |
| Green Plans Picked Up | 6/1/2020 | APPLICANT |
| Plan Check Approved | 4/23/2021 | NILOOFAR MEHRAIN |
| Issued | 4/30/2021 | APPLICANT |
| CofO in Progress | 12/2/2022 | RAUL OLAGI |
| Permit Finaled | 12/17/2022 | MICHAEL SMITH |
| CofO Issued | 12/17/2022 | MICHAEL SMITH |
| Permit Finaled | 12/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 7/1/2020 | KURT CORRAL |
| Address approval | Cleared | 1/11/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2021 | ADRIAN CASTRO |
| Permit | Cleared | 1/11/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 1/11/2021 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 1/14/2021 | SARAH YOUSSEF |
| Construction near power lines | Cleared | 1/15/2021 | WALTER RAMIREZ |
| Construction within easement | Cleared | 1/15/2021 | WALTER RAMIREZ |
| Trees in Parkway | Cleared | 1/28/2021 | JOHN KIM |
| Roof/Waste drainage to street | Cleared | 2/19/2021 | GUILLERMO PETRA |
| Green Code | Cleared | 3/25/2021 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/1/2021 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 12/13/2021 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 12/20/2021 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2022 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 4/4/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 4/4/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 4/4/2022 | Corrections Issued | RAUL OLAGI |
| Underground Mechanical | 4/4/2022 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 4/18/2022 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2022 | Partial Approval | RAUL OLAGI |
| HVAC-Rough | 4/18/2022 | Approved | RAUL OLAGI |
| Verify Sprinkler Sign Off | 4/18/2022 | Approved | RAUL OLAGI |
| Deputy Wood Construction | 4/21/2022 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 4/21/2022 | Approved | RAUL OLAGI |
| Underground Mechanical | 4/21/2022 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/9/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 5/9/2022 | Not Ready for Inspection | RAUL OLAGI |
| Shower Pan | 5/9/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 5/16/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 5/16/2022 | Partial Approval | RAUL OLAGI |
| Insulation | 5/23/2022 | Corrections Issued | ALAN MORELOS |
| Insulation | 5/25/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 6/2/2022 | Approved | DEANDRE HOFFMAN |
| Underground Mechanical | 7/21/2022 | Approved | DEANDRE HOFFMAN |
| ELECTRICAL-Final | 9/14/2022 | Corrections Issued | RAUL OLAGI |
| Final | 9/14/2022 | Corrections Issued | RAUL OLAGI |
| Gas Test | 9/14/2022 | Approved | RAUL OLAGI |
| HVAC-Final | 9/14/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 9/14/2022 | Approved | RAUL OLAGI |
| Service/Power Release | 9/14/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Final | 12/2/2022 | Approved | RAUL OLAGI |
| Final | 12/2/2022 | OK to Issue CofO | RAUL OLAGI |
| Green Building Final | 12/2/2022 | Approved | RAUL OLAGI |
| HVAC-Final | 12/2/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 12/2/2022 | SGSOV Approved | RAUL OLAGI |
| Service/Power Release | 12/2/2022 | Approved | RAUL OLAGI |
| Smoke Detectors | 12/2/2022 | Approved | RAUL OLAGI |