16304 W CHASE ST 91343

Certificate Information: 16304 W CHASE ST 91343

Application / Permit
20010-20000-01264
Plan Check / Job No.
B20VN05505
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 61' x 72'-7" TWO-STORY SINGLE FAMILY DWELLING W/ ATTACHED GARAGE AND ATT. OPEN TRELLIS. AUTOMATIC SPRINKLER SYSTEM IS REQUIRED.
Permit Issued
Issued on 12/7/2020
Issuing Office
Current Status
CofO Issued on 7/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/14/2020 APPLICANT
Assigned to Plan Check Engineer 4/30/2020 SEAN SHAHMIRI
Corrections Issued 5/4/2020 SEAN SHAHMIRI
Quality Review Completed 5/4/2020 OMID HEDAYAT
Building Plans Picked Up 5/7/2020 APPLICANT
Green Plans Picked Up 5/14/2020 APPLICANT
Applicant returned to address corrections 11/24/2020 SEAN SHAHMIRI
Plan Check Approved 11/24/2020 SEAN SHAHMIRI
Issued 12/7/2020 APPLICANT
CofO in Progress 7/7/2023 RAUL OLAGI
Permit Finaled 7/20/2023 MICHAEL SMITH
CofO Issued 7/20/2023 MICHAEL SMITH
Permit Finaled 7/20/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/22/2020 ADRIAN CASTRO
Permit Cleared 7/22/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 7/23/2020 ADRIAN CASTRO
Miscellaneous Cleared 7/23/2020 MIGUEL GAMBOA
Miscellaneous Cleared 7/23/2020 MIGUEL GAMBOA
Sewer availability Cleared 7/23/2020 ADRIAN CASTRO
ZI Cleared 7/24/2020 MIGUEL GAMBOA
Trees in Parkway Cleared 7/29/2020 JOHN KIM
Low Impact Development Cleared 9/4/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 9/9/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 10/19/2020 KURT CORRAL
Green Code Cleared 11/24/2020 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Mejia,, Fernando Finuliar; Lic. No.: C54382 8305 DUCOR AVE      WEST HILLS, CA 91304

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/25/2021 Approved ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 3/1/2021 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 3/1/2021 Approved ARTHUR SARGSYAN
Deputy Reinf. Concrete 3/2/2021 Approved ARTHUR SARGSYAN
Wood Frame 4/8/2021 Partial Approval ARTHUR SARGSYAN
BUILDING-Rough-Frame 6/2/2021 Not Ready for Inspection ARTHUR SARGSYAN
Green Building Rough 6/2/2021 Not Ready for Inspection ARTHUR SARGSYAN
Verify Sprinkler Sign Off 6/2/2021 Not Ready for Inspection ARTHUR SARGSYAN
PLUMBING-Rough 7/26/2021 Partial Approval TROY SANDERS
Underground Mechanical 7/26/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 8/24/2021 No Access for Inspection JOHN HAYES
Green Building Rough 8/24/2021 No Access for Inspection JOHN HAYES
Verify Sprinkler Sign Off 8/24/2021 No Access for Inspection JOHN HAYES
Interior/Exterior Lathing 9/14/2021 Corrections Issued JACK KARGODORIAN
Interior/Exterior Lathing 9/28/2021 Not Ready for Inspection JACK KARGODORIAN
Rough-Elec/Plmb/HVAC 9/28/2021 Corrections Issued JACK KARGODORIAN
BUILDING-Rough-Frame 10/6/2021 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 10/6/2021 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Rough 10/6/2021 Not Ready for Inspection JACK KARGODORIAN
Verify Sprinkler Sign Off 10/6/2021 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 10/13/2021 Corrections Issued RAUL OLAGI
Green Building Rough 10/13/2021 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 10/13/2021 Corrections Issued RAUL OLAGI
PLUMBING-Rough 10/13/2021 Approved RAUL OLAGI
Special/Order Compliance 10/13/2021 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 10/18/2021 Approved RAUL OLAGI
Green Building Rough 10/18/2021 Approved RAUL OLAGI
Interior/Exterior Lathing 10/18/2021 Partial Approval RAUL OLAGI
Special/Order Compliance 10/18/2021 Corrections Issued RAUL OLAGI
Insulation 11/2/2021 Corrections Issued RAUL OLAGI
Insulation 11/8/2021 Approved RAUL OLAGI
Drywall Nailing 11/15/2021 Approved ALAN MORELOS
Shower Pan 12/16/2021 Approved RAUL OLAGI
Interior/Exterior Lathing 1/6/2022 Approved RAUL OLAGI
Gas Test 6/16/2022 Not Ready for Inspection ALAN MORELOS
Gas Test 7/20/2022 Approved DEANDRE HOFFMAN
ELECTRICAL-Final 11/15/2022 Not Ready for Inspection RAUL OLAGI
ELECTRICAL-Final 12/15/2022 Corrections Issued DAVID MATSON
HVAC-Final 12/15/2022 Corrections Issued DAVID MATSON
PLUMBING-Final 12/15/2022 Corrections Issued DAVID MATSON
ELECTRICAL-Final 2/8/2023 Approved RAUL OLAGI
HVAC-Final 2/8/2023 Approved RAUL OLAGI
PLUMBING-Final 2/8/2023 Approved RAUL OLAGI
Sewer 2/8/2023 Approved RAUL OLAGI
Underground Mechanical 2/8/2023 Not Ready for Inspection RAUL OLAGI
Final 6/28/2023 Corrections Issued RAUL OLAGI
Green Building Final 6/28/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 6/28/2023 SGSOV Not Ready RAUL OLAGI
Smoke Detectors 6/28/2023 Approved RAUL OLAGI
Final 7/7/2023 OK to Issue CofO RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 7/7/2023 SGSOV Approved RAUL OLAGI
Service/Power Release 7/7/2023 Approved RAUL OLAGI