6415 N WILBUR AVE 91335

Certificate Information: 6415 N WILBUR AVE 91335

Application / Permit
20010-20000-01262
Plan Check / Job No.
B20VN05501
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 30' X 20' (2) STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 11/20/2020
Issuing Office
Current Status
CofO Issued on 4/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2020 APPLICANT
Assigned to Plan Check Engineer 4/30/2020 SELLA BENYAMIN
Corrections Issued 5/5/2020 SELLA BENYAMIN
Quality Review Completed 5/7/2020 STEVEN KIM
Building Plans Picked Up 5/12/2020 APPLICANT
Green Plans Picked Up 5/14/2020 APPLICANT
Applicant returned to address corrections 10/21/2020 SELLA BENYAMIN
Applicant returned to address corrections 11/13/2020 SELLA BENYAMIN
Plan Check Approved 11/20/2020 SELLA BENYAMIN
Issued 11/20/2020 APPLICANT
CofO in Progress 3/23/2022 SEAN HAUPT
CofO Issued 4/11/2022 MICHAEL SMITH
Permit Finaled 4/11/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/14/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 5/15/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 5/15/2020 JOHN TRIANTAFYLLOS
Green Code Cleared 6/12/2020 DAVID MATSON
ZI Cleared 10/2/2020 LAUREN PADICK
Low Impact Development Cleared 10/6/2020 ORVAL HERNANDEZ-MARCI
Hydrant and Access approval Cleared 11/2/2020 KURT CORRAL
Roof/Waste drainage to street Cleared 11/2/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 14545 VICTORY BLVD 405      VAN NUYS, CA 91411

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/1/2020 Corrections Issued STEVEN BACK
PLUMBING-Rough 12/1/2020 Partial Approval STEVEN BACK
Sewer 12/1/2020 Approved STEVEN BACK
Excavation/Setback/Form/Re-Bar 12/14/2020 Approved STEVEN BACK
Footing/Foundation/Slab 12/14/2020 Approved STEVEN BACK
Underground Mechanical 12/23/2020 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 1/7/2021 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/26/2021 Partial Approval VINCENT HANLEY
PLUMBING-Rough 1/29/2021 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 2/19/2021 Not Ready for Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 2/19/2021 Corrections Issued STEVEN BACK
Green Building Rough 2/19/2021 Not Ready for Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 2/25/2021 Corrections Issued STEVEN BACK
Green Building Rough 2/25/2021 Not Ready for Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 3/25/2021 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 3/30/2021 Corrections Issued STEVEN BACK
HVAC-Rough 3/30/2021 Approved STEVEN BACK
PLUMBING-Rough 3/30/2021 Approved STEVEN BACK
ELECTRICAL-Rough 4/5/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 4/8/2021 Corrections Issued STEVEN BACK
Final 4/8/2021 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 4/8/2021 Corrections Issued STEVEN BACK
Green Building Rough 4/8/2021 Not Ready for Inspection STEVEN BACK
Interior/Exterior Lathing 4/8/2021 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 4/16/2021 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 4/16/2021 Corrections Issued STEVEN BACK
Green Building Rough 4/16/2021 Approved STEVEN BACK
Interior/Exterior Lathing 4/16/2021 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 4/23/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 4/23/2021 Approved STEVEN BACK
Insulation 4/23/2021 Approved STEVEN BACK
Drywall Nailing 4/29/2021 Approved STEVEN BACK
Wood Frame 8/19/2021 No Access for Inspection STEVEN BACK
Wood Frame 12/6/2021 Not Ready for Inspection SEAN HAUPT
Final 12/21/2021 Corrections Issued SEAN HAUPT
Green Building Final 12/21/2021 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 12/21/2021 SGSOV Approved SEAN HAUPT
Service/Power Release 12/21/2021 Corrections Issued SEAN HAUPT
Smoke Detectors 12/21/2021 Corrections Issued SEAN HAUPT
ELECTRICAL-Final 3/23/2022 Approved SEAN HAUPT
Final 3/23/2022 OK to Issue CofO SEAN HAUPT
Green Building Final 3/23/2022 Approved SEAN HAUPT
HVAC-Final 3/23/2022 Approved SEAN HAUPT
PLUMBING-Final 3/23/2022 Approved SEAN HAUPT
Service/Power Release 3/23/2022 Approved SEAN HAUPT
Smoke Detectors 3/23/2022 Approved SEAN HAUPT