4907 N VALJEAN AVE 91436

Certificate Information: 4907 N VALJEAN AVE 91436

Application / Permit
20010-20000-01220
Plan Check / Job No.
B20VN05438
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW (11' X 21') DETACHED RECREATION ROOM BUILDING WITH 1/2 BATH (4'6" X 4'6") & EXTERIOR ACCESS STORAGE (5'6" X 5'6") WITH ATTACHED CANTILEVERED TRELLIS (6'3" X 21') PER ENGINEER DESIGN.
Permit Issued
Issued on 6/3/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 5/26/2020 ROSENDO MEDINA
Issued 6/3/2020 LADBS
CofO in Progress 2/16/2021 RONALD COWAN
Permit Finaled 2/19/2021 DONALD SUNSERI
CofO Issued 2/19/2021 DONALD SUNSERI
Permit Finaled 2/19/2021 DONALD SUNSERI

Permit Application Clearance Information

Construction near power lines Cleared 4/22/2020 RIDWAN HARDY
Roof/Waste drainage to street Cleared 4/22/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/23/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Askarian,, Soroosh Namaghi; Lic. No.: C83413 22287 MULHOLLAND HWY 163      CALABASAS, CA 91302

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/9/2020 Approved RONALD COWAN
Footing/Foundation/Slab 6/9/2020 Approved RONALD COWAN
Underground Mechanical 6/9/2020 Approved RONALD COWAN
ELECTRICAL-Rough 6/15/2020 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 6/15/2020 Approved RONALD COWAN
HVAC-Rough 6/15/2020 Approved RONALD COWAN
Interior/Exterior Lathing 6/15/2020 Approved RONALD COWAN
PLUMBING-Rough 6/15/2020 Approved RONALD COWAN
BUILDING-Rough-Frame 6/19/2020 Not Ready for Inspection RONALD COWAN
Green Building Rough 6/19/2020 Approved RONALD COWAN
Verify Sprinkler Sign Off 6/19/2020 Not Ready for Inspection RONALD COWAN
BUILDING-Rough-Frame 6/22/2020 Partial Approval RONALD COWAN
Insulation 6/22/2020 Approved RONALD COWAN
Drywall Nailing 6/26/2020 Approved RONALD COWAN
BUILDING-Rough-Frame 2/2/2021 Approved RONALD COWAN
Final 2/2/2021 Corrections Issued RONALD COWAN
Green Building Final 2/2/2021 Approved RONALD COWAN
SGSOV-Seismic Gas S/O Valve 2/2/2021 SGSOV Approved RONALD COWAN
Service/Power Release 2/2/2021 Approved RONALD COWAN
Smoke Detectors 2/2/2021 Approved RONALD COWAN
Verify Sprinkler Sign Off 2/2/2021 Approved RONALD COWAN
Final 2/11/2021 OK to Issue CofO RONALD COWAN