7456 1/2 N VASSAR AVE 91303

Certificate Information: 7456 1/2 N VASSAR AVE 91303

Application / Permit
20010-20000-01187
Plan Check / Job No.
B20VN05432
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 26'0"X40'0" 1-STORY ACCESSORY DWELLING UNIT
Permit Issued
Issued on 11/1/2021
Issuing Office
Valley
Current Status
CofO Issued on 2/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2020 APPLICANT
Assigned to Plan Check Engineer 5/21/2020 MARVEL DELACRUZ
Corrections Issued 5/27/2020 MARVEL DELACRUZ
Quality Review Completed 5/28/2020 STEVEN KIM
Green Plans Picked Up 5/28/2020 APPLICANT
Building Plans Picked Up 7/27/2020 APPLICANT
Applicant returned to address corrections 7/2/2021 MARVEL DELACRUZ
Applicant returned to address corrections 9/15/2021 MARVEL DELACRUZ
Applicant returned to address corrections 10/6/2021 MARVEL DELACRUZ
Plan Check Approved 10/22/2021 MARVEL DELACRUZ
Issued 11/1/2021 APPLICANT
CofO in Progress 2/10/2023 ALEXANDER HANDY
Permit Finaled 2/23/2023 JOHN JANSON
CofO Issued 2/23/2023 JOHN JANSON
Permit Finaled 2/23/2023 JOHN JANSON

Permit Application Clearance Information

Green Code Cleared 8/7/2020 DAVID MATSON
Hydrant and Access approval Cleared 4/13/2021 MATTHEW CRAIG
Low Impact Development Cleared 6/18/2021 JORGE MEJIA LEMUS
Address approval Cleared 7/22/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 7/23/2021 GABRIEL ROBLES
Sewer availability Cleared 7/23/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 7/29/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Rahman,, Moksudur; Lic. No.: C69263 14616 MCKENDREE AVE      CHINO, CA 91708

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/4/2022 Corrections Issued STEVEN BACK
Piling/Pier/Caisson 3/4/2022 Not Ready for Inspection STEVEN BACK
Pre-Inspection 3/4/2022 Partial Inspection STEVEN BACK
Footing/Foundation/Slab 3/15/2022 No Access for Inspection STEVEN BACK
Excavation/Setback/Form/Re-Bar 3/21/2022 Approved STEVEN BACK
Footing/Foundation/Slab 3/21/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 4/29/2022 Partial Approval STEVEN BACK
PLUMBING-Rough 4/29/2022 Partial Approval STEVEN BACK
Sewer 4/29/2022 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/16/2022 Partial Approval JESUS PINEDA
Insulation 5/16/2022 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 8/23/2022 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 8/23/2022 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 8/23/2022 Approved STEVEN BACK
Green Building Rough 8/23/2022 Not Ready for Inspection STEVEN BACK
HVAC-Rough 8/23/2022 Approved STEVEN BACK
PLUMBING-Rough 8/23/2022 Approved STEVEN BACK
Verify Sprinkler Sign Off 8/23/2022 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 8/31/2022 Conditional Approval STEVEN BACK
Green Building Rough 8/31/2022 Not Ready for Inspection STEVEN BACK
Verify Sprinkler Sign Off 8/31/2022 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 9/7/2022 Approved STEVEN BACK
Green Building Rough 9/7/2022 Approved STEVEN BACK
Interior/Exterior Lathing 9/7/2022 Partial Approval STEVEN BACK
Drywall Nailing 10/11/2022 Approved STEVEN BACK
Insulation 10/11/2022 Approved STEVEN BACK
ELECTRICAL-Final 12/16/2022 Corrections Issued ALEXANDER HANDY
Service/Power Release 12/16/2022 Not Ready for Inspection ALEXANDER HANDY
Smoke Detectors 12/16/2022 Not Ready for Inspection ALEXANDER HANDY
ELECTRICAL-Final 1/17/2023 Approved ALEXANDER HANDY
Service/Power Release 1/17/2023 Not Ready for Inspection ALEXANDER HANDY
Smoke Detectors 1/17/2023 Not Ready for Inspection ALEXANDER HANDY
PLUMBING-Final 1/23/2023 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 1/23/2023 SGSOV Approved ALEXANDER HANDY
Service/Power Release 1/23/2023 Not Ready for Inspection ALEXANDER HANDY
Gas Test 1/27/2023 Approved ALEXANDER HANDY
PLUMBING-Final 1/27/2023 Approved ALEXANDER HANDY
Final 2/6/2023 Not Ready for Inspection ALEXANDER HANDY
Green Building Final 2/6/2023 Not Ready for Inspection ALEXANDER HANDY
Service/Power Release 2/6/2023 Not Ready for Inspection ALEXANDER HANDY
Smoke Detectors 2/6/2023 Approved ALEXANDER HANDY
Final 2/9/2023 OK to Issue CofO ALEXANDER HANDY
Green Building Final 2/9/2023 Approved ALEXANDER HANDY
HVAC-Final 2/9/2023 Approved ALEXANDER HANDY
Service/Power Release 2/9/2023 Approved ALEXANDER HANDY