9609 N COMANCHE AVE 91311
Certificate Information: 9609 N COMANCHE AVE 91311
- Application / Permit
- 20010-20000-01162
- Plan Check / Job No.
- B20VN05319
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) DETACHED 1-STORY ACCESSORY DWELLING UNIT PER 12.22A33(c) & (d)
- Permit Issued
- Issued on 12/19/2020
- Issuing Office
- Current Status
- CofO Issued on 2/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 5/7/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 5/7/2020 | STEVEN KIM |
| Green Plans Picked Up | 5/8/2020 | APPLICANT |
| Building Plans Picked Up | 5/13/2020 | APPLICANT |
| Plan Check Approved | 9/8/2020 | NILOOFAR MEHRAIN |
| Issued | 12/19/2020 | APPLICANT |
| CofO in Progress | 2/26/2022 | JEFFREY PARD |
| Permit Finaled | 2/28/2022 | JOHN JANSON |
| CofO Issued | 2/28/2022 | JOHN JANSON |
| Permit Finaled | 2/28/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/21/2020 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2020 | JOHN LIN |
| Sewer availability | Cleared | 5/21/2020 | JOHN LIN |
| Hydrant and Access approval | Cleared | 6/2/2020 | GEORGE SUCHAND |
| Green Code | Cleared | 6/3/2020 | DAVID MATSON |
| Construction near power lines | Cleared | 9/8/2020 | WALTER RAMIREZ |
| Construction within easement | Cleared | 9/8/2020 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 10/20/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 10/27/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Allstar Builders Inc; Lic. No.: 980161-B | 22647 VENTURA BLVD #588 WOODLAND HILLS, CA 91364 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/2/2021 | Corrections Issued | JEFFREY PARD |
| PLUMBING-Rough | 3/8/2021 | Not Ready for Inspection | JEFFREY PARD |
| Excavation/Setback/Form/Re-Bar | 3/11/2021 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 3/11/2021 | Partial Approval | JEFFREY PARD |
| Wood Frame | 4/8/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 4/27/2021 | Approved | JEFFREY PARD |
| HVAC-Rough | 4/27/2021 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 4/27/2021 | Approved | JEFFREY PARD |
| Wood Frame | 4/27/2021 | Corrections Issued | JEFFREY PARD |
| BUILDING-Rough-Frame | 5/10/2021 | Partial Approval | JEFFREY PARD |
| Green Building Rough | 5/10/2021 | Not Ready for Inspection | JEFFREY PARD |
| Interior/Exterior Lathing | 5/10/2021 | Approved | JEFFREY PARD |
| Verify Sprinkler Sign Off | 5/10/2021 | Not Ready for Inspection | JEFFREY PARD |
| Insulation | 5/21/2021 | Approved | JEFFREY PARD |
| Shower Pan | 5/21/2021 | Approved | JEFFREY PARD |
| Underground Mechanical | 5/21/2021 | Approved | JEFFREY PARD |
| Drywall Nailing | 6/2/2021 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 9/21/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 9/21/2021 | Corrections Issued | DAVID SCANTLIN |
| Footing/Foundation/Slab | 9/21/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 9/21/2021 | Approved | DAVID SCANTLIN |
| Green Building Rough | 9/21/2021 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 9/21/2021 | SGSOV Not Ready | DAVID SCANTLIN |
| Service/Power Release | 9/21/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 9/21/2021 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 9/21/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 2/15/2022 | Approved | JEFFREY PARD |
| Final | 2/15/2022 | OK to Issue CofO | JEFFREY PARD |
| Footing/Foundation/Slab | 2/15/2022 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 2/15/2022 | SGSOV Approved | JEFFREY PARD |
| Service/Power Release | 2/15/2022 | Approved | JEFFREY PARD |
| Verify Sprinkler Sign Off | 2/15/2022 | Approved | JEFFREY PARD |