5107 N HIGHLAND VIEW AVE 90041
Certificate Information: 5107 N HIGHLAND VIEW AVE 90041
- Application / Permit
- 20010-20000-01161
- Plan Check / Job No.
- B20VN05314
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSE IRREG. 31'-3"X38' ONE STORY ACCESSORY DWELLING UNIT _ PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 12/10/2020
- Issuing Office
- Current Status
- CofO Issued on 12/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2020 | DAWN MC NULTY |
| Corrections Issued | 4/28/2020 | DAWN MC NULTY |
| Quality Review Completed | 4/29/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 5/4/2020 | APPLICANT |
| Green Plans Picked Up | 7/23/2020 | APPLICANT |
| Applicant returned to address corrections | 8/18/2020 | DAWN MC NULTY |
| Applicant returned to address corrections | 10/6/2020 | DAWN MC NULTY |
| Plan Check Approved | 12/10/2020 | DAWN MC NULTY |
| Issued | 12/10/2020 | APPLICANT |
| CofO in Progress | 11/19/2021 | CRAIG VAUGHAN |
| Permit Finaled | 12/15/2021 | DEROLD HAUFF |
| CofO Issued | 12/15/2021 | DEROLD HAUFF |
| Permit Finaled | 12/15/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 7/6/2020 | MIGUEL GAMBOA |
| CPC | Cleared | 7/6/2020 | MIGUEL GAMBOA |
| Address approval | Cleared | 7/14/2020 | CELINA MORENO |
| Highway dedication | Cleared | 7/14/2020 | CELINA MORENO |
| Permit | Cleared | 7/14/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 7/16/2020 | CELINA MORENO |
| Sewer availability | Cleared | 7/16/2020 | CELINA MORENO |
| Specific Plan | Cleared | 7/22/2020 | KEVIN ARUCAN |
| GPI Written Notices | Cleared | 8/18/2020 | DAWN MC NULTY |
| Grading Pre-Inspection | Cleared | 8/18/2020 | DAWN MC NULTY |
| Green Code | Cleared | 8/31/2020 | DAVID MATSON |
| Hydrant and Access approval | Cleared | 9/14/2020 | MATTHEW CRAIG |
| Specific Plan | Cleared | 10/14/2020 | ADRINEH MELKONIAN |
| Low Impact Development | Cleared | 11/17/2020 | ROBIN YAMADA |
| Roof/Waste drainage to street | Cleared | 11/18/2020 | CELINA MORENO |
| "Q" conditions | Cleared | 11/24/2020 | MIGUEL GAMBOA |
Contact Information
| Contractor | E M M C Design & Construction; Lic. No.: 1016221-B | 427 N KINGSLEY DR #5 LOS ANGELES, CA 90004 |
| Engineer | Mah,, Edwin Poy-Dor; Lic. No.: C27141 | 1740 APPIAN WAY MONTEBELLO, CA 90640 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/22/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/22/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 1/11/2021 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 1/11/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 1/14/2021 | Partial Approval | CRAIG VAUGHAN |
| Gas Test | 2/1/2021 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 2/1/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Sewer | 2/1/2021 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 2/3/2021 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2021 | Partial Approval | SCOTT FINNILA |
| Insulation | 2/4/2021 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2021 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 4/5/2021 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 4/5/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 4/5/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 4/7/2021 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 4/7/2021 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 4/7/2021 | Corrections Issued | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 4/16/2021 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 4/16/2021 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 4/16/2021 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/16/2021 | Approved | CRAIG VAUGHAN |
| Insulation | 4/28/2021 | Corrections Issued | THOMAS LOGRASSO |
| Drywall Nailing | 5/10/2021 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 5/10/2021 | Approved | CRAIG VAUGHAN |
| Gas Test | 7/7/2021 | Approved | HAMIK HARTOUNIAN |
| Final | 8/9/2021 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 8/9/2021 | Approved | BRIAN SULLIVAN |
| Green Building Final | 8/9/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 8/9/2021 | SGSOV Not Ready | BRIAN SULLIVAN |
| Service/Power Release | 8/9/2021 | Approved | BRIAN SULLIVAN |
| Smoke Detectors | 8/9/2021 | Approved | BRIAN SULLIVAN |
| Final | 8/19/2021 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 8/19/2021 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 8/19/2021 | SGSOV Not Ready | CRAIG VAUGHAN |
| Final | 10/25/2021 | No Access for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 10/25/2021 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Final | 10/29/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 10/29/2021 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Final | 11/3/2021 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 11/3/2021 | SGSOV Not Ready | CRAIG VAUGHAN |
| Final | 11/8/2021 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 11/8/2021 | SGSOV Approved | CRAIG VAUGHAN |
| Pre-Inspection | 11/12/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 11/18/2021 | OK to Issue CofO | CRAIG VAUGHAN |