8312 N OSO AVE 91306

Certificate Information: 8312 N OSO AVE 91306

Application / Permit
20010-20000-01121
Plan Check / Job No.
B20VN05226
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 46'-6" X 43'-1" 1-STORY IRREGULAR SHAPE ACCESSORY DWELLING UNIT WITH ATTACHED GARAGE.
Permit Issued
Issued on 3/16/2021
Issuing Office
Current Status
CofO Issued on 3/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2020 APPLICANT
Assigned to Plan Check Engineer 4/16/2020 SERGIO MUNIZ
Corrections Issued 4/17/2020 SERGIO MUNIZ
Green Plans Picked Up 5/1/2020 APPLICANT
Quality Review Completed 5/11/2020 OMID HEDAYAT
Plan Check Approved 2/25/2021 SERGIO MUNIZ
Issued 3/16/2021 APPLICANT
Building Plans Picked Up 3/19/2021 APPLICANT
CofO in Progress 3/11/2022 HENRY KIM
CofO Issued 3/16/2022 JOHN JANSON
Permit Finaled 3/16/2022 JOHN JANSON

Permit Application Clearance Information

Green Code Cleared 6/10/2020 MICHAEL AYERS
Low Impact Development Cleared 8/19/2020 ORVAL HERNANDEZ-MARCI
Tract Map conditions Cleared 9/17/2020 MIGUEL GAMBOA
Address approval Cleared 9/22/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 9/22/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 9/22/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 9/22/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 10/19/2020 KURT CORRAL
Construction near power lines Cleared 1/7/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/19/2021 Partial Approval DAVID STEPANYAN
Underground Mechanical 3/30/2021 Partial Approval DAVID STEPANYAN
Footing/Foundation/Slab 4/7/2021 Approved DAVID STEPANYAN
Deputy Wood Construction 4/27/2021 Conditional Approval DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 5/3/2021 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 5/3/2021 Not Ready for Inspection DAVID STEPANYAN
ELECTRICAL-Rough 5/17/2021 Approved DAVID STEPANYAN
HVAC-Rough 5/17/2021 Approved DAVID STEPANYAN
PLUMBING-Rough 5/17/2021 Approved DAVID STEPANYAN
Interior/Exterior Lathing 5/24/2021 Partial Approval DAVID STEPANYAN
BUILDING-Rough-Frame 6/4/2021 Approved DAVID STEPANYAN
Green Building Rough 6/4/2021 Approved DAVID STEPANYAN
Underground Mechanical 6/4/2021 Partial Approval DAVID STEPANYAN
Verify Sprinkler Sign Off 6/4/2021 Approved DAVID STEPANYAN
Insulation 6/10/2021 Approved HENRY KIM
Drywall Nailing 6/16/2021 Approved RYAN SALAZAR
Shower Pan 6/22/2021 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 6/25/2021 Approved SHAVONNE ESPINOZA
ELECTRICAL-Final 7/21/2021 Corrections Issued DAVID STEPANYAN
Final 7/21/2021 Corrections Issued DAVID STEPANYAN
Gas Test 7/21/2021 Approved DAVID STEPANYAN
Green Building Final 7/21/2021 Corrections Issued DAVID STEPANYAN
HVAC-Final 7/21/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Final 7/21/2021 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 7/21/2021 SGSOV Approved DAVID STEPANYAN
Smoke Detectors 7/21/2021 Approved DAVID STEPANYAN
ELECTRICAL-Final 8/18/2021 Not Ready for Inspection DAVID STEPANYAN
HVAC-Final 8/18/2021 Approved DAVID STEPANYAN
PLUMBING-Final 8/18/2021 Not Ready for Inspection DAVID STEPANYAN
Pre-Inspection 8/18/2021 Partial Inspection STEPHANIE SWANSON
Final 9/30/2021 Not Ready for Inspection DAVID STEPANYAN
Green Building Final 9/30/2021 Approved DAVID STEPANYAN
Service/Power Release 9/30/2021 Not Ready for Inspection DAVID STEPANYAN
Underground Mechanical 9/30/2021 Partial Approval DAVID STEPANYAN
Final 10/13/2021 Not Ready for Inspection HENRY KIM
Sewer 10/13/2021 Partial Inspection HENRY KIM
ELECTRICAL-Final 11/5/2021 Approved DAVID STEPANYAN
PLUMBING-Final 11/5/2021 Approved DAVID STEPANYAN
Final 3/10/2022 OK to Issue CofO HENRY KIM
Service/Power Release 3/10/2022 Approved HENRY KIM