3861 N REKLAW DR 91604

Certificate Information: 3861 N REKLAW DR 91604

Application / Permit
20010-20000-01115
Plan Check / Job No.
B20VN05215
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 49' X 36' IRR.-SHAPE 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED 16' 9" X 25' 11" IRR.-SHAPED PATIO COVER. ALL WORK DONE PER ENGINEERING. NFPA 13D FIRE SPRINKLERS TO BE PROVIDED.
Permit Issued
Issued on 3/24/2025
Issuing Office
Valley
Current Status
Issued on 3/24/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/5/2020 APPLICANT
Assigned to Plan Check Engineer 5/22/2020 GURUNATH NESARAJAH
Corrections Issued 5/24/2020 GURUNATH NESARAJAH
Quality Review Completed 5/27/2020 STEVEN KIM
Green Plans Picked Up 5/28/2020 APPLICANT
Applicant returned to address corrections 4/20/2022 GURUNATH NESARAJAH
Plan Check Approved 11/30/2022 GURUNATH NESARAJAH
Building Plans Picked Up 12/7/2022 APPLICANT
Issued 3/24/2025 APPLICANT

Permit Application Clearance Information

Low Impact Development Cleared 11/12/2021 MARTIN FRAGOSO
BHO/Hillside ordinance Cleared 2/1/2022 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 2/1/2022 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 2/1/2022 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 2/1/2022 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 2/17/2022 DAGOVERTO GUERRERO
Permit Cleared 2/18/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 2/18/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 3/1/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 3/1/2022 DAGOVERTO GUERRERO
Distance to fire station Cleared 3/16/2022 CINDY JOSSELYN
Hydrant and Access approval Cleared 3/16/2022 CINDY JOSSELYN
Trees in Parkway Cleared 3/23/2022 GURUNATH NESARAJAH
GPI Written Notices Cleared 8/29/2022 GURUNATH NESARAJAH
Grading Pre-Inspection Cleared 8/29/2022 GURUNATH NESARAJAH
Green Code Cleared 8/29/2022 MICHAEL AYERS

Contact Information

Contractor John Wendell L; Lic. No.: 1034536-B 15330 ARCHWOOD ST      VAN NUYS, CA 91406
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039
Engineer Su,, Yu-Ting; Lic. No.: C76714 28 SAGE      LAKE FOREST, CA 92630
Geologist Carrle,, Conrad Henry; Lic. No.: EG2359 23128 WILDWOOD ROAD      NEWHALL, CA 91321

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/23/2025 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 5/23/2025 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 5/23/2025 Partial Approval CHRISTOPHE COCHRAN
Underground Mechanical 5/23/2025 Approved CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 5/28/2025 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 6/11/2025 Partial Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 6/11/2025 Partial Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 6/16/2025 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 6/17/2025 Partial Approval CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 6/23/2025 Partial Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 6/23/2025 Partial Approval CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 6/26/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Footing/Foundation/Slab 6/26/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Excavation/Setback/Form/Re-Bar 6/30/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 7/2/2025 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 7/2/2025 Partial Approval CHRISTOPHE COCHRAN
Deputy Steel/Welding 7/10/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/11/2025 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 8/1/2025 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 10/10/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 10/14/2025 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 11/4/2025 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 11/4/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 11/4/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 11/4/2025 Corrections Issued CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 11/4/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Wood Frame 11/4/2025 Partial Approval CHRISTOPHE COCHRAN
HVAC-Rough 11/7/2025 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Rough 11/7/2025 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 11/14/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 11/14/2025 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 11/19/2025 Corrections Issued JACK KARGODORIAN
Shower Pan 11/19/2025 Partial Approval JACK KARGODORIAN
ELECTRICAL-Rough 11/21/2025 Corrections Issued CHRISTOPHE COCHRAN
Shower Pan 11/21/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 11/24/2025 Approved CHRISTOPHE COCHRAN
Shower Pan 11/24/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Insulation 12/11/2025 Corrections Issued CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/11/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 12/15/2025 Corrections Issued CHRISTOPHE COCHRAN
Green Building Rough 12/15/2025 Approved CHRISTOPHE COCHRAN
Insulation 12/15/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/15/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 12/15/2025 Approved CHRISTOPHE COCHRAN
Wood Frame 12/15/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Insulation 12/17/2025 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/17/2025 Partial Approval CHRISTOPHE COCHRAN
Wood Frame 12/17/2025 Approved CHRISTOPHE COCHRAN
Drywall Nailing 1/5/2026 Partial Approval JOSE AVILA
ELECTRICAL-Final 6/25/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Final 6/25/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Final 6/25/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
Service/Power Release 6/25/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Final 7/1/2026 Approved CHRISTOPHE COCHRAN
HVAC-Final 7/1/2026 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 7/1/2026 Approved CHRISTOPHE COCHRAN
Service/Power Release 7/1/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Final 7/7/2026 Corrections Issued CHRISTOPHE COCHRAN
Service/Power Release 7/7/2026 Not Ready for Inspection CHRISTOPHE COCHRAN