5634 N STANSBURY AVE 91401
Certificate Information: 5634 N STANSBURY AVE 91401
- Application / Permit
- 20010-20000-01096
- Plan Check / Job No.
- B20VN05187
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 43'8"X50'2" 2-STORY SFD W/ ATTACHED 2-CAR GARAGE. NFPA 13D FIRE SPRINKLERS REQ'D THROUGHOUT
- Permit Issued
- Issued on 9/10/2020
- Issuing Office
- Current Status
- CofO Issued on 12/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2020 | MARVEL DELACRUZ |
| Corrections Issued | 4/28/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 5/1/2020 | STEVEN KIM |
| Building Plans Picked Up | 5/8/2020 | APPLICANT |
| Green Plans Picked Up | 5/8/2020 | APPLICANT |
| Applicant returned to address corrections | 7/28/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 7/30/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 8/21/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 8/25/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 8/27/2020 | MARVEL DELACRUZ |
| Plan Check Approved | 9/10/2020 | MARVEL DELACRUZ |
| Issued | 9/10/2020 | APPLICANT |
| CofO in Progress | 10/28/2022 | RICHARD DOCKUS |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
| CofO Issued | 12/24/2022 | MICHAEL SMITH |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/13/2020 | JOHN TRIANTAFYLLOS |
| Permit | Cleared | 5/13/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2020 | JOHN TRIANTAFYLLOS |
| Green Code | Cleared | 5/14/2020 | MARVEL DELACRUZ |
| Sewer availability | Cleared | 5/14/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 5/22/2020 | MATTHEW CRAIG |
| Trees in Parkway | Cleared | 6/2/2020 | JOHN KIM |
| Low Impact Development | Cleared | 7/6/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/8/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Pampa Investment Inc; Lic. No.: 832632-B | 984 BROADWAY #302 CHULA VISTA, CA 91911 |
| Engineer | Moser,, Bradley Charles; Lic. No.: C68803 | 116 OAKSIDE LN BUELLTON, CA 93427 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/28/2020 | Partial Inspection | WILLIAM KUEHN |
| Sewer | 11/5/2020 | Approved | WILLIAM KUEHN |
| Underground Mechanical | 11/5/2020 | Partial Inspection | WILLIAM KUEHN |
| Footing/Foundation/Slab | 11/25/2020 | Approved | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2020 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 2/24/2021 | Not Ready for Inspection | JOHN HAYES |
| Gas Test | 2/24/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 2/24/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 2/24/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 2/24/2021 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 2/24/2021 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 3/24/2021 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 3/24/2021 | Corrections Issued | DAVID SANDOVAL |
| HVAC-Rough | 4/12/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/12/2021 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/13/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/13/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 4/13/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 4/13/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/29/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 4/29/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/29/2021 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 5/12/2021 | Approved | DANIEL ORRANTE |
| Interior/Exterior Lathing | 7/12/2021 | Approved | DEANDRE HOFFMAN |
| Shower Pan | 7/12/2021 | Approved | DEANDRE HOFFMAN |
| Gas Test | 6/14/2022 | Approved | RICHARD DOCKUS |
| HVAC-Final | 6/27/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 6/27/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 6/28/2022 | Corrections Issued | RICHARD DOCKUS |
| ELECTRICAL-Final | 7/12/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Final | 7/22/2022 | Approved | RICHARD DOCKUS |
| Final | 10/14/2022 | Partial Inspection | MISAEL ESPARZA |
| Green Building Final | 10/14/2022 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 10/14/2022 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 10/14/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 10/14/2022 | Approved | MISAEL ESPARZA |
| Final | 10/27/2022 | OK to Issue CofO | RICHARD DOCKUS |
| Service/Power Release | 10/27/2022 | Not Required | RICHARD DOCKUS |