18000 W RAYEN ST 91325

Certificate Information: 18000 W RAYEN ST 91325

Application / Permit
20010-20000-01075
Plan Check / Job No.
B20VN05162
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (36'-0"x 47'-0") IRR SHAPE 2-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d).
Permit Issued
Issued on 1/5/2021
Issuing Office
Current Status
CofO Issued on 12/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/2/2020 APPLICANT
Assigned to Plan Check Engineer 4/16/2020 TROY DEGUZMAN
Corrections Issued 4/23/2020 TROY DEGUZMAN
Green Plans Picked Up 4/24/2020 APPLICANT
Quality Review Completed 4/27/2020 CHON CHIO KUO
Building Plans Picked Up 5/15/2020 APPLICANT
Applicant returned to address corrections 12/16/2020 TROY DEGUZMAN
Plan Check Approved 1/5/2021 TROY DEGUZMAN
Issued 1/5/2021 APPLICANT
CofO in Progress 11/16/2021 MARK JOHNSON
Permit Finaled 12/23/2021 MICHAEL SMITH
CofO Issued 12/23/2021 MICHAEL SMITH
Permit Finaled 12/23/2021 MICHAEL SMITH

Permit Application Clearance Information

Green Code Cleared 6/9/2020 TROY DEGUZMAN
Address approval Cleared 6/12/2020 ADRIAN CASTRO
Sewer availability Cleared 6/15/2020 ADRIAN CASTRO
Permit Cleared 6/18/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/19/2020 ADRIAN CASTRO
Low Impact Development Cleared 7/31/2020 JORGE MEJIA LEMUS
Trees in Parkway Cleared 8/20/2020 JOHN KIM
Hydrant and Access approval Cleared 9/24/2020 KURT CORRAL
Construction near power lines Cleared 9/28/2020 RIDWAN HARDY
Roof/Waste drainage to street Cleared 11/17/2020 GUILLERMO PETRA

Contact Information

Architect Johnson,, David Michael; Lic. No.: C18045 3638 AUREOLA BLVD      LOS ANGELES, CA 90008
Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/10/2021 Partial Approval MARK JOHNSON
Footing/Foundation/Slab 2/23/2021 Corrections Issued MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 3/17/2021 Approved MARK JOHNSON
Footing/Foundation/Slab 3/17/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 5/11/2021 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Rough 5/11/2021 Approved MARK JOHNSON
HVAC-Rough 5/11/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 5/11/2021 Approved MARK JOHNSON
PLUMBING-Rough 5/11/2021 Approved MARK JOHNSON
Verify Sprinkler Sign Off 5/11/2021 Not Ready for Inspection MARK JOHNSON
BUILDING-Rough-Frame 5/21/2021 Approved MARK JOHNSON
Green Building Rough 5/21/2021 Approved MARK JOHNSON
Insulation 5/21/2021 Approved MARK JOHNSON
Verify Sprinkler Sign Off 5/21/2021 Approved MARK JOHNSON
Drywall Nailing 6/4/2021 Corrections Issued MARK JOHNSON
Sewer 10/6/2021 Approved MARK JOHNSON
Drywall Nailing 11/5/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 11/5/2021 Corrections Issued JENNIFER RABUCHIN
Final 11/5/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Final 11/5/2021 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/5/2021 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 11/5/2021 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 11/5/2021 Approved JENNIFER RABUCHIN
Final 11/15/2021 Conditional Approval MARK JOHNSON
Green Building Final 11/15/2021 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 11/15/2021 SGSOV Approved MARK JOHNSON
Service/Power Release 11/15/2021 Approved MARK JOHNSON
Final 11/17/2021 OK to Issue CofO MARK JOHNSON