8607 N AQUEDUCT AVE 91343

Certificate Information: 8607 N AQUEDUCT AVE 91343

Application / Permit
20010-20000-01064
Plan Check / Job No.
B20VN05152
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 31'6"X40'4" DETACHED 1-STORY ACCESSORY DWELLING UNIT. ALL WORK PER WFPP. NFPA 13 D FIRE SPRINKLERS REQ'D THROUGHOUT
Permit Issued
Issued on 11/25/2020
Issuing Office
Current Status
CofO Issued on 5/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2020 APPLICANT
Assigned to Plan Check Engineer 5/21/2020 MARVEL DELACRUZ
Corrections Issued 5/22/2020 MARVEL DELACRUZ
Quality Review Completed 5/27/2020 STEVEN KIM
Building Plans Picked Up 5/29/2020 APPLICANT
Green Plans Picked Up 6/1/2020 APPLICANT
Plan Check Approved 11/5/2020 MARVEL DELACRUZ
Issued 11/25/2020 APPLICANT
CofO in Progress 5/5/2022 RAUL OLAGI
Permit Finaled 5/27/2022 MICHAEL SMITH
CofO Issued 5/27/2022 MICHAEL SMITH
Permit Finaled 5/27/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/5/2020 LEE GUILBEAUX
Permit Cleared 6/5/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/15/2020 LEE GUILBEAUX
Sewer availability Cleared 6/15/2020 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 6/15/2020 LEE GUILBEAUX
Hydrant and Access approval Cleared 9/9/2020 MATTHEW CRAIG
Low Impact Development Cleared 10/6/2020 MARTIN FRAGOSO
Green Code Cleared 10/14/2020 MICHAEL AYERS
Roof/Waste drainage to street Cleared 10/20/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Pampa Investment Inc; Lic. No.: 832632-B 984 BROADWAY #302      CHULA VISTA, CA 91911

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/1/2020 Partial Approval ARTHUR SARGSYAN
Sewer 12/1/2020 Partial Approval ARTHUR SARGSYAN
Footing/Foundation/Slab 12/4/2020 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 12/18/2020 Partial Approval ARTHUR SARGSYAN
ELECTRICAL-Rough 12/23/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 12/23/2020 Not Ready for Inspection ARTHUR SARGSYAN
PLUMBING-Rough 12/23/2020 Approved ARTHUR SARGSYAN
Wood Frame 12/23/2020 Not Ready for Inspection ARTHUR SARGSYAN
BUILDING-Rough-Frame 12/29/2020 Approved ARTHUR SARGSYAN
Green Building Rough 12/29/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 12/29/2020 Approved ARTHUR SARGSYAN
MERV13>=Rough 12/29/2020 Approved ARTHUR SARGSYAN
Verify Sprinkler Sign Off 12/29/2020 Approved ARTHUR SARGSYAN
Insulation 1/7/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 1/7/2021 Approved ARTHUR SARGSYAN
Shower Pan 1/7/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 1/12/2021 Approved DANIEL ORRANTE
Final 3/15/2021 No Access for Inspection ARTHUR SARGSYAN
Green Building Final 3/15/2021 Not Ready for Inspection ARTHUR SARGSYAN
MERV13>=Final 3/15/2021 No Access for Inspection ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/15/2021 SGSOV Approved ARTHUR SARGSYAN
Service/Power Release 3/15/2021 No Access for Inspection ARTHUR SARGSYAN
Smoke Detectors 3/15/2021 Not Ready for Inspection ARTHUR SARGSYAN
ELECTRICAL-Final 2/7/2022 Corrections Issued RAUL OLAGI
Final 2/7/2022 Corrections Issued RAUL OLAGI
Green Building Final 2/7/2022 Approved RAUL OLAGI
HVAC-Final 2/7/2022 Corrections Issued RAUL OLAGI
MERV13>=Final 2/7/2022 Corrections Issued RAUL OLAGI
PLUMBING-Final 2/7/2022 Corrections Issued RAUL OLAGI
Smoke Detectors 2/7/2022 Approved RAUL OLAGI
ELECTRICAL-Final 4/4/2022 Approved RAUL OLAGI
Final 4/4/2022 Corrections Issued RAUL OLAGI
Gas Test 4/4/2022 Approved RAUL OLAGI
HVAC-Final 4/4/2022 Approved RAUL OLAGI
MERV13>=Final 4/4/2022 Approved RAUL OLAGI
PLUMBING-Final 4/4/2022 Approved RAUL OLAGI
Service/Power Release 4/4/2022 Not Ready for Inspection RAUL OLAGI
Final 5/4/2022 OK to Issue CofO RAUL OLAGI
Service/Power Release 5/4/2022 Approved RAUL OLAGI