7218 1/2 N BALCOM AVE 91335

Certificate Information: 7218 1/2 N BALCOM AVE 91335

Application / Permit
20010-20000-01057
Plan Check / Job No.
B20VN05130
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING ONE CAR GARAGE INTO RECREATION ROOM (221sf) AND ADD 2 STORY ADU (1199sf) (1200SF MAX PER ORDINANCE, LAMC 12.22 A.33 (c)-(d)) NFPA 13D THRU OUT
Permit Issued
Issued on 6/21/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2020 APPLICANT
Assigned to Plan Check Engineer 4/16/2020 AUNG SOE
Corrections Issued 4/23/2020 AUNG SOE
Green Plans Picked Up 4/27/2020 APPLICANT
Quality Review Completed 5/7/2020 QUAN NGHIEM
Building Plans Picked Up 5/19/2020 APPLICANT
Plan Check Approved 6/21/2023 AUNG SOE
Issued 6/21/2023 APPLICANT
CofO in Progress 2/15/2024 JEFFREY BULL
Permit Finaled 3/14/2024 JOHN JANSON
CofO Issued 3/14/2024 JOHN JANSON
Permit Finaled 3/14/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/25/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/25/2020 ADRIAN CASTRO
Sewer availability Cleared 9/25/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 4/1/2023 RUEL COLE
Low Impact Development Cleared 4/12/2023 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 6/6/2023 DAGOVERTO GUERRERO
Green Code Cleared 6/21/2023 AUNG SOE

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/1/2023 Approved JEFFREY BULL
Sewer 8/1/2023 Approved JEFFREY BULL
Underground Mechanical 8/1/2023 Not Ready for Inspection JEFFREY BULL
Underground Mechanical 8/25/2023 Approved JEFFREY BULL
Footing/Foundation/Slab 8/29/2023 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 9/21/2023 Partial Approval JEFFREY BULL
BUILDING-Rough-Frame 10/18/2023 Corrections Issued JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 10/18/2023 Approved JEFFREY BULL
Green Building Rough 10/18/2023 Not Ready for Inspection JEFFREY BULL
Rough-Elec/Plmb/HVAC 10/18/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 10/24/2023 Partial Approval JEFFREY BULL
Shower Pan 10/24/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 11/8/2023 Corrections Issued MORRIS JACKSON
Green Building Rough 11/8/2023 Approved MORRIS JACKSON
Insulation 11/8/2023 Not Ready for Inspection MORRIS JACKSON
Drywall Nailing 11/14/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 2/15/2024 Approved JEFFREY BULL
ELECTRICAL-Final 2/15/2024 Approved JEFFREY BULL
Final 2/15/2024 OK to Issue CofO JEFFREY BULL
Green Building Final 2/15/2024 Approved JEFFREY BULL
HVAC-Final 2/15/2024 Approved JEFFREY BULL
PLUMBING-Final 2/15/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 2/15/2024 SGSOV Approved JEFFREY BULL
Service/Power Release 2/15/2024 Approved JEFFREY BULL
Smoke Detectors 2/15/2024 Approved JEFFREY BULL