16822 W ADLON ROAD 91436
Certificate Information: 16822 W ADLON ROAD 91436
- Application / Permit
- 20010-20000-01034
- Plan Check / Job No.
- B20VN05065
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 21'7" x 18'6" TWO STORY ACCESSORY DWELLING UNIT. SHALL BE FULLY SPRINKLERED. ALL WORK GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)1, (d)1, and (g)
- Permit Issued
- Issued on 4/8/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2020 | JEFFREY TANGONAN |
| Corrections Issued | 5/5/2020 | JEFFREY TANGONAN |
| Quality Review Completed | 5/7/2020 | STEVEN KIM |
| Green Plans Picked Up | 5/7/2020 | APPLICANT |
| Applicant returned to address corrections | 2/4/2021 | JEFFREY TANGONAN |
| Plan Check Approved | 3/8/2021 | JEFFREY TANGONAN |
| Issued | 4/8/2021 | APPLICANT |
| Building Plans Picked Up | 4/23/2021 | APPLICANT |
| CofO in Progress | 1/4/2024 | VINCENT HANLEY |
| Permit Finaled | 2/15/2024 | JOHN JANSON |
| CofO Issued | 2/15/2024 | JOHN JANSON |
| Permit Finaled | 2/15/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/17/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 7/17/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 7/17/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 7/17/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/17/2020 | LEE GUILBEAUX |
| Street Frontage | Cleared | 7/17/2020 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 8/4/2020 | KURT CORRAL |
| Green Code | Cleared | 9/3/2020 | DAVID MATSON |
| Low Impact Development | Cleared | 9/30/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 1/14/2021 | ADRIAN CASTRO |
| GPI Written Notices | Cleared | 3/8/2021 | JEFFREY TANGONAN |
| Grading Pre-Inspection | Cleared | 3/8/2021 | JEFFREY TANGONAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/23/2021 | Partial Approval | RONALD COWAN |
| Sewer | 4/23/2021 | Partial Approval | RONALD COWAN |
| Footing/Foundation/Slab | 4/28/2021 | Partial Approval | RONALD COWAN |
| Sewer | 4/28/2021 | Approved | RONALD COWAN |
| Underground Mechanical | 4/28/2021 | Approved | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2022 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2022 | Approved | PETER FOLLING |
| ELECTRICAL-Rough | 8/23/2022 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 8/23/2022 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 12/2/2022 | Corrections Issued | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2022 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 12/5/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 12/9/2022 | Partial Approval | VINCENT HANLEY |
| HVAC-Rough | 12/9/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 12/9/2022 | Approved | VINCENT HANLEY |
| Gas Test | 12/20/2022 | Partial Approval | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 12/20/2022 | Approved | VINCENT HANLEY |
| Shower Pan | 12/20/2022 | Approved | VINCENT HANLEY |
| Smoke Detectors | 12/20/2022 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/22/2023 | Approved | VINCENT HANLEY |
| Drywall Nailing | 2/22/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2023 | Approved | VINCENT HANLEY |
| Gas Test | 2/22/2023 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 2/22/2023 | Approved | VINCENT HANLEY |
| Insulation | 2/22/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 2/22/2023 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 2/22/2023 | Approved | VINCENT HANLEY |
| Wood Frame | 2/22/2023 | Approved | VINCENT HANLEY |
| Service/Power Release | 7/11/2023 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Final | 9/20/2023 | Approved | VINCENT HANLEY |
| HVAC-Final | 9/20/2023 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 9/20/2023 | Approved | VINCENT HANLEY |
| Service/Power Release | 9/26/2023 | Approved | VINCENT HANLEY |
| Final | 10/4/2023 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 10/4/2023 | Approved | VINCENT HANLEY |
| Green Building Final | 10/4/2023 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 10/4/2023 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 10/4/2023 | Approved | VINCENT HANLEY |
| Smoke Detectors | 10/4/2023 | Approved | VINCENT HANLEY |
| Final | 1/3/2024 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 1/3/2024 | Approved | VINCENT HANLEY |