13040 W JOUETT ST 91331

Certificate Information: 13040 W JOUETT ST 91331

Application / Permit
20010-20000-01011
Plan Check / Job No.
B20VN04977
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (73'-6"x 19'-0") ONE STORY SINGLE FAMILY DWELLING WITH NFPA-13D FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
Permit Issued
Issued on 9/9/2020
Issuing Office
Current Status
CofO Issued on 7/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2020 APPLICANT
Assigned to Plan Check Engineer 4/16/2020 TROY DEGUZMAN
Corrections Issued 4/21/2020 TROY DEGUZMAN
Quality Review Completed 4/21/2020 CHON CHIO KUO
Building Plans Picked Up 4/23/2020 APPLICANT
Green Plans Picked Up 4/23/2020 APPLICANT
Applicant returned to address corrections 6/12/2020 TROY DEGUZMAN
Plan Check Approved 9/9/2020 TROY DEGUZMAN
Issued 9/9/2020 APPLICANT
CofO in Progress 6/25/2021 MICHEL ABAJAN
CofO Issued 7/10/2021 MICHAEL SMITH
Permit Finaled 7/10/2021 MICHAEL SMITH

Permit Application Clearance Information

Hydrant and Access approval Cleared 6/5/2020 MATTHEW CRAIG
Address approval Cleared 6/19/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 6/22/2020 GUILLERMO PETRA
Sewer availability Cleared 6/22/2020 GUILLERMO PETRA
Green Code Cleared 6/25/2020 TROY DEGUZMAN
Low Impact Development Cleared 7/27/2020 ROBIN YAMADA
Roof/Waste drainage to street Cleared 7/29/2020 GUILLERMO PETRA
ZI Cleared 9/9/2020 HERMINIGILDO AGUSTIN

Contact Information

Architect Kivotos,, Juan M; Lic. No.: C26491 1323 N NIAGARA STREET      BURBANK, CA 91505
Contractor Owner-Builder       ,
Engineer Yogurtian,, Arpinee; Lic. No.: C49916 2529 FOOTHILL BLVD, STE 208      LA CRESCENTA, CA 91214

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/15/2020 Approved MICHEL ABAJAN
METHANE-Barrier 10/15/2020 Approved MICHEL ABAJAN
METHANE-Subgrade 10/15/2020 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 10/27/2020 Partial Approval MICHEL ABAJAN
Green Building Rough 10/27/2020 Not Ready for Inspection MICHEL ABAJAN
METHANE-Rough 10/27/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 10/27/2020 Partial Approval MICHEL ABAJAN
Verify Sprinkler Sign Off 10/27/2020 Not Ready for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 11/24/2020 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 12/4/2020 Approved MICHEL ABAJAN
ELECTRICAL-Rough 12/4/2020 Approved MICHEL ABAJAN
Green Building Rough 12/4/2020 Approved MICHEL ABAJAN
HVAC-Rough 12/4/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 12/4/2020 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 12/4/2020 Approved MICHEL ABAJAN
Insulation 12/15/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 12/15/2020 Approved MICHEL ABAJAN
Drywall Nailing 12/21/2020 Approved MICHAEL TEMPLE
Underground Mechanical 3/24/2021 Partial Approval MICHEL ABAJAN
Pre-Inspection 4/13/2021 Approved MICHEL ABAJAN
Final 4/28/2021 Corrections Issued MICHEL ABAJAN
Green Building Final 4/28/2021 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 4/28/2021 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 4/28/2021 Corrections Issued MICHEL ABAJAN
Smoke Detectors 4/28/2021 Approved MICHEL ABAJAN
Final 5/6/2021 Corrections Issued MICHEL ABAJAN
Green Building Final 5/6/2021 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 5/6/2021 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 5/6/2021 Not Ready for Inspection MICHEL ABAJAN
Final 6/15/2021 Corrections Issued MICHEL ABAJAN
Green Building Final 6/15/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/15/2021 SGSOV Approved MICHEL ABAJAN
Service/Power Release 6/15/2021 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 6/18/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 6/25/2021 Approved MICHEL ABAJAN
Final 6/25/2021 OK to Issue CofO MICHEL ABAJAN
HVAC-Final 6/25/2021 Approved MICHEL ABAJAN
PLUMBING-Final 6/25/2021 Approved MICHEL ABAJAN
Service/Power Release 6/25/2021 Approved MICHEL ABAJAN