13042 W JOUETT ST 91331

Certificate Information: 13042 W JOUETT ST 91331

Application / Permit
20010-20000-01009
Plan Check / Job No.
B20VN04974
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 73'-6" X 19' (1) STORY SINGLE FAMILY DWELLING; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 9/16/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2020 APPLICANT
Assigned to Plan Check Engineer 4/16/2020 SELLA BENYAMIN
Corrections Issued 4/17/2020 SELLA BENYAMIN
Quality Review Completed 4/21/2020 STEVEN KIM
Building Plans Picked Up 4/23/2020 APPLICANT
Green Plans Picked Up 4/23/2020 APPLICANT
Applicant returned to address corrections 6/17/2020 SELLA BENYAMIN
Applicant returned to address corrections 7/21/2020 OMID HEDAYAT
Plan Check Approved 9/9/2020 SELLA BENYAMIN
Issued 9/16/2020 APPLICANT
CofO in Progress 9/17/2021 MICHEL ABAJAN
CofO Issued 11/15/2021 MICHAEL SMITH
Permit Finaled 11/15/2021 MICHAEL SMITH

Permit Application Clearance Information

Hydrant and Access approval Cleared 6/9/2020 MATTHEW CRAIG
Permit Cleared 6/19/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/23/2020 ADRIAN CASTRO
Sewer availability Cleared 6/23/2020 ADRIAN CASTRO
Green Code Cleared 6/25/2020 SELLA BENYAMIN
Low Impact Development Cleared 7/28/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 7/28/2020 ADRIAN CASTRO

Contact Information

Architect Kivotos,, Juan M; Lic. No.: C26491 1323 N NIAGARA STREET      BURBANK, CA 91505
Contractor Owner-Builder       ,
Engineer Yogurtian,, Arpinee; Lic. No.: C49916 2529 FOOTHILL BLVD, STE 208      LA CRESCENTA, CA 91214

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/5/2020 Partial Inspection MICHEL ABAJAN
Footing/Foundation/Slab 10/15/2020 Approved MICHEL ABAJAN
METHANE-Barrier 10/15/2020 Approved MICHEL ABAJAN
METHANE-Subgrade 10/15/2020 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 10/27/2020 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 10/27/2020 Partial Approval MICHEL ABAJAN
Wood Frame 10/27/2020 Partial Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 12/15/2020 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 1/19/2021 Approved MICHEL ABAJAN
Green Building Rough 1/19/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/19/2021 Approved MICHEL ABAJAN
METHANE-Rough 1/19/2021 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 1/19/2021 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 1/19/2021 Approved MICHEL ABAJAN
Insulation 1/25/2021 Approved MICHEL ABAJAN
Drywall Nailing 1/28/2021 Approved MICHEL ABAJAN
ELECTRICAL-Final 4/14/2021 Partial Inspection MICHEL ABAJAN
Final 4/28/2021 Corrections Issued MICHEL ABAJAN
Green Building Final 4/28/2021 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 4/28/2021 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 4/28/2021 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 4/28/2021 Approved MICHEL ABAJAN
Sewer 7/21/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 9/9/2021 SGSOV Not Ready JENNIFER RABUCHIN
ELECTRICAL-Final 9/10/2021 Corrections Issued JENNIFER RABUCHIN
Final 9/10/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Final 9/10/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 9/10/2021 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 9/10/2021 SGSOV Approved JENNIFER RABUCHIN
ELECTRICAL-Final 9/14/2021 Approved MICHEL ABAJAN
Final 9/14/2021 Corrections Issued MICHEL ABAJAN
HVAC-Final 9/14/2021 Approved MICHEL ABAJAN
Service/Power Release 9/14/2021 Not Ready for Inspection MICHEL ABAJAN
Final 9/17/2021 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 9/17/2021 Approved MICHEL ABAJAN