10653 W STALLION RANCH ROAD 91040
Certificate Information: 10653 W STALLION RANCH ROAD 91040
- Application / Permit
- 20010-20000-00992
- Plan Check / Job No.
- B20VN04905
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW 34'0" x 20'6" DETACHED GARAGE PER ENGINEERING
- Permit Issued
- Issued on 4/27/2021
- Issuing Office
- Current Status
- CofO Issued on 1/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2020 | JEFFREY TANGONAN |
| Corrections Issued | 3/26/2020 | JEFFREY TANGONAN |
| Applicant returned to address corrections | 7/23/2020 | JEFFREY TANGONAN |
| Applicant returned to address corrections | 4/15/2021 | JEFFREY TANGONAN |
| Issued | 4/27/2021 | APPLICANT |
| Building Plans Picked Up | 4/28/2021 | APPLICANT |
| CofO in Progress | 11/10/2021 | WILLIAM KUEHN |
| CofO Issued | 1/22/2022 | MICHAEL SMITH |
| Permit Finaled | 1/22/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 4/14/2020 | JOHN TRIANTAFYLLOS |
| BHO/Hillside ordinance | Cleared | 4/14/2020 | JOHN TRIANTAFYLLOS |
| BHO/Hillside ordinance | Cleared | 4/14/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 4/14/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 4/14/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 4/16/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 4/29/2020 | KURT CORRAL |
| Tract Map conditions | Cleared | 12/16/2020 | MIGUEL GAMBOA |
| Specific Plan | Cleared | 4/5/2021 | MIGUEL GAMBOA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: C56881 | 8325 FOOTHILL BLVD. STE A SUNLAND, CA 91040 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/21/2021 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 5/21/2021 | Approved | MATTHEW NELSON |
| Grading Pre-Inspection | 5/26/2021 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 6/3/2021 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 6/24/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 6/24/2021 | Approved | MATTHEW NELSON |
| Drywall Nailing | 7/21/2021 | Partial Inspection | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 7/27/2021 | No Access for Inspection | WILLIAM KUEHN |
| Drywall Nailing | 7/27/2021 | No Access for Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 8/3/2021 | Approved | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2021 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 8/16/2021 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 10/14/2021 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Final | 10/14/2021 | Approved | WILLIAM KUEHN |
| Final | 10/14/2021 | Corrections Issued | WILLIAM KUEHN |
| Green Building Final | 10/14/2021 | Approved | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 10/14/2021 | SGSOV Approved | WILLIAM KUEHN |
| Service/Power Release | 10/14/2021 | Not Required | WILLIAM KUEHN |
| Smoke Detectors | 10/14/2021 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Final | 11/9/2021 | Approved | WILLIAM KUEHN |
| Final | 11/9/2021 | OK to Issue CofO | WILLIAM KUEHN |