6432 N SATSUMA AVE 91606
Certificate Information: 6432 N SATSUMA AVE 91606
- Application / Permit
- 20010-20000-00966
- Plan Check / Job No.
- B20VN04860
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 34' X 17'7 " DETACHED TWO-STORY ACCESSORY DWELLING UNIT , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 9/1/2020
- Issuing Office
- Current Status
- CofO Issued on 7/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2020 | APPLICANT |
| Green Plans Picked Up | 4/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2020 | RARES BODEA |
| Corrections Issued | 4/17/2020 | RARES BODEA |
| Quality Review Completed | 4/17/2020 | STEVEN KIM |
| Building Plans Picked Up | 4/17/2020 | APPLICANT |
| Plan Check Approved | 8/31/2020 | RARES BODEA |
| Issued | 9/1/2020 | APPLICANT |
| CofO in Progress | 6/30/2021 | DANIEL DREW |
| Permit Finaled | 7/10/2021 | MICHAEL SMITH |
| CofO Issued | 7/10/2021 | MICHAEL SMITH |
| Permit Finaled | 7/10/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/8/2020 | HOWARD COOPER |
| Hydrant and Access approval | Cleared | 7/28/2020 | KURT CORRAL |
| Green Code | Cleared | 8/11/2020 | AARON COSTA |
| Low Impact Development | Cleared | 8/21/2020 | ORVAL HERNANDEZ-MARCI |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2020 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 8/26/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/26/2020 | RIDWAN HARDY |
| Sewer availability | Cleared | 8/26/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 8/31/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mah,, Edwin Poy-Dor; Lic. No.: C27141 | 1740 APPIAN WAY MONTEBELLO, CA 90640 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/28/2020 | Not Ready for Inspection | DANIEL DREW |
| PLUMBING-Rough | 9/28/2020 | Partial Approval | DANIEL DREW |
| Footing/Foundation/Slab | 10/5/2020 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 12/4/2020 | Not Ready for Inspection | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2020 | Approved | DANIEL DREW |
| Green Building Rough | 12/4/2020 | Approved | DANIEL DREW |
| PLUMBING-Rough | 12/4/2020 | Approved | DANIEL DREW |
| Verify Sprinkler Sign Off | 12/4/2020 | Approved | DANIEL DREW |
| Footing/Foundation/Slab | 1/5/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 1/22/2021 | Approved | DANIEL DREW |
| HVAC-Rough | 1/22/2021 | Approved | DANIEL DREW |
| PLUMBING-Rough | 1/22/2021 | Approved | DANIEL DREW |
| Insulation | 1/27/2021 | Approved | DANIEL DREW |
| Insulation | 2/4/2021 | Approved | DANIEL DREW |
| Drywall Nailing | 2/10/2021 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 2/23/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Final | 4/19/2021 | Corrections Issued | DANIEL DREW |
| Gas Test | 4/19/2021 | Not Ready for Inspection | DANIEL DREW |
| PLUMBING-Final | 4/19/2021 | Not Ready for Inspection | DANIEL DREW |
| ELECTRICAL-Final | 4/27/2021 | Approved | DANIEL DREW |
| Gas Test | 4/27/2021 | Approved | DANIEL DREW |
| HVAC-Final | 4/27/2021 | Not Ready for Inspection | DANIEL DREW |
| PLUMBING-Final | 4/27/2021 | Approved | DANIEL DREW |
| Service/Power Release | 4/27/2021 | Not Ready for Inspection | DANIEL DREW |
| BUILDING-Rough-Frame | 5/11/2021 | Partial Inspection | MICHEL ABAJAN |
| Final | 5/11/2021 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 5/11/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 5/11/2021 | SGSOV Not Ready | MICHEL ABAJAN |
| Service/Power Release | 5/11/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 5/11/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/14/2021 | Approved | CHARLES POWELL |
| Final | 6/14/2021 | Not Ready for Inspection | CHARLES POWELL |
| Green Building Final | 6/14/2021 | Approved | CHARLES POWELL |
| SGSOV-Seismic Gas S/O Valve | 6/14/2021 | SGSOV Approved | CHARLES POWELL |
| Service/Power Release | 6/14/2021 | Corrections Issued | CHARLES POWELL |
| Smoke Detectors | 6/14/2021 | Approved | CHARLES POWELL |
| Final | 6/25/2021 | Not Ready for Inspection | DANIEL DREW |
| Final | 6/30/2021 | OK to Issue CofO | DANIEL DREW |
| Service/Power Release | 6/30/2021 | Approved | DANIEL DREW |