4937 N RUBIO AVE 91436

Certificate Information: 4937 N RUBIO AVE 91436

Application / Permit
20010-20000-00961
Plan Check / Job No.
B20VN04843
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) IRREGULAR SHAPED 77' 11" X 40' 8" SINGLE FAMILY DWELLING WITH ATACHED GARAGE AND (N) 23'-1" X 10'-6" OPEN PATIO COVER ALL WORK PER ENGINEERING NFPA 13D FIRE SPRINKLER SYSTEM REQUIRED THROUGHOUT
Permit Issued
Issued on 3/22/2021
Issuing Office
Current Status
CofO Issued on 2/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2020 APPLICANT
Green Plans Picked Up 4/1/2020 APPLICANT
Assigned to Plan Check Engineer 4/9/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 4/15/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 5/1/2020 OMID HEDAYAT
Building Plans Picked Up 5/4/2020 APPLICANT
Plan Check Approved 2/18/2021 SEWADA ZADOORAN MILAGARDI
Issued 3/22/2021 APPLICANT
CofO in Progress 2/17/2022 DAVID SANDOVAL
Permit Finaled 2/28/2022 JOHN JANSON
CofO Issued 2/28/2022 JOHN JANSON
Permit Finaled 2/28/2022 JOHN JANSON

Permit Application Clearance Information

Green Code Cleared 4/21/2020 MICHAEL AYERS
Address approval Cleared 4/30/2020 LEE GUILBEAUX
Miscellaneous Cleared 4/30/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/4/2020 LEE GUILBEAUX
Permit Cleared 5/4/2020 LEE GUILBEAUX
Sewer availability Cleared 5/4/2020 LEE GUILBEAUX
Trees in Parkway Cleared 5/12/2020 JOHN KIM
Hydrant and Access approval Cleared 6/1/2020 JOHN CONNEALLY
Low Impact Development Cleared 11/13/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 11/24/2020 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 11/24/2020 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/7/2021 Partial Approval RONALD COWAN
Underground Mechanical 6/7/2021 Partial Approval RONALD COWAN
Footing/Foundation/Slab 6/9/2021 Approved RONALD COWAN
Deputy Other (see comments) 6/11/2021 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/25/2021 No Access for Inspection DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 6/30/2021 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 7/12/2021 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 7/12/2021 Partial Approval STEVEN BACK
HVAC-Rough 7/12/2021 Approved STEVEN BACK
PLUMBING-Rough 7/12/2021 Approved STEVEN BACK
Shower Pan 7/16/2021 Approved RONALD COWAN
Interior/Exterior Lathing 7/22/2021 Partial Approval RONALD COWAN
ELECTRICAL-Rough 8/25/2021 Approved PETER FOLLING
BUILDING-Rough-Frame 8/27/2021 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 8/27/2021 Approved RONALD COWAN
Green Building Rough 8/27/2021 Approved RONALD COWAN
Verify Sprinkler Sign Off 8/27/2021 Approved RONALD COWAN
Interior/Exterior Lathing 9/2/2021 Approved RONALD COWAN
Insulation 9/8/2021 Approved RONALD COWAN
Drywall Nailing 9/10/2021 Approved RONALD COWAN
Gas Test 12/10/2021 Approved MORRIS JACKSON
ELECTRICAL-Final 1/6/2022 Corrections Issued DAVID SANDOVAL
PLUMBING-Final 1/6/2022 Approved DAVID SANDOVAL
Service/Power Release 1/6/2022 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Final 1/14/2022 Approved DAVID SANDOVAL
HVAC-Final 1/14/2022 Approved DAVID SANDOVAL
Final 2/17/2022 OK to Issue CofO DAVID SANDOVAL
Green Building Final 2/18/2022 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 2/18/2022 SGSOV Approved DAVID SANDOVAL
Service/Power Release 2/18/2022 Approved DAVID SANDOVAL
Smoke Detectors 2/18/2022 Approved DAVID SANDOVAL