13663 W BRACKEN ST 91331
Certificate Information: 13663 W BRACKEN ST 91331
- Application / Permit
- 20010-20000-00952
- Plan Check / Job No.
- B20VN04810
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT (37'-6"X20'-0') ALL WORK PER WFPP
- Permit Issued
- Issued on 9/4/2020
- Issuing Office
- Current Status
- CofO Issued on 6/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2020 | APPLICANT |
| Green Plans Picked Up | 3/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 4/17/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 4/24/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 4/27/2020 | APPLICANT |
| Plan Check Approved | 9/4/2020 | MOHAMMAD ESMAILI |
| Issued | 9/4/2020 | APPLICANT |
| CofO in Progress | 6/8/2022 | JENNIFER RABUCHIN |
| CofO Issued | 6/16/2022 | MICHAEL SMITH |
| Permit Finaled | 6/16/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/12/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 5/13/2020 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 6/8/2020 | WALTER RAMIREZ |
| Hydrant and Access approval | Cleared | 6/15/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 7/31/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/6/2020 | GUILLERMO PETRA |
| Green Code | Cleared | 8/13/2020 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/21/2020 | Partial Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 9/28/2020 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 9/28/2020 | Partial Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 10/6/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 10/6/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 10/9/2020 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2020 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/3/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 12/3/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 12/8/2020 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/29/2020 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/29/2020 | Approved | GREGG CUMMINGS |
| Green Building Rough | 12/29/2020 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 12/29/2020 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 12/29/2020 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 12/29/2020 | Approved | GREGG CUMMINGS |
| Insulation | 1/13/2021 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 1/13/2021 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 1/25/2021 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 1/25/2021 | Partial Approval | GREGG CUMMINGS |
| Sewer | 3/5/2021 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 3/5/2021 | Partial Approval | GREGG CUMMINGS |
| Underground Mechanical | 3/25/2021 | Approved | GREGG CUMMINGS |
| Final | 5/7/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 5/7/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Final | 5/7/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 5/7/2021 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 5/7/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 5/7/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 5/13/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Service/Power Release | 5/13/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 9/28/2021 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 9/28/2021 | Approved | GREGG CUMMINGS |
| Green Building Final | 9/28/2021 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 9/28/2021 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 9/28/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 9/28/2021 | Approved | GREGG CUMMINGS |
| Pre-Inspection | 4/8/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 4/14/2022 | Corrections Issued | GREGG CUMMINGS |
| Service/Power Release | 4/14/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 5/12/2022 | Corrections Issued | DAVID MATSON |
| Service/Power Release | 5/12/2022 | Not Ready for Inspection | DAVID MATSON |
| ELECTRICAL-Final | 5/19/2022 | Approved | JENNIFER RABUCHIN |
| Final | 5/19/2022 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 5/19/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 5/19/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/19/2022 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 5/19/2022 | Approved | JENNIFER RABUCHIN |