9739 N SHOSHONE AVE 91325

Certificate Information: 9739 N SHOSHONE AVE 91325

Application / Permit
20010-20000-00949
Plan Check / Job No.
B20VN04788
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW IRR. SHAPED 22'x35' TWO-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 2/9/2021
Issuing Office
Valley
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2020 APPLICANT
Assigned to Plan Check Engineer 4/16/2020 SEAN SHAHMIRI
Corrections Issued 4/23/2020 SEAN SHAHMIRI
Green Plans Picked Up 4/27/2020 APPLICANT
Quality Review Completed 5/5/2020 OMID HEDAYAT
Building Plans Picked Up 5/8/2020 APPLICANT
Applicant returned to address corrections 12/28/2020 SEAN SHAHMIRI
Plan Check Approved 1/22/2021 SEAN SHAHMIRI
Applicant returned to address corrections 1/26/2021 SEAN SHAHMIRI
Issued 2/9/2021 APPLICANT
CofO in Progress 1/5/2024 JAVIER RAMOS JR
Permit Finaled 3/29/2024 DANIEL ORRANTE
CofO Issued 3/29/2024 DANIEL ORRANTE
Permit Finaled 3/29/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 5/5/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 5/7/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 5/7/2020 JOHN TRIANTAFYLLOS
Green Code Cleared 6/8/2020 AARON COSTA
ZI Cleared 6/22/2020 VINCENT QUITORIANO
Hydrant and Access approval Cleared 9/22/2020 KURT CORRAL
Low Impact Development Cleared 9/22/2020 JORGE MEJIA LEMUS
Construction near power lines Cleared 1/14/2021 RIDWAN HARDY
Roof/Waste drainage to street Cleared 1/19/2021 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 1/22/2021 SEAN SHAHMIRI

Contact Information

Contractor Owner-Builder       ,
Engineer Papazyan,, Andranik; Lic. No.: C56824 635 W COLORADO ST STE 104      GLENDALE, CA 91204

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/29/2021 No Access for Inspection MARK JOHNSON
PLUMBING-Rough 7/27/2021 Partial Approval MARK JOHNSON
Underground Mechanical 7/27/2021 Partial Approval MARK JOHNSON
Excavation/Setback/Form/Re-Bar 8/20/2021 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 3/8/2022 Partial Approval MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 5/18/2022 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 8/4/2022 Partial Approval JAVIER RAMOS JR
HVAC-Rough 8/4/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 8/24/2022 Partial Approval JAVIER RAMOS JR
Interior/Exterior Lathing 9/14/2022 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 10/3/2022 Corrections Issued DEANDRE HOFFMAN
PLUMBING-Rough 10/13/2022 Approved JAVIER RAMOS JR
Deputy Wood Construction 10/27/2022 Conditional Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 11/3/2022 Not Ready for Inspection JAVIER RAMOS JR
Insulation 11/3/2022 Corrections Issued JAVIER RAMOS JR
Drywall Nailing 11/28/2022 Not Ready for Inspection JAVIER RAMOS JR
Green Building Rough 11/28/2022 Approved JAVIER RAMOS JR
Shower Pan 12/6/2022 Not Ready for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 12/21/2022 Partial Approval JAVIER RAMOS JR
Drywall Nailing 12/21/2022 Approved JAVIER RAMOS JR
Insulation 12/21/2022 Approved JAVIER RAMOS JR
Shower Pan 12/21/2022 Approved JAVIER RAMOS JR
Sewer 2/7/2023 Approved JAVIER RAMOS JR
Underground Mechanical 2/7/2023 Partial Approval JAVIER RAMOS JR
Pre-Inspection 2/22/2023 Approved JAVIER RAMOS JR
Underground Mechanical 2/22/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 3/22/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 3/22/2023 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 3/22/2023 Approved CHRISTOPHE COCHRAN
Green Building Final 3/22/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 3/22/2023 SGSOV Not Ready CHRISTOPHE COCHRAN
Service/Power Release 3/22/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 3/22/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 3/22/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 5/8/2023 Approved JAVIER RAMOS JR
Final 5/8/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 5/8/2023 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 5/8/2023 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 5/8/2023 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 5/8/2023 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 5/8/2023 Approved JAVIER RAMOS JR
Final 12/8/2023 No Access for Inspection MISAEL ESPARZA
Green Building Final 12/8/2023 No Access for Inspection MISAEL ESPARZA
Service/Power Release 12/8/2023 No Access for Inspection MISAEL ESPARZA
Final 1/5/2024 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 1/5/2024 Approved JAVIER RAMOS JR
Service/Power Release 1/5/2024 Approved JAVIER RAMOS JR